Chwilio Deddfwriaeth

The Millbrook Gas Fired Generating Station Order 2019

 Help about what version

Pa Fersiwn

 Help about advanced features

Nodweddion Uwch

Changes over time for: The Millbrook Gas Fired Generating Station Order 2019 (without Schedules)

 Help about opening options

Alternative versions:

Changes to legislation:

There are currently no known outstanding effects for the The Millbrook Gas Fired Generating Station Order 2019. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

PART 1 E+W+SPRELIMINARY

Citation and commencementE+W+S

1.  This Order may be cited as the Millbrook Gas Fired Generating Station Order 2019 and comes into force on 3rd April 2019.

Commencement Information

I1Art. 1 in force at 3.4.2019, see art. 1

InterpretationE+W+S

2.—(1) In this Order—

the 1961 Act” means the Land Compensation Act 1961 M1;

the 1965 Act” means the Compulsory Purchase Act 1965 M2;

the 1980 Act” means the Highways Act 1980 M3;

the 1984 Act” means the Road Traffic Regulation Act 1984 M4;

the 1990 Act” means the Town and Country Planning Act 1990 M5;

the 1991 Act” means the New Roads and Street Works Act 1991 M6;

the 2008 Act” means the Planning Act 2008 M7;

the access road visibility splay” means the visibility splay shown hatched in purple on the access road visibility splay plan;

access road visibility splay plan” means the plan identified in Table 11 of Schedule 14 (documents and plans to be certified) to this Order and which is certified by the Secretary of State as the access road visibility splay plan for the purposes of this Order;

address” includes any number or address used for the purposes of electronic transmission;

apparatus” has the same meaning as in Part 3 (street works in England and Wales) of the 1991 Act;

authorised development” means the development described in Schedule 1 (authorised development) which is development within the meaning of section 32 (meaning of “development”) of the 2008 Act;

book of reference” means the document identified in Table 11 of Schedule 14 (documents and plans to be certified) to this Order and which is certified by the Secretary of State as the book of reference for the purposes of this Order;

building” includes any structure or erection or any part of a building, structure or erection;

carriageway” has the same meaning as in the 1980 Act;

commence” means beginning to carry out any material operation, as defined in section 155 (when development begins) of the 2008 Act, comprised in or carried out for the purposes of the authorised development other than operations consisting of environmental surveys and monitoring, investigations for the purpose of assessing ground conditions, receipt and erection of construction plant and equipment, erection of any temporary means of enclosure, the temporary display of site notices or advertisements and the words “commencement” and “commenced” and cognate expressions are to be construed accordingly;

date of final commissioning” means the date on which the authorised development commences operation by generating power on a commercial basis but excluding the generation of power during commissioning and testing;

design principles statement” means the document identified in Table 11 of Schedule 14 (documents and plans to be certified) to this Order and certified as such by the Secretary of State for the purposes of this Order;

electronic transmission” means a communication transmitted—

(a)

by means of an electronic communications network; or

(b)

by other means but while in electronic form;

the environmental statement” means the document identified in Table 11 of Schedule 14 (documents and plans to be certified) to this Order and which is certified as such by the Secretary of State for the purposes of this Order;

exhaust gas emission flue stack” means the exhaust gas emission flue stack including ancillary support structures, sound proof cladding, and emissions monitoring platforms;

footpath” and “footway” have the same meaning as in the 1980 Act;

gas turbine generator” means one gas turbine which drives a single electricity generator for the purposes of generating electricity including air inlet filter house, air inlet duct, exhaust diffuser, and auxiliaries such as lube oil system, air dryers, fuel gas filter package, instrument air system and compressor washing;

gross rated electrical output” means the aggregate of gross electrical power as measured at the terminals of the generator in accordance with standards agreed with the regulating authority under the Environmental Permitting (England and Wales) Regulations 2016;

highway” and “highway authority” have the same meaning as in the 1980 Act;

land plans” means the plans identified in Table 11 of Schedule 14 (documents and plans to be certified) to this Order and which are certified as the land plans by the Secretary of State for the purposes of this Order;

limits of deviation” means, in respect of numbered works 1A, 1B, 1C, 1D, 2A, 2B, 3A, 3B, 4A, 4B, 5, 6, 7, and 8 the outer limits of the corresponding numbered area shown on the works plans;

low level restoration scheme agricultural track” means an access track into Rookery South Pit from Green Lane which is in part existing and in part to be constructed in accordance with the planning permission for the low level restoration scheme of Rookery South Pit (reference number BC/CM/2000/8);

low level restoration scheme baseline works” means the works permitted by the planning permission for the low level restoration scheme of Rookery South Pit (reference number BC/CM/2000/8) and shown on the low level restoration scheme baseline works plan;

low level restoration scheme baseline works plan” means the plan identified in Table 11 of Schedule 14 (documents and plans to be certified) to this Order and which is certified as the low level restoration scheme baseline works plan by the Secretary of State for the purposes of this Order;

low level restoration scheme drainage strategy” means the drainage strategy to be approved pursuant to conditions 8 and 9 of the planning permission for the low level restoration scheme of Rookery South Pit (reference number BC/CM/2000/8);

low level restoration scheme secondary access track” means an access track into Rookery South Pit from Station Lane which is to be constructed in accordance with the planning permission for the low level restoration scheme of Rookery South Pit (reference number BC/CM/2000/8);

maintain” includes, to the extent assessed in the environmental statement, inspect, repair, adjust, alter, remove, refurbish, reconstruct, replace and improve any part, but not the whole of, the authorised development and “maintenance” and “maintaining” are to be construed accordingly;

Millbrook Power Limited” means Millbrook Power Limited (Company No. 08920458) whose registered office is at Drax Power Station, Drax, Selby, North Yorkshire YO58 8PH;

National Grid Electricity” means National Grid Electricity Transmission plc (Company Registration Number 02366977) whose registered office is at 1 to 3 Strand, London, WE2N 5EH;

National Grid Gas” means National Grid Gas plc (Company Registration Number 02006000) whose registered office is at 1 to 3 Strand, London WC2N 5EH;

Network Rail” means Network Rail Infrastructure Limited (Company Registration Number 02904587) whose registered office is at 1 Eversholt Street, London, NW1 2DN;

Order land” means the land which is required for, or is required to facilitate, or is incidental to, or is affected by, the authorised development shown on the land plans and described in the book of reference;

Order limits” means the limits shown on the works plans;

outline construction environment management plan” means the document identified in Table 11 of Schedule 14 (documents and plans to be certified) to this Order and which is certified as the outline construction environment management plan by the Secretary of State for the purposes of this Order;

outline construction traffic management measures” means the document identified in Table 11 of Schedule 14 (documents and plans to be certified) to this Order and which is certified as the outline construction traffic management measures by the Secretary of State for the purposes of this Order;

outline landscape and ecological mitigation and management strategy” means the document identified in Table 11 of Schedule 14 (documents and plans to be certified) to this Order and which is certified as the outline landscape and ecological mitigation and management strategy by the Secretary of State for the purposes of this Order;

outline lighting strategy” means the document identified in Table 11 of Schedule 14 (documents and plans to be certified) to this Order and which is certified as the outline lighting strategy by the Secretary of State for the purposes of this Order;

outline travel plan” means document identified in Table 11 of Schedule 14 (documents and plans to be certified) to this Order and which is certified as the outline travel plan by the Secretary of State for the purposes of this Order;

owner”, in relation to land, has the same meaning as in section 7 (interpretation) of the Acquisition of Land Act 1981 M8;

relevant planning authority” means Central Bedfordshire Council in relation to land in its area and Bedford Borough Council in relation to land in its area, and “the relevant planning authorities” means both of them;

requirements” means those matters set out in Schedule 2 to this Order;

rights of way, streets and access plan” means the plan identified in Table 11 of Schedule 14 (documents and plans to be certified) to this Order and which is certified as the rights of way, streets and access plan by the Secretary of State for the purposes of this Order;

Rookery South access road” means the access road comprising numbered work 5A pursuant to The Rookery South (Resource Recovery Facility) Order 2011 M9;

statutory undertaker” means any person falling within section 127(8) (statutory undertakers' land) of the 2008 Act;

street” means a street within the meaning of section 48 (streets, street works and undertakers) of the 1991 Act, together with land on the verge of a street or between two carriageways, and includes any footpath and “street” includes any part of a street;

street authority”, in relation to a street, has the same meaning as in Part 3 (street works in England and Wales) of the 1991 Act;

tribunal” means the Lands Chamber of the Upper Tribunal;

undertaker” means

(a)

in respect of the authorised development, Millbrook Power Limited;

(b)

in respect of numbered works 5, 6 and 7, Millbrook Power Limited and National Grid Electricity; and

(c)

in respect of numbered work 3A, Millbrook Power Limited and National Grid Gas;

watercourse” includes all rivers, streams, creeks, ditches, drains, canals, cuts, culverts, dykes, sluices, sewers and passages through which water flows except a public sewer or drain; and

works plans” means the plans identified in Table 11 of Schedule 14 (documents and plans to be certified) to this Order and which is certified as the works plans by the Secretary of State for the purposes of this Order.

(2) References in this Order to rights over land include references to rights to do or to place and maintain anything in, on or under land or in the air-space above its surface and references in this Order to the imposition of restrictions are references to restrictive covenants over land which interfere with the interests or rights of another and are for the benefit of land which is acquired under this Order or over which rights are created and acquired under this Order or is otherwise comprised in this Order.

(3) All distances, directions and lengths referred to in this Order are approximate and distances between lines and/or points on a numbered work comprised in the authorised development and shown on the works plan and rights of way, streets and access plan are to be taken to be measured along that work.

(4) All areas described in square metres in the book of reference are approximate.

(5) References in this Order to numbered works are references to the works comprising the authorised development as numbered in Schedule 1 and shown on the works plans and a reference to numbered work 1 means 1A to 1D (inclusive), a reference to numbered work 2 means 2A and 2B (inclusive), a reference to numbered work 3 means 3A and 3B (inclusive), and a reference to numbered work 4 means 4A and 4B (inclusive). References in this Order to points identified by letters or numbers are to be construed as references to points so lettered or numbered on the rights of way, streets and access plan.

(6) The expression “includes” is to be construed without limitation.

(7) References to any statutory body include that body's successor bodies as from time to time have jurisdiction over the authorised development.

Commencement Information

I2Art. 2 in force at 3.4.2019, see art. 1

Marginal Citations

M81981. c.67.

PART 2 E+W+SPRINCIPAL POWERS

Development consent etc. granted by the OrderE+W+S

3.—(1) Subject to the provisions of this Order and to the requirements in Schedule 2, the undertaker is granted development consent for the authorised development in Schedule 1 to be carried out within the Order limits.

(2) Subject to paragraph (3), each numbered work must be situated within the numbered area shown on the works plans.

(3) In constructing each numbered work, the undertaker may deviate within the corresponding numbered area(s) shown on the works plans up to the limits of deviation.

Commencement Information

I3Art. 3 in force at 3.4.2019, see art. 1

Maintenance of authorised developmentE+W+S

4.—(1) The undertaker may at any time maintain the authorised development except to the extent that this Order or an agreement made under this Order provides otherwise.

(2) This article only authorises the carrying out of maintenance works within the Order limits.

Commencement Information

I4Art. 4 in force at 3.4.2019, see art. 1

Operation of authorised developmentE+W+S

5.—(1) The undertaker is authorised to use and operate the generating station comprised in the authorised development.

(2) This article does not relieve the undertaker of any requirement to obtain any permit or licence or any obligation under any legislation that may be required to authorise the operation of the generating station.

Commencement Information

I5Art. 5 in force at 3.4.2019, see art. 1

Benefit of this OrderE+W+S

6.—(1) Subject to paragraph (2) and article 7 (consent to transfer benefit of the Order), the provisions of this Order have effect solely for the benefit of Millbrook Power Limited.

(2) Paragraph (1) does not apply to—

(a)numbered works 5, 6 and 7 for which development consent is granted by this Order for the benefit of Millbrook Power Limited and National Grid Electricity; and

(b)numbered works 3A for which development consent is granted by this Order for the benefit of Millbrook Power Limited and National Grid Gas.

Commencement Information

I6Art. 6 in force at 3.4.2019, see art. 1

Consent to transfer benefit of the OrderE+W+S

7.—(1) Subject to paragraph (4), the undertaker may—

(a)transfer to another person (“the transferee”) any or all of the benefit of the provisions of this Order (including any of the numbered works) and such related statutory rights as may be agreed in writing between the undertaker and the transferee; or

(b)grant to another person (“the lessee”) for a period agreed between the undertaker and the lessee any or all of the benefit of the provisions of this Order (including any of the numbered works) and such related statutory rights as may be so agreed.

(2) Where a transfer or grant has been made in accordance with paragraph (1) references in this Order to the undertaker include references to the transferee or the lessee.

(3) The exercise by a person of any benefits or rights conferred in accordance with any transfer or grant under paragraph (1) is subject to the same restrictions, liabilities and obligations as would apply under this Order if those benefits or rights were exercised by the undertaker.

(4) The consent of the Secretary of State is required for the exercise of the powers of paragraph (1) except where—

(a)the transferee or lessee is the holder of a licence under section 6 (licences authorising supply, etc) of the Electricity Act 1989 M10 or section 7 (licensing of public gas transporters) of the Gas Act 1986 M11; or

(b)the time limits for all claims for compensation in respect of the acquisition of land or effects upon land under this Order have elapsed and—

(i)no such claims have been made;

(ii)any such claims that have been made have all been compromised or withdrawn;

(iii)compensation has been paid in final settlement of all such claims;

(iv)payment of compensation into court in lieu of settlement of all such claims has taken place; or

(v)it has been determined by a tribunal or court of competent jurisdiction in respect of all claims that no compensation is payable.

(5) Where the consent of the Secretary of State is not required under paragraph (4), the undertaker must notify the Secretary of State in writing before transferring or granting a benefit referred to in paragraph (1).

(6) The notification referred to in paragraph (5) must state —

(a)the name and contact details of the person to whom the benefit of the powers will be transferred or granted;

(b)subject to paragraph (7), the date on which the transfer will take effect;

(c)the powers to be transferred or granted;

(d)pursuant to paragraph (3), the restrictions, liabilities and obligations that will apply to the person exercising the powers transferred or granted; and

(e)where relevant, a plan showing the works or areas to which the transfer or grant relates.

(7) The date specified under paragraph (6)(b) must not be earlier than the expiry of five working days from the date of the receipt of the notice.

(8) The notice given under paragraph (6) must be signed by the undertaker and the person to whom the benefit of the powers will be transferred or granted as specified in that notice.

Commencement Information

I7Art. 7 in force at 3.4.2019, see art. 1

Marginal Citations

M101989 c.29. Section 6 was amended by section 30 of the Utilities Act 2000 (c.27), and section 6(10) amended by section 89(3) of the Energy Act 2004 (c.20). There are other amendments to this section that are not relevant to this Order.

M111986 c.44. Section 7 was amended by section 5 of the Gas Act 1995 (c.45) and section 76(2) of the Utilities Act 2000 (c.27). There are other amendments to the section that are not relevant to this Order.

PART 3 E+W+SSTREETS

Power to alter layout etc. of streetsE+W+S

8.—(1) The undertaker may for the purposes of the authorised development alter the layout of or carry out any works in the street in the case of permanent works as specified in column (2) of Part 1(permanent alteration of layout) of Schedule 3 in the manner specified in relation to that street in column (3) and in the case of temporary works as specified in column (2) of Part 2 (temporary alteration of layout) of Schedule 3 in the manner specified in relation to that street in column (3).

(2) Without prejudice to the specific powers conferred by paragraph (1) but subject to paragraphs (3) and (4), the undertaker may, for the purposes of constructing, operating and maintaining the authorised development alter the layout of any street within the Order limits and, without limitation on the scope of this paragraph, the undertaker may—

(a)alter the level or increase the width of any kerb, footway, cycle track or verge;

(b)make and maintain passing place(s).

(3) The undertaker must restore any street that has been temporarily altered under this article to the reasonable satisfaction of the street authority.

(4) The powers conferred by paragraph (2) must not be exercised without the consent of the street authority.

(5) Paragraphs (3), and (4) do not apply where the undertaker is the street authority for a street in which the works are being carried out.

Commencement Information

I8Art. 8 in force at 3.4.2019, see art. 1

Street worksE+W+S

9.—(1) The undertaker may, for the purposes of the authorised development, enter on so much of any of the streets specified in Schedule 4 (streets subject to street works) as is within the Order limits and may—

(a)break up or open the street, or any sewer, drain or tunnel under it;

(b)drill, tunnel or bore under the street;

(c)place and keep apparatus in the street;

(d)maintain apparatus in the street or change its position; and

(e)execute any works required for or incidental to any works referred to in sub-paragraphs (a), (b), (c) and (d).

(2) The authority given by paragraph (1) is a statutory right for the purposes of sections 48(3) (streets, street works and undertakers) and 51(1) (prohibition of unauthorised street works) of the 1991 Act.

(3) Where the undertaker is not the street authority, the provisions of sections 54 to 106 of the 1991 Act apply to any street works carried out under paragraph (1).

Commencement Information

I9Art. 9 in force at 3.4.2019, see art. 1

Construction and maintenance of new or altered means of accessE+W+S

10.—(1) Those parts of each means of access specified in Part 1 of Schedule 5 (access) to be constructed under this Order must be completed to the reasonable satisfaction of the highway authority and must be maintained by and at the expense of the undertaker for a period of 12 months from completion and from the expiry of that period by and at the expense of the highway authority.

(2) Those parts of each means of access specified in Part 2 of Schedule 5 to be constructed under this Order and which are not intended to be a public highway must be completed to the reasonable satisfaction of the street authority and must be maintained by and at the expense of the undertaker for a period of 12 months from completion and from the expiry of that period by and at the expense of the street authority.

(3) Those restoration works carried out pursuant to article 8(3) (power to alter layout, etc., of streets) identified in Part 3 of Schedule 5 which are not intended to be a public highway must be completed to the reasonable satisfaction of the street authority and must be maintained by and at the expense of the street authority.

(4) In any action against the undertaker in respect of loss or damage resulting from any failure by it to maintain a street under this article, it is a defence (without prejudice to any other defence or the application of the law relating to contributory negligence) to prove that the undertaker had taken such care as in all the circumstances was reasonably required to secure that the part of the street to which the action relates was not dangerous to traffic.

(5) For the purposes of a defence under paragraph (4), a court is, in particular, to have regard to the following matters—

(a)the character of the street including the traffic which was reasonably to be expected to use it;

(b)the standard of maintenance appropriate for a street of that character and used by such traffic;

(c)the state of repair in which a reasonable person would have expected to find the street;

(d)whether the undertaker knew, or could reasonably have been expected to know, that the condition of the part of the street to which the action relates was likely to cause danger to users of the street; and

(e)where the undertaker could not reasonably have been expected to repair that part of the street before the cause of action arose, what warning notices of its condition had been displayed.

but for the purposes of such a defence it is not relevant that the undertaker had arranged for a competent person to carry out or supervise the maintenance of that part of the street to which the action relates unless it is also proved that the undertaker had given that person proper instructions with regard to the maintenance of the street and that those instructions had been carried out.

Commencement Information

I10Art. 10 in force at 3.4.2019, see art. 1

Temporary prohibition or restriction of use of streetsE+W+S

11.—(1) The undertaker, during and for the purposes of carrying out the authorised development, may temporarily alter, divert, prohibit the use of or restrict the use of any street and may for any reasonable time—

(a)divert the traffic from the street; and

(b)subject to paragraph (3), prevent all persons from passing along the street.

(2) Without prejudice to the scope of paragraph (1), the undertaker may use any street where the use has been prohibited or restricted under the powers conferred by this article and within the Order limits as a temporary working site.

(3) The undertaker must provide reasonable access for non-motorised users (including pedestrians) going to or from premises abutting a street affected by the temporary alteration, diversion, prohibition or restriction of a street under this article if there would otherwise be no such access.

(4) Without prejudice to the generality of paragraph (1), the undertaker may temporarily alter, divert, prohibit the use of or restrict the use of the streets specified in columns (1) and (2) of Schedule 6 (temporary prohibition or restriction of the use of streets) to the extent specified in column (3) of that Schedule.

(5) The undertaker must not temporarily alter, divert, prohibit the use of or restrict the use of—

(a)any street specified in paragraph (4) without first consulting the street authority; and

(b)any other street without the consent of the street authority which may attach reasonable conditions to any consent.

(6) Any person who suffers loss by the suspension or extinguishment of any private right of way under this article shall be entitled to compensation to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

Commencement Information

I11Art. 11 in force at 3.4.2019, see art. 1

Stopping up of StreetsE+W+S

12.—(1) Subject to the provisions of this article, the undertaker may, in connection with the carrying out of the authorised development, stop up each of the streets specified in columns (1) and (2) of Schedule 7 (streets to be stopped up for which a substitute is to be provided) to the extent specified, by reference to the letters and numbers shown on the rights of way, streets and access plan, in column (3) of those Parts of that Schedule.

(2) No street specified in columns (1) and (2) of Schedule 7 shall be wholly or partly stopped up under this article unless-

(a)the new street to be substituted for it, which is specified in column (4) of that Part of that Schedule, has been completed to the reasonable satisfaction of the street authority and is open for use; or

(b)a temporary alternative route for the passage of such traffic as could have used the street to be stopped up is first provided and subsequently maintained by the undertaker, to the reasonable satisfaction of the street authority, between the commencement and termination points for the stopping up of the street until the completion and opening of the new street in accordance with sub-paragraph (a).

(3) Where a street has been stopped up under this article—

(a)all rights of way over or along the street so stopped up shall be extinguished; and

(b)the undertaker may appropriate and use for the purposes of the authorised development so much of the site of the street as is bounded on both sides by land owned by the undertaker.

(4) Any person who suffers loss by the suspension or extinguishment of any private right of way under this article shall be entitled to compensation to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(5) This article is subject to article 30 (apparatus and rights of statutory undertakers in streets).

Commencement Information

I12Art. 12 in force at 3.4.2019, see art. 1

Access to worksE+W+S

13.  The undertaker may, for the purposes of the authorised development—

(a)form and layout the permanent means of access, or improve existing means of access, in the locations specified in Part 1 of Schedule 3 (streets subject to permanent and temporary alteration of layout);

(b)form and layout the temporary means of access in the locations specified in Part 2 of Schedule 3; and

(c)with the approval of the relevant planning authorities after consultation with the highway authority, form and lay out such other means of access or improve the existing means of access, at such locations within the Order limits as the undertaker reasonably requires for the purposes of the authorised development.

Commencement Information

I13Art. 13 in force at 3.4.2019, see art. 1

Agreements with street authoritiesE+W+S

14.—(1) A street authority and the undertaker may enter into agreements with respect to—

(a)the construction of any new street including any structure carrying the street;

(b)the strengthening, improvement, repair or reconstruction of any street under the powers conferred by this Order;

(c)the maintenance of the structure of any bridge or tunnel carrying a street;

(d)any alteration, diversion, prohibition or restriction in the use of a street authorised by this Order; or

(e)the carrying out in the street of any of the works referred to in article 10(1) (construction and maintenance of new or altered means of access).

(2) Such an agreement may, without prejudice to the generality of paragraph (1)—

(a)make provision for the street authority to carry out any function under this Order which relates to the street in question;

(b)include an agreement between the undertaker and street authority specifying a reasonable time for the completion of the works; and

(c)contain such terms as to payment and otherwise as the parties consider appropriate.

Commencement Information

I14Art. 14 in force at 3.4.2019, see art. 1

Traffic RegulationE+W+S

15.—(1) Subject to the provisions of this article and the consent of the traffic authority in whose area the road concerned is situated, the undertaker may, in so far as may be expedient or necessary for the purposes of or in connection with the construction of the authorised development or any other development necessary for the authorised development that takes place within the Order limits, at any time prior to when the authorised development first becomes operational—

(a)permit, prohibit or restrict the stopping, parking, waiting, loading or unloading of vehicles on any road; and

(b)make provision as to the direction or priority of vehicular traffic on any road,

either at all times or at times, on days or during such periods as may be specified by the undertaker.

(2) The undertaker must not exercise the powers under paragraph (1) of this article unless it has—

(a)given not less than 4 weeks' notice in writing of its intention so to do to the traffic authority in whose area the road is situated; and

(b)advertised its intention in such manner as the traffic authority may specify in writing within 7 days of its receipt of notice of the undertaker's intention in the case of sub-paragraph (a).

(3) Any prohibition, restriction or other provision made by the undertaker under article 11 (temporary prohibition or restriction of use of streets) or paragraph (1) of this article has effect as if duly made by, as the case may be—

(a)the traffic authority in whose area the road is situated as a traffic regulation order under the 1984 Act; or

(b)the local authority in whose area the road is situated as an order under section 32 (power of local authorities to provide parking places) of the 1984 Act,

and the instrument by which it is effected is deemed to be a traffic order for the purposes of Schedule 7 (road traffic contraventions subject to civil enforcement) to the Traffic Management Act 2004 M12.

(4) In this article—

(a)subject to sub-paragraph (b) expressions used in this article and in the 1984 Act have the same meaning; and

(b)a “road” means a road that is a public highway maintained by and at the expense of the traffic authority.

Commencement Information

I15Art. 15 in force at 3.4.2019, see art. 1

Marginal Citations

M122004 c.18. There are amendments to this Act not relevant to this Order.

PART 4 E+W+SSUPPLEMENTAL POWERS

Discharge of waterE+W+S

16.—(1) The undertaker may use any watercourse or any public sewer or drain for the drainage of water in connection with the carrying out or maintenance of the authorised development and for that purpose may lay down, take up and alter pipes and may, on any land within the Order limits, make openings into, and connections with, the watercourse, public sewer or drain.

(2) Any dispute arising from the making of connections to or the use of a public sewer or drain by the undertaker pursuant to paragraph (1) must be determined as if it were a dispute under section 106 (right to communicate with public sewers) of the Water Industry Act 1991 M13.

(3) The undertaker must not discharge any water into any watercourse, public sewer or drain except with the consent of the person to whom it belongs; and such consent may be given subject to such terms and conditions as that person may reasonably impose, but must not be unreasonably withheld.

(4) The undertaker must not make any opening into any public sewer or drain except—

(a)in accordance with plans approved by the person to whom the sewer or drain belongs but approval must not be unreasonably withheld; and

(b)where that person has been given the opportunity to supervise the making of the opening.

(5) The undertaker must take such steps as are reasonably practicable to secure that any water discharged into a watercourse or public sewer or drain pursuant to this article is as free as may be practicable from gravel, soil or other solid substance, oil or matter in suspension.

(6) This article does not authorise any water discharge activities or groundwater activities for which an environmental permit would be required pursuant to regulation 12(1) (requirement for an environmental permit) of the Environmental Permitting (England and Wales) Regulations 2016 M14.

(7) In this article—

(a)public sewer or drain” means a sewer or drain which belongs to the Homes and Communities Agency, the Environment Agency, a harbour authority within the meaning of section 57 (interpretation) of the Harbours Act 1964 M15, an internal drainage board, a joint planning board, a local authority, a National Park Authority, a sewerage undertaker or an urban development corporation; and

(b)other expressions, excluding watercourse, used both in this article and in the Water Resources Act 1991 M16 have the same meaning as in that Act.

Commencement Information

I16Art. 16 in force at 3.4.2019, see art. 1

Marginal Citations

M131991 c.56. Section 106 was amended by sections 43(2) and 35(8)(a) and paragraph 1 of Schedule 2 to the Competition and Service (Utilities) Act 1992 (c.43) and sections 99(2), (4), (5)(a), (5)(b),(5)(c) and 36(2) of the Water Act 2003 (c.37).

M151964 c.40. Paragraph 9B was inserted into Schedule 2 paragraph 9 of Schedule 3 of by the Transport and Works Act 1992 (c.42). There are other amendments to the 1964 Act that are not relevant to this Order.

Authority to survey and investigate the landE+W+S

17.—(1) The undertaker may for the purposes of this Order enter on any land shown within the Order limits or on any land which may be affected by the authorised development and—

(a)survey or investigate the land;

(b)without prejudice to the generality of sub-paragraph (a), make trial holes in such positions on the land as the undertaker thinks fit to investigate the nature of the surface layer and subsoil and remove soil samples;

(c)without prejudice to the generality of sub-paragraph (a), carry out ecological or archaeological investigations on such land; and

(d)place on, leave on and remove from the land apparatus for use in connection with the survey and investigation of land and making of trial holes.

(2) No land may be entered or equipment placed or left on or removed from the land under paragraph (1) unless at least 14 days' notice has been served on every owner and occupier of the land.

(3) Any person entering land under this article on behalf of the undertaker—

(a)must, if so required on entering the land, produce written evidence of their authority to do so; and

(b)may take onto the land such vehicles and equipment as are necessary to carry out the survey or investigation or to make the trial holes.

(4) No trial holes are to be made under this article—

(a)in land located within the highway boundary without the consent of the highway authority; or

(b)in a private street without the consent of the street authority,

but such consent must not be unreasonably withheld.

(5) The undertaker must compensate the owners and occupiers of the land for any loss or damage arising by reason of the exercise of the authority conferred by this article, such compensation to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(6) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the entry onto, or possession of land under this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.

Commencement Information

I17Art. 17 in force at 3.4.2019, see art. 1

PART 5 E+W+SPOWERS OF ACQUISITION

Compulsory acquisition of landE+W+S

18.—(1) The undertaker may acquire compulsorily so much of the Order land as is required for the authorised development or to facilitate it, or as is incidental to it.

(2) This article is subject to article 21 (compulsory acquisition of rights etc.), article 24 (acquisition of subsoil only) and article 27 (temporary use of land for carrying out the authorised development).

Commencement Information

I18Art. 18 in force at 3.4.2019, see art. 1

Statutory authority to override easements and other rightsE+W+S

19.—(1) The carrying out or use of the authorised development and the doing of anything else authorised by this Order is authorised for the purpose specified in section 158(2) (nuisance: statutory authority) of the 2008 Act, notwithstanding that it involves—

(a)an interference with an interest or right to which this article applies; or

(b)a breach of a restriction as to use of land arising by virtue of contract.

(2) The undertaker must pay compensation to any person whose land is injuriously affected by—

(a)an interference with an interest or right to which this article applies; or

(b)a breach of a restriction as to use of land arising by virtue of contract,

caused by the carrying out or use of the authorised development and the operation of section 158 (benefit of order granting development consent) of the 2008 Act.

(3) The interests and rights to which this article applies are any easement, liberty, privilege, right or advantage annexed to land and adversely affecting other land, including any natural right to support.

(4) Subsection (2) of section 10 (further provision as to compensation for injurious affection) of the 1965 Act applies to paragraph (2) by virtue of section 152(5) (compensation in case where no right to claim in nuisance) of the 2008 Act.

(5) Any rule or principle applied to the construction of section 10 of the 1965 Act must be applied to the construction of paragraph (2) (with any necessary modifications).

Commencement Information

I19Art. 19 in force at 3.4.2019, see art. 1

Time limit for exercise of authority to acquire land compulsorilyE+W+S

20.—(1) After the end of the period of 5 years beginning on the day on which this Order is made—

(a)no notice to treat is to be served under Part 1 of the 1965 Act; and

(b)no declaration is to be executed under section 4 of the Compulsory Purchase (Vesting Declarations) Act 1981 M17 (execution of declaration) as applied by article 23 (application of the Compulsory Purchase (Vesting Declarations) Act 1981).

(2) The authority conferred by article 27 (temporary use of land for carrying out the authorised development) must cease at the end of the period referred to in paragraph (1), save that nothing in this paragraph prevents the undertaker remaining in possession of land after the end of that period, if the land was entered and possession was taken before the end of that period.

Commencement Information

I20Art. 20 in force at 3.4.2019, see art. 1

Marginal Citations

Compulsory acquisition of rights etc.E+W+S

21.—(1) Subject to paragraph (2), the undertaker may acquire such rights over the Order land or impose restrictive covenants affecting the land as may be required for any purpose for which that land may be acquired under article 18 (compulsory acquisition of land), by creating them as well as acquiring rights already in existence.

(2) In respect of such parts of the Order land that are shown edged red and shaded blue on the land plans, the undertaker may acquire compulsorily the existing rights over land and create and acquire compulsorily the new rights and impose the restrictions described in the book of reference and shown on the land plans.

(3) Subject to section 8 M18 (provisions as to divided land) and Schedule 2A (counter-notice requiring purchase of land) of the 1965 Act (as substituted by paragraph 5(8) of Schedule 8 to this Order (modification of compensation and compulsory purchase enactments for the creation of new rights and imposition of new restrictions), where the undertaker creates or acquires a right over land or imposes a restriction under paragraph (1) or (2), the undertaker is not to be required to acquire a greater interest in that land.

(4) Schedule 8 is to have effect for the purpose of modifying the enactments relating to compensation and the provisions of the 1965 Act in their application in relation to the compulsory acquisition under this article of a right over land by the creation of a new right or the imposition of a restriction.

(5) In any case where the acquisition of new rights or the imposition of a restriction under paragraph (1) or (2) is required for the purposes of diverting, replacing or protecting the apparatus of a statutory undertaker, the undertaker may, with the consent of the Secretary of State, transfer the power to create and acquire such rights or impose such restrictions to the statutory undertaker in question.

(6) The exercise by a statutory undertaker of any power in accordance with a transfer under paragraph (5) is subject to the same restrictions, liabilities and obligations as would apply under this Order if that power were exercised by the undertaker.

(7) Subject to the modifications set out in Schedule 8 the enactments for the time being in force with respect to compensation for the compulsory purchase of land are to apply in the case of a compulsory acquisition under this Order in respect of a right by the creation of a new right or imposition of a restriction as they apply to the compulsory purchase of land and interests in land.

Commencement Information

I21Art. 21 in force at 3.4.2019, see art. 1

Marginal Citations

M18Section 8 was amended by section 199 of and Schedule 17 to the Housing and Planning Act 2016 (c.22). Section 8 is modified by section 9 of and Schedule 3 (as amended by section 108 of the Utilities Act 2000 (c.27) to the Gas Act 1986 (c.44), section 151 of and Schedule 18 to the Water Act 1989 (c.15), section 10 of and Schedule 3 to the Electricity Act 1989 (c.29), Schedules 9 and 11 to the Water Industry Act 1991 (c.56) and Schedules 18 and 19 to the Water Resources Act 1991 (c.57). There were other amendments, and are other modifications, to that section that are not relevant to this Order.

Private rightsE+W+S

22.—(1) Subject to the provisions of this article, all private rights and restrictions over land subject to compulsory acquisition under this Order are extinguished—

(a)as from the date of acquisition of the land by the undertaker, whether compulsorily or by agreement; or

(b)on the date of entry on the land by the undertaker under section 11(1) M19 (powers of entry) of the 1965 Act,

whichever is the earliest.

(2) Subject to the provisions of this article, all private rights and restrictions over land subject to the compulsory acquisition of rights or imposition of restrictions under this Order are suspended and unenforceable or, where so notified by the undertaker, extinguished in so far as in either case their continuance would be inconsistent with the exercise of the right—

(a)as from the date of acquisition of the right by the undertaker, whether compulsorily or by agreement; or

(b)on the date of entry on the land by the undertaker under section 11(1) (powers of entry) of the 1965 Act in pursuance of the right,

whichever is the earliest.

(3) Subject to the provisions of this article, and where so notified by the undertaker, all private rights and restrictions over land owned by the undertaker are extinguished on commencement of any activity authorised by this Order which interferes with or breaches such rights.

(4) Subject to the provisions of this article, all private rights or restrictions over land of which the undertaker takes temporary possession under this Order are suspended and unenforceable for as long as the undertaker remains in lawful possession of the land and so far as their continuance would be inconsistent with the exercise of the temporary possession of that land.

(5) Any person who suffers loss by the extinguishment or suspension of any private right or restriction under this Order is entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

(6) This article does not apply in relation to any right to which section 138 (extinguishment of rights, and removal of apparatus, of statutory undertakers etc.) of the 2008 Act or article 29 (statutory undertakers) applies.

(7) Paragraphs (1) to (3) have effect subject to—

(a)any notice given by the undertaker before—

(i)the completion of the acquisition of the land or the creation and acquisition of rights or the imposition of restrictions over land,

(ii)the undertaker's appropriation of it,

(iii)the undertaker's entry onto it, or

(iv)the undertaker's taking temporary possession of it,

that any or all of those paragraphs are not to apply to any right specified in the notice; and

(b)any agreement made at any time between the undertaker and the person in or to whom the right or restriction in question is vested, belongs or benefits.

(8) If any such agreement as is referred to in paragraph (7)(b)—

(a)is made with a person in or to whom the right is vested or belongs; and

(b)is expressed to have effect also for the benefit of those deriving title from or under that person,

it is effective in respect of the persons so deriving title, whether the title was derived before or after the making of the agreement.

Commencement Information

I22Art. 22 in force at 3.4.2019, see art. 1

Marginal Citations

M19Section 11(1) was amended by section 34 of, and Schedule 4 to, the Acquisition of Land Act 1981 (c. 67) and sections 186 and 187 of, and paragraph 6 of Schedule 14 and paragraph 3 of Schedule 16 to, the Housing and Planning Act 2016 (c. 22). There are other amendments to the section that are not relevant to this Order.

Application of the Compulsory Purchase (Vesting Declarations) Act 1981E+W+S

23.—(1) The Compulsory Purchase (Vesting Declarations) Act 1981 applies as if this Order were a compulsory purchase order.

(2) The Compulsory Purchase (Vesting Declarations) Act 1981, as applied by paragraph (1), has effect with the following modifications.

(3) In section 1 (application of act) for subsection 2 there is substituted—

(2) This section applies to any Minister, any local or other public authority or any other body or person authorised to acquire land by means of a compulsory purchase order.

(4) In section 5(2) (earliest date for execution of declaration), omit the words from “, and this subsection” to the end.

(5) Section 5A (time limit for general vesting declaration) is omitted.

(6) In section 5B (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application to High Court in respect of compulsory purchase order), the three year period mentioned in section 5A” substitute “ section 118 of the 2008 Act (legal challenges relating to applications for orders granting development consent), the five year period mentioned in article 20 (time limit for exercise of authority to acquire land compulsorily) of the Millbrook Gas Fired Generating Station Order 2019 ”.

(7) In section 6 (notices after execution of declaration), in subsection (1)(b) for “section 15 of, or paragraph 6 of Schedule 1 to, the Acquisition of Land Act 1981” substitute “ section 134 (notice of authorisation of compulsory acquisition) of the Planning Act 2008 ”.

(8) In section 7 (constructive notice to treat), in subsection (1)(a), omit the words “(as modified by section 4 of the Acquisition of Land Act 1981)”.

(9) In Schedule A1 (counter-notice requiring purchase of land not in general vesting declaration), for paragraph 1(2) substitute—

(2) But see article 24(3) (acquisition of subsoil only) of the Millbrook Gas Fired Generating Station Order 2019, which excludes the acquisition of subsoil only from this Schedule.

(10) References to the 1965 Act in the Compulsory Purchase (Vesting Declarations) Act 1981 must be construed as references to that Act as applied by section 125 of the 2008 Act (and as modified by article 25 (modification of Part 1 of the Compulsory Purchase Act 1965) to the compulsory acquisition of land under this Order.

Commencement Information

I23Art. 23 in force at 3.4.2019, see art. 1

Acquisition of subsoil onlyE+W+S

24.—(1) The undertaker may acquire compulsorily so much of, or such rights in, the subsoil of the land referred to in paragraph (1) of article 18 (compulsory acquisition of land) and paragraphs (1) and 21(2) of article 21 (compulsory acquisition of rights etc.) as may be required for any purpose for which that land or rights or restrictions over that land may be created and acquired or imposed under that provision instead of acquiring the whole of the land.

(2) Where the undertaker acquires any part of, or rights in, the subsoil of land under paragraph (1), the undertaker is not to be required to acquire an interest in any other part of the land.

(3) The following do not apply in connection with the exercise of the power under paragraph (1) in relation to subsoil only—

(a)Schedule 2A (counter-notice requiring purchase of land not in notice to treat) to the 1965 Act;

(b)Schedule A1 (counter-notice requiring purchase of land not in general vesting declaration) to the Compulsory Purchase (Vesting Declarations) Act 1981; and

(c)section 153(4A) (blighted land: proposed acquisition of part interest; material detriment test) of the 1990 Act.

(4) Paragraphs (2) and (3) are to be disregarded where the undertaker acquires a cellar, vault, arch or other construction forming part of a house, building or manufactory.

Commencement Information

I24Art. 24 in force at 3.4.2019, see art. 1

Modification of Part 1 of the Compulsory Purchase Act 1965E+W+S

25.—(1) Part 1 of the 1965 Act, as applied to this Order by section 125 (application of compulsory acquisition provisions) of the 2008 Act, is modified as follows.

(2) In section 4A(1) (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application to High Court in respect of compulsory purchase order), the three year period mentioned in section 4” substitute “ section 118 of the Planning Act 2008 (legal challenges relating to applications for orders granting development consent), the five year period mentioned in article 20 (time limit for exercise of authority to acquire land compulsorily) of the Millbrook Gas Fired Generating Station Order 2019 ”.

(3) In section 11A (powers of entry: further notice of entry)—

(a)in section (1)(a), after “land” insert “ under that provision ”;

(b)in subsection (2), after “land” insert “ under that provision ”.

(4) In section 22(2) (interests omitted from purchase), for “section 4 of this Act” substitute “ article 20 (time limit for exercise of authority to acquire land compulsorily) of the Millbrook Gas Fired Generating Station Order 2019 ”.

(5) In Schedule 2A (counter-notice requiring purchase of land not in notice to treat)—

(a)for paragraphs 1(2) and 14(2) substitute—

(2) But see article 24(3) (acquisition of subsoil only) of the Millbrook Gas Fired Generating Station Order 2019, which excludes the acquisition of subsoil only from this Schedule; and

(b)after paragraph 29, insert—

PART 4

INTERPRETATION

30.  In this Schedule, references to entering on and taking possession of land do not include doing so under article 27 (temporary use of land for carrying out the authorised development) or article 28 (temporary use of land for maintaining the authorised development) of the Millbrook Gas Fired Generating Station Order 2019.

Commencement Information

I25Art. 25 in force at 3.4.2019, see art. 1

Rights under or over streetsE+W+S

26.—(1) The undertaker may enter upon and appropriate so much of the subsoil of, or air-space over, any street within the Order limits as may be required for the purposes of the authorised development and may use the subsoil or air-space for those purposes or any other purpose ancillary to the authorised development.

(2) Subject to paragraph (3), the undertaker may exercise any power conferred by paragraph (1) in relation to a street without being required to acquire any part of the street or any easement or right in the street.

(3) Paragraph (2) does not apply in relation to—

(a)any subway or underground building; or

(b)any cellar, vault, arch or other construction in, on or under a street which forms part of a building fronting onto the street.

(4) Subject to paragraph (5), any person who is an owner or occupier of land in respect of which the power of appropriation conferred by paragraph (1) is exercised without the undertaker acquiring any part of that person's interest in the land, and who suffers loss by the exercise of that power, is to be entitled to compensation to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(5) Compensation is not payable under paragraph (4) to any person who is an undertaker to whom section 85 (sharing cost of necessary measures) of the 1991 Act applies in respect of measures of which the allowable costs are to be borne in accordance with that section.

Commencement Information

I26Art. 26 in force at 3.4.2019, see art. 1

Temporary use of land for carrying out the authorised developmentE+W+S

27.—(1) The undertaker may, in connection with the carrying out of the authorised development—

(a)enter on and take possession of—

(i)so much of the land specified in columns (1) and (2) of Schedule 9 (land of which temporary possession may be taken) for the purpose specified in relation to that land in column (3) of that Schedule relating to the part of the authorised development specified in column (4) of that Schedule;

(ii)any other Order land in respect of which no notice of entry has been served under section 11 (powers of entry) of the 1965 Act and no declaration has been made under section 4 (execution of declaration) of the Compulsory Purchase (Vesting Declarations) Act 1981;

(b)remove any buildings, fences, debris and vegetation from that land;

(c)construct temporary works (including the provision of means of access) and buildings on that land; and

(d)construct any works specified in relation to that land in column (3) of Schedule 9, or any other mitigation works.

(2) Not less than 14 days before entering on and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land.

(3) The undertaker may not, without the agreement of the owners of the land, remain in possession of any land under this article—

(a)in the case of land specified in paragraph (1)(a)(i) after the end of the period of one year beginning with the date of final commissioning of the authorised development; or

(b)in the case of land referred to in paragraph (1)(a)(ii) after the end of the period of one year beginning with the date of final commissioning of the authorised development unless the undertaker has, before the end of that period, served notice of entry under section 11 (powers of entry) of the 1965 Act or made a declaration under section 4 (execution of declaration) of the Compulsory Purchase (Vesting Declarations) Act 1981 or has otherwise acquired the land subject to temporary possession.

(4) Unless the undertaker has served notice of entry under section 11 (powers of entry) of the 1965 Act or made a declaration under section 4 (execution of declaration) of the Compulsory Purchase (Vesting Declarations) Act 1981 or has otherwise acquired the land subject to temporary possession, the undertaker must, before giving up possession of land of which temporary possession has been taken under this article, remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but the undertaker is not to be required to replace a building or any debris removed under this article.

(5) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.

(6) Any dispute as to a person's entitlement to compensation under paragraph (5), or as to the amount of the compensation, is to be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(7) Nothing in this article affects any liability to pay compensation under section 10(2) (further provisions as to compensation for injurious affection) of the 1965 Act or under any other enactment in respect of loss or damage arising from the carrying out of the authorised development, other than loss or damage for which compensation is payable under paragraph (5).

(8) The undertaker may not compulsorily acquire under this Order the land referred to in paragraph (1)(a)(i).

(9) Nothing in this article precludes the undertaker from—

(a)creating and acquiring new rights or imposing restrictions over any part of the Order land identified in part 1 of the book of reference under article 21 (compulsory acquisition of rights etc.); or

(b)acquiring any right in the subsoil of any part of the Order land identified in part 1 of the book of reference under article 24 (acquisition of subsoil only) or article 26 (rights under or over streets)

(10) Where the undertaker takes possession of land under this article, the undertaker is not to be required to acquire the land or any interest in it.

(11) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.

(12) Nothing in this article prevents the taking of temporary possession more than once in relation to any land specified in Schedule 9 (land of which temporary possession may be taken).

(13) The provisions of the Neighbourhood Planning Act 2017 M20 do not apply insofar as they relate to temporary possession of land under this article in connection with the carrying out of the authorised development.

Commencement Information

I27Art. 27 in force at 3.4.2019, see art. 1

Marginal Citations

Temporary use of land for maintaining the authorised developmentE+W+S

28.—(1) Subject to paragraph (2), at any time during the maintenance period relating to any part of the authorised development, the undertaker may—

(a)enter on and take temporary possession of any land within the Order land if such possession is reasonably required for the purpose of maintaining the authorised development; and

(b)construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.

(2) Paragraph (1) does not authorise the undertaker to take temporary possession of—

(a)any house or garden belonging to a house; or

(b)any building (other than a house) if it is for the time being occupied.

(3) Not less than 28 days before entering on and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land.

(4) The undertaker may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance of the part of the authorised development for which possession of the land was taken.

(5) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.

(6) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.

(7) Any dispute as to a person's entitlement to compensation under paragraph (6), or as to the amount of the compensation, is to be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(8) Nothing in this article affects any liability to pay compensation under section 10(2) (further provisions as to compensation for injurious affection) of the 1965 Act or under any other enactment in respect of loss or damage arising from the maintenance of the authorised development, other than loss or damage for which compensation is payable under paragraph (6).

(9) Where the undertaker takes possession of land under this article, the undertaker is not to be required to acquire the land or any interest in it.

(10) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.

(11) In this article “the maintenance period” means the period of 5 years beginning with the date of final commissioning except where the authorised development is landscaping where “the maintenance period” means such period as set out in the landscape and ecological mitigation and management strategy which is approved by Central Bedfordshire Council pursuant to Requirement 3 beginning with the date on which that part of the landscaping is completed provided that such period shall not exceed 10 years.

(12) The provisions of the Neighbourhood Planning Act 2017 do not apply insofar as they relate to temporary possession of land under this article in connection with the maintenance of the authorised development.

Commencement Information

I28Art. 28 in force at 3.4.2019, see art. 1

Statutory undertakersE+W+S

29.  Subject to the provisions of Schedule 10 (protective provisions), the undertaker may—

(a)acquire compulsorily the land belonging to statutory undertakers within the Order land;

(b)extinguish or suspend the rights of or restrictions for the benefit of, and remove or reposition the apparatus belonging to statutory undertakers on, under, over or within the Order land; and

(c)create and acquire compulsorily the rights and/or impose restrictions over any Order land belonging to statutory undertakers.

Commencement Information

I29Art. 29 in force at 3.4.2019, see art. 1

Apparatus and rights of statutory undertakers in streetsE+W+S

30.  Where a street is altered or diverted or its use is temporarily prohibited or restricted under article 10 (construction and maintenance of new or altered means of access) or article 11 (temporary prohibition or restriction of use of streets) or where a street is stopped up under article 12 (stopping up of streets) any statutory undertaker whose apparatus is under, in, on, along or across the street is to have the same powers and rights in respect of that apparatus, subject to Schedule 10 (protective provisions), as if this Order had not been made.

Commencement Information

I30Art. 30 in force at 3.4.2019, see art. 1

Recovery of costs of new connectionsE+W+S

31.—(1) Where any apparatus of a public utility undertaker or of a public communications provider is removed under article 29 (statutory undertakers) any person who is the owner or occupier of premises to which a supply was given from that apparatus is to be entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of effecting a connection between the premises and any other apparatus from which a supply is given.

(2) Paragraph (1) does not apply in the case of the removal of a public sewer but where such a sewer is removed under article 29 (statutory undertakers) any person who is—

(a)the owner or occupier of premises the drains of which communicated with the sewer; or

(b)the owner of a private sewer which communicated with that sewer,

is to be entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of making the drain or sewer belonging to that person communicate with any other public sewer or with a private sewerage disposal plant.

(3) This article does not have effect in relation to apparatus to which article 30 (apparatus and rights of statutory undertakers in streets) or Part 3 (water supply) of the 1991 Act applies.

(4) In this article—

public communication provider” has the same meaning as in section 151(1) (interpretation of chapter 1) of the Communications Act 2003 M21; and

public utility undertaker” has the same meaning as in the 1980 Act.

Commencement Information

I31Art. 31 in force at 3.4.2019, see art. 1

Marginal Citations

PART 6 E+W+SOPERATIONS

Felling or lopping of trees and removal of hedgerowsE+W+S

32.—(1) The undertaker may, subject to paragraph (3), fell or lop any tree or shrub within or overhanging land within the Order limits or cut back its roots, if it reasonably believes it to be necessary to do so to prevent the tree or shrub—

(a)from obstructing or interfering with the construction, maintenance or operation of the authorised development or any apparatus used in connection with the authorised development; or

(b)from constituting a danger to persons using the authorised development.

(2) The undertaker may, for the purposes of the authorised development and subject to paragraph (3), remove any hedgerows within the Order limits that may be required for the purposes of carrying out the authorised development.

(3) In carrying out any activity authorised by paragraph (1) or paragraph (2), the undertaker must do no unnecessary damage to any tree or shrub and must pay compensation to any person for any loss or damage arising from such activity.

(4) Any dispute as to a person's entitlement to compensation under paragraph (3), or as to the amount of compensation, is to be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(5) In this article “hedgerow” has the same meaning as in the Hedgerows Regulations 1997 M22.

Commencement Information

I32Art. 32 in force at 3.4.2019, see art. 1

Marginal Citations

PART 7 E+W+SMISCELLANEOUS AND GENERAL

Application of landlord and tenant lawE+W+S

33.—(1) This article applies to—

(a)any agreement for leasing to any person the whole or any part of the authorised development or the right to operate the same; and

(b)any agreement entered into by the undertaker with any person for the construction, maintenance, use or operation of the authorised development, or any part of it,

so far as any such agreement relates to the terms on which any land which is the subject of a lease granted by or under that agreement is to be provided for that person's use.

(2) No enactment or rule of law regulating the rights and obligations of landlords and tenants prejudices the operation of any agreement to which this article applies.

(3) Accordingly, no such enactment or rule of law applies in relation to the rights and obligations of the parties to any lease granted by or under any such agreement so as to—

(a)exclude or in any respect modify any of the rights and obligations of those parties under the terms of the lease, whether with respect to the termination of the tenancy or any other matter;

(b)confer or impose on any such party any right or obligation arising out of or connected with anything done or omitted on or in relation to land which is the subject of the lease, in addition to any such right or obligation provided for by the terms of the lease; or

(c)restrict the enforcement (whether by action for damages or otherwise) by any party to the lease of any obligation of any other party under the lease.

Commencement Information

I33Art. 33 in force at 3.4.2019, see art. 1

Cases in which land is to be treated as not being operational landE+W+S

34.  Development consent granted by this Order is to be treated as specific planning permission for the purposes of section 264(3)(a) (cases in which land is to be treated as not being operational land) of the 1990 Act.

Commencement Information

I34Art. 34 in force at 3.4.2019, see art. 1

Defence to proceedings in respect of statutory nuisanceE+W+S

35.—(1) Where proceedings are brought under section 82(1) (summary proceedings by persons aggrieved by statutory nuisances) of the Environmental Protection Act 1990 M23 in relation to a nuisance falling within paragraph (g) (noise emitted from premises so as to be prejudicial to health or a nuisance) of section 79(1) of that Act, no order is to be made, and no fine may be imposed, under section 82(2) of that Act if the defendant shows that the nuisance—

(a)relates to premises used by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development and that the nuisance is attributable to the carrying out of the authorised development in accordance with a notice served under section 60 (control of noise on construction sites), or a consent given under section 61 (prior consent for work on construction sites), of the Control of Pollution Act 1974 M24; or

(b)is a consequence of the construction or maintenance of the authorised development and that it cannot reasonably be avoided; or

(c)is a consequence of the use of the authorised development and that it cannot reasonably be avoided.

(2) Section 61(9) (consent for work on construction site to include statement that it does not of itself constitute a defence to proceedings under section 82 of the Environmental Protection Act 1990) of the Control of Pollution Act 1974 does not to apply where the consent relates to the use of premises by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development.

Commencement Information

I35Art. 35 in force at 3.4.2019, see art. 1

Marginal Citations

M231990 c.43. There are amendments not relevant to this Order.

M241974 c.40. Section 61 was amended by section 162 of and paragraph 15 of Schedule 15 to the Environmental Protection Act 1990 (c.43). There are other amendments not relevant to this Order.

Protective provisionsE+W+S

36.  Schedule 10 (protective provisions) (and Schedule 13 (arbitration rules)) has effect.

Commencement Information

I36Art. 36 in force at 3.4.2019, see art. 1

Amendment and Modification of statutory provisionsE+W+S

37.  The Rookery South (Resource Recovery Facility) Order 2011 is to be amended for the purposes of this Order only as set out in Schedule 11 (modifications to the Rookery South (Resource Recovery Facility) Order 2011).

Commencement Information

I37Art. 37 in force at 3.4.2019, see art. 1

Certification of plans etc.E+W+S

38.—(1) The undertaker must, as soon as practicable after the making of this Order, submit to the Secretary of State copies of all documents and plans listed in Table 11 of Schedule 14 (documents and plans to be certified) to this Order for certification that they are true copies of the documents referred to in this Order.

(2) A plan or document so certified is to be admissible in any proceedings as evidence of the contents of the document of which it is a copy.

Commencement Information

I38Art. 38 in force at 3.4.2019, see art. 1

Service of noticesE+W+S

39.—(1) A notice or other document required or authorised to be served for the purposes of this Order may be served—

(a)by post;

(b)by delivering it to the person on whom it is to be served or to whom it is to be given or supplied; or

(c)with the consent of the recipient and subject to paragraphs (6) to (8), by electronic transmission.

(2) Where the person on whom a notice or other document to be served for the purposes of this Order is a body corporate, the notice or document is duly served if it is served on the secretary or clerk of that body.

(3) For the purposes of section 7 (references to service by post) of the Interpretation Act 1978 M25 as it applies for the purposes of this article, the proper address of any person in relation to the service on that person of a notice or document under paragraph (1) is, if that person has given an address for service, that address and otherwise—

(a)in the case of the secretary of clerk of that body corporate, the registered or principal office of that body, and,

(b)in any other case, the last known address of that person at that time of service.

(4) Where for the purposes of this Order a notice or other document is required or authorised to be served on a person as having an interest in, or as the occupier of, land and the name or address of that person cannot be ascertained after reasonable enquiry, the notice may be served by—

(a)addressing it to that person by the description of “owner”, or as the case may be “occupier” of the land (describing it); and

(b)either leaving it in the hands of the person who is or appears to be resident or employed on the land or leaving it conspicuously affixed to some building or object on or near the land.

(5) Where a notice or other document required to be served or sent for the purposes of this Order is served or sent by electronic transmission the requirement is to be taken to be fulfilled only where—

(a)the recipient of the notice or other document to be transmitted has given consent to the use of electronic transmission in writing or by electronic transmission;

(b)the notice or document is capable of being accessed by the recipient;

(c)the notice or document is legible in all material respects; and

(d)in a form sufficiently permanent to be used for subsequent reference.

(6) Where the recipient of a notice or other document served or sent by electronic transmission notifies the sender within seven days of receipt that the recipient requires a paper copy of all or any part of that notice or other document the sender must provide such a copy as soon as reasonably practicable.

(7) Any consent to the use of an electronic transmission by a person may be revoked by that person in accordance with paragraph (8).

(8) Where a person is no longer willing to accept the use of electronic transmission for any of the purposes of this Order—

(a)that person must give notice in writing or by electronic transmission revoking any consent given by that person for that purpose; and

(b)such revocation is final and takes effect on a date specified by the person in the notice but that date must not be less than 7 days after the date on which the notice is given.

(9) This article does not exclude the employment of any method of service not expressly provided for by it.

Commencement Information

I39Art. 39 in force at 3.4.2019, see art. 1

Marginal Citations

Procedure in relation to certain approvalsE+W+S

40.—(1) Where an application is made to or a request is made of the relevant planning authorities, highway authority, traffic authority, street authority, or the owner of a watercourse, sewer or drain or the beneficiary of any of the protective provisions contained in Schedule 10 (protective provisions) for any consent, agreement or approval required or contemplated by any of the provisions of the Order (not including the requirements but including the protective provisions contained in Schedule 10), such consent, agreement or approval to be validly given, must be given in writing and must not be unreasonably withheld or delayed.

(2) Schedule 12 (procedure for discharge of requirements) has effect in relation to all consents, agreements or approvals granted, refused or withheld in relation to the requirements in Schedule 2 (requirements).

(3) Save for applications made pursuant to Schedule 12 (procedure for discharge of requirements) and where stated to the contrary if, within eight weeks after the application or request has been submitted to an authority, beneficiary of protective provisions or an owner as referred to in paragraph (1) of this article (or such longer period as may be agreed with the undertaker in writing) it has not notified the undertaker of its disapproval and the grounds of disapproval, it is deemed to have approved the application or request.

(4) The procedure set out in paragraph 1(3) of Schedule 12 (procedure for discharge of requirements) has effect in relation to any refusal by an authority, beneficiary of protective provisions, or an owner as referred to in paragraph (1) of this article to any consent, agreement or approval required under this Order, including such as may be required pursuant to the protective provisions contained within Schedule 10 (protective provisions).

(5) Where any application is made as described in paragraph (1), the undertaker must include a statement in such application that refers to the timeframe for consideration of the application and the consequences of failure to meet that timeframe as prescribed by paragraph (3).

Commencement Information

I40Art. 40 in force at 3.4.2019, see art. 1

ArbitrationE+W+S

41.  Any difference under any provision of this Order, unless otherwise provided for, is to be referred to and settled by a single arbitrator to be agreed between the parties or, failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) by the Secretary of State.

Commencement Information

I41Art. 41 in force at 3.4.2019, see art. 1

FundingE+W+S

42.—(1) The undertaker must not exercise the powers conferred by the provisions referred to in paragraph (2) in relation to any land unless it has first put in place either—

(a)a guarantee and the amount of that guarantee approved by the Secretary of State in respect of the liabilities of the undertaker to pay compensation pursuant to the provisions referred to in paragraph (2) in respect of the exercise of the relevant power in relation to that land; or

(b)an alternative form of security and the amount of that security approved by the Secretary of State in respect of the liabilities of the undertaker to pay compensation pursuant to the provisions referred to in paragraph (2) in respect of the exercise of the relevant power in relation to that land.

(2) The provisions are—

(a)article 18 (compulsory acquisition of land);

(b)article 19 (statutory authority to override easements and other rights);

(c)article 21 (compulsory acquisition of rights etc);

(d)article 22 (private rights);

(e)article 24 (acquisition of subsoil only);

(f)article 26 (rights under or over streets);

(g)article 27 (temporary use of land for carrying out the authorised development);

(h)article 28 (temporary use of land for maintaining the authorised development); and

(i)article 29 (statutory undertakers).

(3) A guarantee or alternative form of security given in respect of the liabilities of the undertaker to pay compensation pursuant to the provisions referred to in paragraph (2) is to be treated as enforceable against the guarantor or person providing the alternative form of security by any person to whom such compensation is payable and must be in such a form as to be capable of enforcement by such a person.

(4) Nothing in this article requires a guarantee or alternative form of security to be in place for more than 15 years after the date on which the relevant power is exercised.

Commencement Information

I42Art. 42 in force at 3.4.2019, see art. 1

Low Level Restoration SchemeE+W+S

43.  Insofar as compliance with any article of this Order or any requirement in Schedule 2 (requirements) prevents the undertaker from complying with any condition contained in the planning permission granted under the Town and Country Planning Act 1990 for the low level restoration scheme for Rookery South Pit (reference number BC/CM/2000/8), the undertaker shall not be in breach of that condition.

Commencement Information

I43Art. 43 in force at 3.4.2019, see art. 1

Signed by the authority of the Secretary of State for Business, Energy and Industrial Strategy

Gareth Leigh

Head of Energy Infrastructure Planning

Department for Business, Energy and Industrial Strategy

Yn ôl i’r brig

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open yr Offeryn Cyfan

Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill