Chwilio Deddfwriaeth

The Environmental Permitting (England and Wales) Regulations 2016

Changes over time for: SCHEDULE 8

 Help about opening options

Changes to legislation:

The Environmental Permitting (England and Wales) Regulations 2016, SCHEDULE 8 is up to date with all changes known to be in force on or before 01 May 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to the whole Instrument associated Parts and Chapters:

Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):

Regulation 35(1)

SCHEDULE 8E+WPart B installations and Part B mobile plant etc.

This Atodlen has no associated Memorandwm Esboniadol

ApplicationE+W

1.—(1) Subject to sub-paragraph (2), in England and Wales, this Schedule applies in relation to every Part B installation.

(2) Where installations are Part B installations solely because of the aggregation of the net rated thermal input of two or more appliances in accordance with paragraph 2 under the heading “Interpretation and application of Part B” in Section 1.1 of Part 2 of Schedule 1, only paragraph 4(1)(a) of this Schedule applies to those installations (in addition to the provisions in Schedule 24).

(3) In Wales only, this Schedule also applies in relation to every small waste incineration plant (in addition to the provisions in Schedule 13) and in relation to every solvent emission activity (in addition to the provisions in Schedule 14).

InterpretationE+W

2.  For the purposes of this Schedule—

best available techniques” means the most effective and advanced stage in the development of activities and their methods of operation which indicates the practical suitability of particular techniques for providing in principle the basis for emission limit values relevant to air pollution designed to prevent and, where that is not practicable, generally to reduce emissions and the impact on the environment as a whole, where—

(a)

techniques” includes both the technology used and the way in which the installation is designed, built, maintained, operated and decommissioned;

(b)

available techniques” means those techniques developed on a scale which allows implementation in the relevant industrial sector, under economically and technically viable conditions, taking into consideration the costs and advantages, and which are reasonably accessible to the operator;

(c)

best” means most effective in achieving a high general level of protection of the environment as a whole;

installation” means a Part B installation, Part B mobile plant, small waste incineration plant or solvent emission activity.

Exercise of regulator's functions: generalE+W

3.  The regulator must exercise its functions under these Regulations for the purpose of preventing or, where that is not practicable, reducing emissions into the air.

Applications for the grant of an environmental permitE+W

4.—(1) The regulator must ensure that every application for the grant of an environmental permit includes the following information—

(a)the installation and its activities;

(b)the sources of emissions to air from the installation;

(c)the nature and quantities of foreseeable emissions into the air from the installation as well as identification of significant effects of those emissions on the environment;

(d)the proposed technology or other techniques for preventing, or where that is not possible, reducing emissions to air from the installation;

(e)further measures planned to ensure that the installation is operated in such a way that—

(i)all appropriate preventive measures are taken against pollution, in particular through the application of best available techniques, and

(ii)no significant pollution is caused;

(f)measures planned to monitor emissions into the air;

(g)the main alternatives, if any, to the techniques or measures required in paragraphs (d) to (f);

(h)a non-technical summary of the details referred to in paragraphs (a) to (g).

(2) Sub-paragraph (1)(d) does not apply to the extent that the application relates to the burning of waste oil in an appliance with a net rated thermal input of less than 0.4 megawatts at a Part B installation.

(3) In the case of a new installation or a substantial change where Article 4 of Directive 2011/92/EU of the European Parliament and of the Council on the assessment of the effects of certain public and private projects on the environment M1 applies, any relevant information obtained or conclusion arrived at pursuant to Articles 5, 6 or 7 of that Directive shall be taken into consideration by the regulator for the purposes of granting the environmental permit.

[F1(4) In sub-paragraph (3), a reference to a numbered Article of Directive 2011/92/EU is to be construed as a reference to the EU-derived domestic legislation which transposed that Article in respect of England and Wales.]

Textual Amendments

Marginal Citations

M1OJ No L 26, 28.1.2012, p 1, as last amended by Directive 2014/52/EU (OJ No L 124, 25.4.2014, p 1).

Exercise of relevant functionsE+W

5.—(1) The regulator must, for the purpose of preventing or, where that is not practicable, reducing emissions into the air, exercise its relevant functions in relation to the installations to which this Schedule applies—

(a)so as to ensure that they are operated in such a way that—

(i)appropriate preventive measures are taken against air pollution, in particular through the application of best available techniques;

(ii)no significant air pollution is caused;

(b)where an environmental quality standard requires stricter conditions than those achievable by the use of best available techniques, additional measures are required by the permit, without prejudice to other measures which might be taken to comply with environmental quality standards;

(c)permits include emission limit values, which may if appropriate be supplemented or replaced by equivalent parameters or technical measures, for polluting substances likely to be emitted into the air from the installation concerned in significant quantities;

F2(d). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(2) The regulator must ensure that emission limit values or equivalent parameters or technical measures are based on best available techniques without prescribing the use of any technique or specific technology, but taking into account the technical characteristics of the installation, including (except in the case of mobile plant) its geographical location and the local environmental conditions.

(3) In this paragraph “substance” means any chemical element and its compounds and any biological entity or micro-organism, with the exception of the following substances—

(a)radioactive substances as defined in [F3Article 4] of the Basic Safety Standards Directive;

(b)genetically modified micro-organisms as defined in Article 2(b) of Directive 2009/41/EC of the European Parliament and of the Council on the contained use of genetically modified micro-organisms M2;

(c)genetically modified organisms as defined in point 2 of Article 2 of Directive 2001/18/EC of the European Parliament and of the Council on the deliberate release into the environment of genetically modified organisms M3.

Textual Amendments

Marginal Citations

M2OJ No L 125, 21.5.2009, p 75.

M3OJ No L 106, 17.4.2001, p 1, as last amended by Directive (EU) 2015/412 (OJ No L 68, 13.3.2015, p 1).

Change in operationE+W

6.—(1) Operators holding environmental permits for installations to which this Schedule applies must notify the regulator of any substantial change in the operation of that installation.

(2) Where there is a substantial change in the operation of an installation, the regulator must ensure that the environmental permit is reviewed and, if necessary, updated.

Review of permitsE+W

7.  The regulator must review an environmental permit where—

(a)the air pollution caused by the installation is of such significance that the existing emission limit values of the permit need to be revised or new values need to be included in the permit,

(b)substantial changes in best available techniques make it possible to reduce emissions significantly without imposing excessive costs,

(c)the operational safety of the process or activity requires other techniques to be used, or

(d)new legislation necessitates a review.

Developments in best available techniquesE+W

8.  The regulator must ensure that it is informed of developments in best available techniques.

Yn ôl i’r brig

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open yr Offeryn Cyfan

Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill