The Town and Country Planning (Development Management Procedure) (England) Order 2015

 Help about what version

Pa Fersiwn

 Help about advanced features

Nodweddion Uwch

Changes to legislation:

There are currently no known outstanding effects for the The Town and Country Planning (Development Management Procedure) (England) Order 2015, Part 4. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Part 4E+WConsultation

Consultations before the grant of permissionE+W

18.—(1) [F1Subject to paragraph (1A),] before granting planning permission for development which, in their opinion, falls within a category set out in the Table in Schedule 4, a local planning authority must consult the authority or person mentioned in relation to that category, except where—

(a)the local planning authority are the authority so mentioned;

(b)the local planning authority are required to consult the authority so mentioned under paragraph 7 of Schedule 1 to the 1990 Act (local planning authorities: distribution of functions) M1 or article 24;

(c)the authority or person so mentioned has advised the local planning authority that they do not wish to be consulted;

(d)the development is subject to any standing advice published by the authority or person so mentioned in relation to the category of development; or

(e)the development is not EIA development and is the subject of an application in relation to which article 20 applies.

[F2(1A) Paragraph (1) does not apply in relation to an application for technical details consent unless the authority or person mentioned in relation to a category in the Table in Schedule 4 has advised the local planning authority by a valid notice that they wish to be consulted in relation to the development.

(1B) For the purposes of paragraph (1A) a notice is valid if it specifies a particular site and it was given in writing to the local planning authority before the date on which the permission in principle to which the application for technical details consent relates was granted.]

(2) The exception in paragraph (1)(c) does not apply where, in the opinion of the local planning authority, development falls within paragraph (zb) of the Table in Schedule 4.

(3) The exception in paragraph (1)(d) does not apply where—

(a)the development is EIA development; or

(b)the standing advice was published more than 2 years before the date of the application for planning permission for the development and the guidance has not been amended or confirmed as being current by the authority or person within that period.

(4) The Secretary of State may give directions to a local planning authority requiring that authority to consult any person or body named in the directions, in any case or class of case specified in the directions.

(5) Where, by or under this article or article 20, a local planning authority are required to consult any person or body (“consultee”) before granting planning permission—

(a)they must, unless an applicant has served a copy of an application for planning permission on the consultee, give notice of the application to the consultee; and

(b)[F3subject to paragraphs (6) and (8)], they must not determine the application until at least 21 days after the date on which notice is given under sub-paragraph (a) or, if earlier, 21 days after the date of service of a copy of the application on the consultee by the applicant.

(6) Paragraph (5)(b) does not apply if before the end of the period referred to in that sub-paragraph—

(a)the local planning authority have received representations concerning the application from all consultees; or

(b)all consultees give notice that they do not intend to make representations.

(7) The local planning authority must, in determining the application, take into account any representations received from any consultee.

[F4(8) In the case of an application for public service infrastructure development, in paragraph (5)(b), “21 days” is to be read, in each place it occurs, as if it were a reference to “18 days”.]

Textual Amendments

Marginal Citations

M1Paragraph 7 of Schedule 1 was substituted by section 118(1) of, and paragraphs 1 and 16 of Schedule 6 to, the 2004 Act, and was amended by paragraph 3 of Schedule 5 to the Local Democracy, Economic Development and Construction Act 2009 (c. 20) and paragraph 1 of Schedule 8 and Schedule 25 to the 2011 Act.

Consultations before the grant of planning permission: urgent Crown developmentE+W

19.—(1) This article applies in relation to applications made to the Secretary of State under section 293A of the 1990 Act (urgent Crown development: application) M2.

(2) Before granting planning permission for development which, in the opinion of the Secretary of State, falls within a category set out in the Table in Schedule 4, the Secretary of State must consult the authority or person mentioned in relation to that category, except where—

(a)the Secretary of State is required to consult the authority so mentioned under section 293A(9)(a) of the 1990 Act;

(b)the authority or person so mentioned has advised the Secretary of State that they do not wish to be consulted; or

(c)the development is subject to any standing advice published by the authority or person so mentioned to the Secretary of State in relation to the category of development.

(3) The exception in paragraph (2)(b) does not apply where, in the opinion of the Secretary of State, development falls within paragraph (zb) of the Table in Schedule 4.

(4) The exception in paragraph (2)(c) does not apply where—

(a)the development is EIA development; or

(b)the standing advice was issued more than 2 years before the date of the application for planning permission for the development and the guidance has not been amended or confirmed as being current by the authority or person within that period.

(5) Where, by or under this article, the Secretary of State is required to consult any person or body (“consultee”) before granting planning permission—

(a)the Secretary of State must, unless an applicant has served a copy of an application for planning permission on the consultee, give notice of the application to the consultee; and

(b)[F5subject to paragraphs (6) and (8)], the Secretary of State must not determine the application until at least 21 days after the date on which notice is given under sub-paragraph (a) or, if earlier, 21 days after the date of service of a copy of the application on the consultee by the applicant.

(6) Paragraph (5)(b) does not apply if before the end of the period referred to in that sub-paragraph—

(a)the Secretary of State has received representations concerning the application from the consultee; or

(b)all consultees give notice that they do not intend to make representations.

(7) The Secretary of State must, in determining the application, take into account any representations received from any consultee.

[F6(8) In the case of an application for public service infrastructure development, in paragraph (5)(b), “21 days” is to be read, in each place it occurs, as if it were a reference to “18 days”.]

Textual Amendments

Marginal Citations

M2Section 293A was inserted by section 82(1) of the 2004 Act.

Consultations before the grant of planning permission pursuant to section 73 or the grant of a replacement planning permission subject to a new time limitE+W

20.—(1) Paragraph (2) applies in relation to an application—

(a)made pursuant to section 73 of the 1990 Act (determination of applications to develop land without conditions previously attached);

(b)for planning permission where the development that is the subject of the application—

(i)has not yet begun; and

(ii)was granted planning permission on or before 1st October 2010 subject to a time limit imposed by or under section 91 (general condition limiting duration of planning permission) or 92 (outline planning permission) of the 1990 Act M3 which has not expired; or

(c)for outline planning permission where the development that is the subject of the application—

(i)has begun in accordance with the terms of, and any reserved matters approved under, an outline planning permission which is required or expressly permitted to be implemented in phases, other than a permission granted on an application made under sub-paragraph (b); and

(ii)was granted that outline planning permission on or before 1st October 2010 subject to a time limit imposed by or under section 91 or 92 of the 1990 Act which has not expired.

(2) Before granting planning permission on an application in relation to which this paragraph applies, the local planning authority must consult such authorities or persons falling within a category set out in the Table in Schedule 4 as the local planning authority consider appropriate.

Marginal Citations

M3Sections 91 and 92 were amended by section 51(1) of the 2004 Act and section 91 was subsequently amended by paragraph 13 of Schedule 12 to the Localism Act 2011 (c. 20); there have been other amendments to section 91 which are not relevant to this Order.

Consultation with county planning authorityE+W

[F721.(1) Subject to paragraph (2) the period prescribed for the purposes of paragraph 7(7)(c) of Schedule 1 to the 1990 Act (local planning authorities: distribution of functions) is 21 days.

(2) In the case of an application for public service infrastructure development, in paragraph (1), “21 days” is to be read as if it were a reference to “18 days”.]

Duty to respond to consultationE+W

22.—(1) The requirements to consult which are prescribed for the purposes of section 54(2)(b) of the 2004 Act (duty to respond to consultation) are those contained in—

(a)articles 18 and 19 and Schedule 4, except as provided for in paragraph (2);

(b)article 20;

(c)article 24;

(d)paragraphs W(5) and (6) of Part 3 of Schedule 2 to the Permitted Development Order (change of use) M4;

[F8(da)paragraph W(6A) of Part 3 of Schedule 2 to the Permitted Development Order as provided for by paragraph MA.2(4)(c) of that Part;]

(e)[F9paragraphs [F10BC.3(3)],] E.3(5) and (6) of Part 4 of Schedule 2 to the Permitted Development Order ([F11temporary buildings and uses]);

[F12(ea)paragraph M.2(i)(iii) of Part 7 of Schedule 2 to the Permitted Development Order (extensions etc for schools, colleges, universities, prisons and hospitals);]

(f)paragraph A.3(5)(a) of Part 16 of Schedule 2 to the Permitted Development Order (development by electronic communications code operators);

[F13(fa)paragraph B(5), (6) and (6A) of Part 20 of Schedule 2 to the Permitted Development Order (construction of new dwellinghouses);]

(g)section 71(3) of the 1990 Act (consultations in connection with determinations under section 70);

(h)paragraph 4(2) of Schedule 1 to the 1990 Act M5;

(i)paragraph 7 of Schedule 1 to the 1990 Act; and

(j)paragraph 3(b) of Schedule 4 to the Planning (Listed Buildings and Conservation Areas) Act 1990 (further provisions as to exercise of functions by different authorities) M6.

(2) A requirement to consult under paragraph (zb)(iii) of Schedule 4 is not a prescribed requirement for the purposes of section 54(2)(b) of the 2004 Act.

[F14(3) Subject to paragraph (6) the period prescribed for the purposes of section 54(4) of the 2004 Act is—

(a)the period of 21 days beginning with the day on which—

(i)the document on which the views of the consultee are sought is received by the consultee, or

(ii)where there is more than one such document and they are sent on different days, the last of those documents is received by the consultee, or

(b)such other period as may be agreed in writing between the consultee and the consultor.]

(4) The information to be provided to the consultee for the purposes of the consultation, pursuant to section 54(5)(b) of the 2004 Act, is such information as will enable that person to provide a substantive response.

(5) For the purposes of this article and article 23 and pursuant to section 54(5)(c) of the 2004 Act, a substantive response is one which—

(a)states that the consultee has no comment to make;

(b)states that, on the basis of the information available, the consultee is content with the development proposed;

(c)refers the consultor to current standing advice by the consultee on the subject of the consultation; or

(d)provides advice to the consultor.

[F15(6) In the case of an application for public service infrastructure development, where the requirements to consult contained in paragraph (1)(a), (b), (c), (h) or (i) apply, the prescribed period of 21 days in paragraph (3) is to be read as if it were a reference to 18 days.]

Textual Amendments

Marginal Citations

M5Paragraph 4(2) of Schedule 1 was amended by sections 19(2) and 84 of, and paragraph 53 of Schedule7 and Part 1 of Schedule 19 to, the Planning and Compensation Act 1991 (c. 34).

M61990 c. 9. Paragraph 3 of Schedule 4 was substituted by paragraph 61 of Schedule 7 to the Planning and Compensation Act 1991 (c. 34) and amended by sections 78 and 120 of, and paragraph 33(7) of Schedule 10 and Schedule 24 to, the Environment Act 1995 (c. 25).

Duty to respond to consultation: annual reportsE+W

23.—(1) Each consultee who is, by virtue of section 54 of the 2004 Act and article 22, under a duty to respond to consultation, must give to the Secretary of State, not later than 1st July in each year, a report as to that consultee's compliance with section 54(4) of the 2004 Act.

(2) The report must relate to the period of 12 months commencing on 1st April in the preceding year (“the report year”).

(3) The report must contain, in respect of any report year—

(a)a statement as to the number of occasions on which the consultee was consulted by a person other than a local planning authority;

(b)a statement as to the number of occasions on which a substantive response was given to a person other than a local planning authority within the period referred to in section 54(4) of the 2004 Act;

(c)a statement as to the number of occasions on which the consultee was consulted by a local planning authority;

(d)a statement as to the number of occasions on which a substantive response was given to a local planning authority within the period referred to in section 54(4) of the 2004 Act; and

(e)in relation to occasions on which the consultee has given a substantive response outside the period referred to in section 54(4) of the 2004 Act, a summary of the reasons why the consultee failed to comply with the duty to respond within that period.

Recommendations by district planning authority before determination of county matters applicationE+W

24.—(1) [F16Subject to paragraphs (2) and (3)], a county planning authority must, before determining—

(a)an application for planning permission under Part 3 of the 1990 Act (control over development),

(b)an application for a certificate of lawful use or development under section 191 or 192 of the 1990 Act (certificates of lawfulness of existing or proposed use or development) M7, or

(c)an application for approval of reserved matters,

give the district planning authority, if any, for the area in which the relevant land lies a period of at least 21 days, from the date of receipt of the application by the district authority, within which to make recommendations about the manner in which the application must be determined; and must take any such recommendations into account.

(2) Paragraph (1) does not prevent a county planning authority determining an application if before the end of the period referred to in that paragraph—

(a)the county planning authority have received recommendations concerning the application from the district planning authority; or

(b)the district planning authority give notice to the county planning authority that they do not intend to make recommendations.

[F17(3) In the case of an application for planning permission for public service infrastructure development, in paragraph (1) “21 days” is to be read as if it were a reference to “18 days”.]

(3) A county planning authority must—

(a)on determining an application of a kind mentioned in paragraph (1), as soon as reasonably practicable notify the district planning authority, if any, of the terms of their decision; or

(b)if any such application is referred to the Secretary of State, inform the district planning authority, if any, of the date when it was so referred and, when notified to them, of the terms of the decision.

Textual Amendments

Marginal Citations

M7Sections 191 and 192 were substituted by section 10(1) of the Planning and Compensation Act 1991 (c. 34).

Representations by parish council before determination of applicationE+W

25.—(1) [F18Subject to paragraph (5)] where the council of a parish are given information in relation to an application pursuant to paragraph 8(1) [F19or paragraph 8(3B)] of Schedule 1 to the 1990 Act (local planning authorities: distribution of functions) M8, they must, as soon as practicable, notify the local planning authority who are determining the application whether they propose to make any representations about the manner in which the application should be determined, and must make any representations to that authority within 21 days of the notification to them of the application.

(2) A local planning authority must not determine any application in respect of which a parish are required to be given information before—

(a)the council of the parish inform them that they do not propose to make any representations;

(b)representations are made by that council; or

(c)the period of 21 days mentioned in paragraph (1) has elapsed,

whichever occurs first; and in determining the application the authority must take into account any representations received from the council of the parish.

(3) The appropriate authority must notify the council of the parish of—

(a)the terms of the decision on any such application; or

(b)where the application is referred to the Secretary of State—

(i)the date when it was so referred; and

(ii)when notified to the appropriate authority, the terms of the Secretary of State's decision.

(4) For the purposes of paragraph (3), the “appropriate authority” is—

(a)where the parish is situated in a National Park, the National Park authority;

(b)where the parish is situated in Greater London or a metropolitan county, and is not situated in a National Park, the local planning authority;

(c)where the parish is situated in a district which has no district council and is not situated in a National Park, the county planning authority;

(d)in any other case, the district planning authority.

[F20(5) In the case of an application for planning permission for public service infrastructure development, in paragraph (1) and sub-paragraph (c) of paragraph (2) “21 days” is to be read as if it were a reference to “18 days”.]

Textual Amendments

Marginal Citations

M8Paragraph 8(1) of Schedule 1 was substituted by paragraph 53 of Schedule 7 to the Planning and Compensation Act 1991 (c. 34). There are other amendments to paragraph 8 which are not relevant to this Order.

[F21Representations by neighbourhood forum before determination of applicationE+W

[F2225A.(1) Where a neighbourhood forum for a neighbourhood area are given information in relation to an application under paragraph 8A(1) or paragraph 8A(1B) of Schedule 1 to the 1990 Act (local planning authorities: distribution of functions)—

(a)subject to paragraph (2) the forum must, as soon as practicable, notify the local planning authority who are determining the application whether the forum proposes to make representations about the manner in which the application should be determined, and must make any representations to that authority within 21 days of the notification to the forum of the application; and

(b)article 25(2) to (4) applies in relation to any such application as if any reference to a council of a parish or to the parish (however expressed) were a reference to the neighbourhood forum or neighbourhood area, as appropriate.

(2) In the case of an application for public service infrastructure development, in paragraph (1), “21 days” is to be read as if it were a reference to “18 days”.]]

Notification of mineral applicationsE+W

26.—(1) Where notice has been given for the purposes of this article to a mineral planning authority as respects land which is in their area and it is specified in the notice—

(a)by the Coal Authority that the land contains coal,

(b)by the [F23Oil and Gas Authority] that the land contains gas or oil, or

(c)by the Crown Estate Commissioners that the land contains silver or gold,

the mineral planning authority must not determine any application for planning permission to win and work any mineral on that land without first notifying the body or person who gave the notice that an application has been made.

(2) In paragraph (1)(a), “coal” means coal other than that—

(a)won or worked during the course of operations which are carried on exclusively for the purpose of exploring for coal; or

(b)which it is necessary to dig or carry away in the course of activities carried on for purposes which do not include the getting of coal or any product of coal.

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Asesiadau Effaith

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill