Request for a scoping opinion

1.  A request for a scoping opinion must be accompanied by—

(a)a chart, plan or map sufficient to identify the location of the regulated activity and of other activities to be carried out in the course of the project;

(b)a brief description of the nature and purpose of the project and the regulated activity and their possible effects on the environment; and

(c)such other information or representations as the applicant may wish to provide or make.

Information required where another application has been made

2.  Where the regulated activity is to be carried out in the course of a project in respect of which the applicant has made an application to a consenting authority other than the regulator, an applicant seeking a scoping opinion must—

(a)inform the appropriate authority and the regulator (if the regulator is not also the appropriate authority) of any such application;

(b)if any such consenting authority has requested an environmental statement in respect of that project, inform the appropriate authority and the regulator (if the regulator is not also the appropriate authority) of that request; and

(c)if so requested by the appropriate authority or the regulator, provide the appropriate authority with a copy of any environmental statement and of any other environmental information provided to any such consenting authority.

Payment of a fee for a scoping opinion

3.—(1) The appropriate authority may require an applicant to pay a reasonable fee in respect of—

(a)the administrative expenses of providing a scoping opinion; and

(b)the cost of carrying out any examinations or tests that, in the opinion of the appropriate authority, are necessary or expedient to enable the appropriate authority to produce its scoping opinion.

(2) If the appropriate authority considers that it is appropriate to do so, it may—

(a)require the applicant to make a reasonable advance payment against the fee that it is entitled to charge for its scoping opinion;

(b)determine the balance of the fee payable after carrying out the work necessary to produce its scoping opinion in accordance with the remaining provisions of this Schedule; and

(c)require the applicant to pay the balance of the fee that it is entitled to charge prior to the notification of its scoping opinion.

Procedure for reaching a scoping opinion

4.—(1) The appropriate authority must, if it considers that it has not been provided with sufficient information to enable it to give a scoping opinion, notify the applicant in writing of the matters on which it requires further information and the applicant must supply that further information to the appropriate authority within such period as the appropriate authority may reasonably require.

(2) The applicant must supply the appropriate authority with such number of additional copies of the documentation as the appropriate authority may reasonably require.

(3) The appropriate authority need not deal further with the request for a scoping opinion until the applicant has complied with the requirements of sub-paragraphs (1) and (2).

(4) Where an applicant has failed to comply with the requirements of sub-paragraph (1) or (2) within such reasonable period as the appropriate authority has specified, or such longer period as the appropriate authority may reasonably allow—

(a)the appropriate authority may treat the request as having been withdrawn;

(b)the regulator may treat the application to which the request relates as having been withdrawn; and

(c)the appropriate authority (if the regulator is not also the appropriate authority) may direct the regulator to treat the application as withdrawn.

Matters to be considered in reaching a scoping opinion

5.  In reaching a scoping opinion, the appropriate authority must consider—

(a)the specific characteristics of the project;

(b)the nature and purpose of regulated activities of the type concerned in the project;

(c)the environmental features likely to be affected by the project; and

(d)the extent to which the applicant may reasonably be required to compile the information, having regard, inter alia, to current knowledge and methods of assessment.

Consultation

6.—(1) The appropriate authority must consult such of the consultation bodies as it considers appropriate before giving a scoping opinion.

(2) When carrying out any consultation under sub-paragraph (1), the appropriate authority must allow the consultation body a reasonable period within which to respond and that period must not be less than 28 days from the date of the letter that the consultation body receives from the appropriate authority or such other period as may be agreed between the consultation body and the appropriate authority.

Notification of a scoping opinion

7.  The appropriate authority must, as soon as reasonably practicable, provide its scoping opinion and a written statement of the reasons for its opinion to—

(a)the applicant;

(b)if the appropriate authority is not also the regulator, the regulator; and

(c)such of the consultation bodies as it consulted in accordance with paragraph 6.

Availability of scoping opinions for inspection

8.—(1) Subject to sub-paragraph (2), the appropriate authority must ensure that, as soon as possible after being sent to the applicant—

(a)its scoping opinion is publicised in such manner as it considers appropriate; and

(b)in the case of a deposit, its scoping opinion is made available on the Public Register.

(2) Sub-paragraph (1) does not require disclosure of any excluded information.

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Asesiadau Effaith

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill