Changes to legislation:

There are currently no known outstanding effects for the The Merchant Shipping (Passenger Ship Construction: Ships of Classes III to VI (A)) Regulations 1998, Section 47. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

General precautions against shock, fire and other hazardsU.K.

47.—(1) All electrical equipment shall be so constructed and installed that there will be no danger or injury to any person handling it in a proper manner. Exposed metal parts of electrical equipment which are not intended to have a voltage above that of earth, but which may have such a voltage under fault conditions, shall be earthed unless such equipment is—

(a)supplied at a voltage not exceeding 50 volts direct current or 55 volts root mean square alternating current between conductors hereinafter referred to as RMS ac, from a source other than an auto-transformer;

(b)supplied at a voltage not exceeding 250 volts RMS ac by safety isolating transformers supplying only one consuming device; or

(c)of double insulation construction.

(2) All electrical apparatus shall be constructed and installed so that it will not cause injury when handled or touched in the normal manner. In particular when electric lamps, welding equipment, tools or other apparatus are used in confined or damp spaces or spaces with large exposed conductive surfaces, special provision shall be made so far as practicable, to ensure that the danger of electric shock is reduced to a minimum. Such spaces shall at least include open decks and machinery spaces.

(3) Every main and emergency switchboard shall be so arranged as to give easy access for operation and sufficient access for maintenance without danger to any person. Every such switchboard shall be suitably guarded and a non-conducting mat or grating shall be provided at the back and front where necessary. No exposed parts which may have a voltage between conductors or to earth exceeding 250 volts direct current or 50 volts RMS ac shall be installed on the face of any switchboard or control panel.

(4) Subject to paragraph (6) the hull-return system shall not be used in any such ship for power, heat and light distribution systems.

(5) The final sub-circuits of any hull-return system of distribution shall be two-wire.

(6) The requirements of paragraphs (4) and (5) do not preclude the use of—

(a)impressed current cathodic protection systems;

(b)limited and locally earthed systems; and

(c)insulation monitoring devices with a maximum circulation current of 30 milliamperes.

(7) The insulation of any distribution system that is not earthed shall be continuously monitored by a system capable of giving audible and visual indication of abnormally low insulation values.

(8) Every separate electrical circuit shall be protected against short circuits.

(9) Each separate electrical circuit, other than a circuit which operates the ship’s steering gear, shall, unless it is permitted otherwise, be protected against overload. There shall be clearly and permanently indicated on or near each overload protective device the current carrying capacity of the circuit which it protects and the rating or setting of the device.

(10) All lighting and power circuits terminating in a cargo space shall be provided with a multiple pole switch outside the space for disconnecting all such circuits.

(11) Accumulator batteries shall be housed in boxes or compartments which are constructed to protect the batteries from damage and are so ventilated as to minimise the accumulation of explosive gas. Subject to regulation 48(1), electrical or other equipment which may constitute a source of ignition of flammable vapours shall not be installed in any compartment assigned to accumulator batteries. Accumulator batteries shall not be installed in sleeping accommodation spaces.

(12) Every electrical space-heater forming part of the equipment of a ship shall be fixed in position and shall be so constructed as to reduce the risk of fire to a minimum. No such heater shall be constructed with an element so exposed that clothing, curtains or other material can be scorched or set on fire by heat from the element.

(13) All electric cables external to equipment shall be flame retardant and shall be installed so that their flame retarding or equivalent properties are not impaired. The Certifying Authority may permit installation of cables which do not comply with the foregoing for particular purposes, such as radio frequency cables, where compliance would be impracticable.

(14) Cables shall be installed and supported in such a manner as to avoid chafing and other damage. All metal sheaths and metal armour of cables shall be electrically continuous and shall be earthed except that the Certifying Authority may permit such earthing to be omitted for particular purposes.

(15) Cables serving emergency services shall not so far as is practicable be routed through galleys, laundries, machinery spaces of Category A and their casings or other high fire risk areas except insofar as it is necessary to provide emergency services in such areas. Cables connecting fire pumps to the emergency switchboard shall be of fire resistant type where they pass through high fire risk areas.

Additional requirements for ships constructed on or after 1st September 1984

(16) In every ship distribution systems shall be so arranged that a fire in any main fire zone will not interfere with essential services in any other main fire zone. Main and emergency feeders passing through any main fire zone shall be separated as widely as is practicable both horizontally and vertically.

(17) Cables serving emergency services shall where practicable be installed in such a manner as to preclude them being rendered unserviceable by the effect of a fire in an adjacent space and subsequent heating of the dividing bulkhead.

(18) The electrical, mechanical, flame retarding and where applicable fire resisting properties of the terminations and joints in any conductor shall be at least equivalent to those of the conductor.

Commencement Information

I1Reg. 47 in force at 12.11.1998, see reg. 1

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.