There are outstanding changes not yet made by the legislation.gov.uk editorial team to Planning (Scotland) Act 2019. Those changes will be listed when you open the content using the Table of Contents below. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.

  1. Introductory Text

  2. PART 1 Development planning

    1. Development planning

      1. 1.Purpose of planning

      2. 2.National Planning Framework

      3. 3.Open space strategy

      4. 4.Housing needs of older people and disabled people: parliamentary report

      5. 5.Strategic development: regional spatial strategies

      6. 6.Removal of requirement to prepare strategic development plans

      7. 7.Local development plans

      8. 8.List of persons seeking land for self-build housing

      9. 9.Supplementary guidance

      10. 10.Key agencies

      11. 11.Delivery programmes

      12. 12.Amendment of National Planning Framework and local development plans

      13. 13.Development plan

    2. Local place plans

      1. 14.Local place plans

  3. PART 2 Masterplan consent areas

    1. 15.Masterplan consent area schemes

    2. 16.Bar to creation of new simplified planning zones

  4. PART 3 Development management

    1. Meaning of “development”

      1. 17.Meaning of “development”: use of dwellinghouse for short-term holiday lets

    2. Applications

      1. 18.Pre-application consultation

      2. 19.Assessment of health effects

      3. 20.Regulations about procedure for certain applications

      4. 21.Removal of requirement to recover costs before determining certain applications

      5. 22.Declining to determine an application

    3. Notice by planning authority of certain applications made to them

      1. 23.Notice by planning authority of certain applications made to them

    4. Assessment of environmental effects

      1. 24.Assessment of environmental effects

    5. Conditional grant of planning permission: noise-sensitive developments

      1. 25.Conditional grant of planning permission: noise-sensitive developments

    6. Conditional grant of planning permission: provision of toilet facilities within certain large developments

      1. 26.Conditional grant of planning permission: provision of toilet facilities within certain large developments

    7. Delegation of development decisions

      1. 27.Delegation of development decisions

      2. 28.Schemes of delegation

    8. Call-in of applications by Scottish Ministers: further provision

      1. 29.Call-in of applications by Scottish Ministers: further provision

    9. Determination of applications: statement to accompany notification

      1. 30.Determination of applications: statement to accompany notification

    10. Agreements relating to period before which an appeal may be made

      1. 31.Agreements relating to period before which an appeal may be made

    11. Duration of planning permission

      1. 32.Duration of planning permission

      2. 33.Completion notices

    12. Planning obligations

      1. 34.Planning obligations: financial agreements

      2. 35.Planning obligations: publication

      3. 36.Planning obligations: annual report

      4. 37.Planning obligations: modification or discharge

    13. Declining to determine an application: further provision

      1. 38.Declining to determine an application: further provision

    14. Development orders

      1. 39.Withdrawal of planning permission granted by development order

  5. PART 4 Other matters

    1. Promotion and use of mediation etc.

      1. 40.Promotion and use of mediation etc.

    2. Charges and fees

      1. 41.Fees for planning applications etc.

    3. Enforcement

      1. 42.Fines: increases and duty of court in determining amount

      2. 43.Liability for expenses under enforcement notice

      3. 44.Enforcement charters: statement on major developments

    4. Training for taking planning decisions

      1. 45.Power to impose training requirements: planning authorities

    5. Performance of planning authorities

      1. 46.Annual report by planning authorities on performance

      2. 47.National performance monitoring

    6. Regulations

      1. 48.Regulations

    7. Ministerial directions

      1. 49.Publication of directions

    8. Chief planning officers

      1. 50.Chief planning officers

    9. National Scenic Areas

      1. 51.National Scenic Areas

    10. Notice by planning authority of applications for listed building consent

      1. 52.Notice by planning authority of applications for listed building consent

    11. Forestry and woodland strategy

      1. 53.Forestry and woodland strategy

  6. PART 5 Infrastructure levy

    1. 54.Power to provide for levy

    2. 55.Guidance

    3. 56.Interpretation of Part and schedule

    4. 57.Power to change meaning of “infrastructure”

    5. 58.Lapsing of power to provide for levy

  7. PART 6 Final provisions

    1. 59.Ancillary provision

    2. 60.Power to replace descriptions with actual dates

    3. 61.Regulation-making powers

    4. 62.Minor and consequential amendments and repeals

    5. 63.Commencement

    6. 64.Short title

    1. SCHEDULE 1

      Infrastructure-levy regulations

      1. General

        1. 1.In this schedule, “infrastructure-levy regulations” means regulations under section 54....

        2. 2.This schedule (apart from paragraphs 15(2) and 16) is without...

        3. 3.Infrastructure-levy regulations may make incidental, supplementary, consequential, transitional, transitory or...

        4. 4.Any provision which infrastructure-levy regulations may make may be made...

      2. Who is liable for what

        1. 5.Infrastructure-levy regulations may set out— (a) the kinds of development...

      3. Relief where relevant planning obligation

        1. 6.Infrastructure-levy regulations may make provision to grant relief from liability...

      4. Local exemptions and discounts

        1. 7.Infrastructure-levy regulations may— (a) confer on local authorities the power...

      5. Collection and enforcement

        1. 8.Infrastructure-levy regulations may— (a) make provision about the collection of—...

      6. Financial penalty for late payment

        1. 9.(1) Infrastructure-levy regulations may allow, or require, local authorities to...

      7. Stopping development

        1. 10.(1) Infrastructure-levy regulations may— (a) empower a local authority to...

      8. Remission and repayment

        1. 11.Infrastructure-levy regulations may provide for the remission or repayment (with...

      9. Appeals

        1. 12.Infrastructure-levy regulations may— (a) establish a process for appealing against...

      10. Accounting requirements

        1. 13.(1) Infrastructure-levy regulations may make provision about the accounts that...

      11. Expenditure of levy income

        1. 14.(1) Infrastructure-levy regulations may make provision about the particular purposes...

      12. Use of planning and development powers

        1. 15.(1) Infrastructure-levy regulations may make provision about how any of...

      13. Maximum penalties

        1. 16.(1) The maximum penalty that infrastructure-levy regulations can specify for...

    2. SCHEDULE 2

      Minor and consequential amendments and repeals

      1. PART 1 Development planning

        1. Removal of requirement to prepare strategic development plans

          1. 1.(1) The Town and Country Planning (Scotland) Act 1997 is...

        2. Local development plans

          1. 2.(1) The Town and Country Planning (Scotland) Act 1997 is...

        3. Delivery programmes

          1. 3.(1) The Town and Country Planning (Scotland) Act 1997 is...

        4. Development plan

          1. 4.(1) Schedule 1 of the Town and Country Planning (Scotland)...

      2. PART 2 Masterplan consent areas

        1. Masterplan consent area schemes

          1. 5.(1) The Town and Country Planning (Scotland) Act 1997 is...

      3. PART 3 Development management

        1. Duration of planning permission

          1. 6.(1) The Town and Country Planning (Scotland) Act 1997 is...

        2. Schemes of delegation and local review

          1. 7.(1) The Town and Country Planning (Scotland) Act 1997 is...

        3. Development orders

          1. 8.(1) The Town and Country Planning (Scotland) Act 1997 is...

      4. PART 4 Regulations

        1. 9.(1) The Town and Country Planning (Scotland) Act 1997 is...

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Nodiadau Esboniadol

Text created by the Scottish Government to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Acts of the Scottish Parliament except those which result from Budget Bills.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill