Changes over time for: Cross Heading: Operational standards rules

 Help about opening options

Alternative versions:

Status:

Point in time view as at 01/10/2023.

Changes to legislation:

Building Act 1984, Cross Heading: Operational standards rules is up to date with all changes known to be in force on or before 24 May 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.

[F1Operational standards rulesE+W

Textual Amendments

F1Pt. 2A inserted (6.4.2023 for specified purposes except in relation to W., 5.9.2023 for W. for specified purposes, 1.10.2023 for specified purposes except in relation to W) by Building Safety Act 2022 (c. 30), ss. 42, 170(4); S.I. 2023/362, reg. 3(1)(s); S.I. 2023/914, reg. 2(b)(viii) (with reg. 7); S.I. 2023/993, reg. 2(k)

58ZOperational standards rulesE+W

(1)The regulatory authority may make rules (“operational standards rules”) applying to local authorities and registered building control approvers in relation to their exercise of building control functions.

(2)Operational standards rules may in particular make provision about standards to be met, and practices, procedures or methods to be adopted, in exercising building control functions.

(3)In this Part “building control functions”, in relation to a local authority or registered building control approver, means the functions of the authority or approver under this Act and regulations made under it.

(4)The operational standards rules may make different provision for different cases (for example, for different descriptions of work).

(5)The regulatory authority may revise the operational standards rules at any time.

(6)The regulatory authority must publish the operational standards rules (and any revised rules).

58Z1Reporting requirementsE+W

(1)The regulatory authority may direct local authorities and registered building control approvers to provide it, at specified times or intervals, with specified reports, returns and other information relating to the exercise of their building control functions.

(2)Specified” means specified in the direction.

(3)A direction under this section—

(a)must be in writing;

(b)may be general or specific;

(c)may be varied or revoked.

(4)A registered building control approver who, without reasonable excuse, fails to comply with a direction under this section commits an offence.

(5)An offence under subsection (4) is punishable on summary conviction by a fine.

58Z2Information: WalesE+W

(1)This section applies where the Welsh Ministers are the regulatory authority.

(2)The Welsh Ministers may by notice in writing require a local authority or registered building control approver to provide the Welsh Ministers with any documents or information relating to the exercise of their building control functions that the Welsh Ministers reasonably require.

(3)The notice must specify—

(a)the documents or information required,

(b)the date by which they must be provided, and

(c)the form in which they must be provided.

(4)A registered building control approver who, without reasonable excuse, fails to comply with a notice under this section commits an offence.

(5)An offence under subsection (4) is punishable on summary conviction by a fine.

58Z3InvestigationsE+W

(1)If it appears to the regulatory authority (on receipt of a complaint or otherwise) that a local authority or registered building control approver may have contravened the operational standards rules, the regulatory authority may investigate the matter.

(2)The regulatory authority must prepare and publish a statement of the procedure it will follow when investigating an authority or approver under this section (which must include an opportunity for the authority or approver to make representations).

(3)The regulatory authority may revise the statement at any time (and must publish any revised statement).

58Z4Improvement noticeE+W

(1)The regulatory authority may give an improvement notice to a local authority or a registered building control approver if it appears to the regulatory authority (following an investigation under section 58Z3 or otherwise) that the local authority or registered building control approver has contravened operational standards rules.

(2)An improvement notice is a notice requiring the local authority or registered building control approver to remedy the contravention by doing, or by refraining from doing, anything specified in the order.

(3)An improvement notice may have effect—

(a)until it is revoked, or

(b)for a period specified in the notice.

(4)Where the regulatory authority gives an improvement notice, it must also give the local authority or registered building control approver a statement of the reasons for giving the notice.

(5)Where the regulatory authority gives an improvement notice to a registered building control approver, in prescribed cases it must as soon as reasonably practicable provide copies of the notice and the statement—

(a)to each local authority in England, where the regulatory authority is the regulator, or

(b)to each local authority in Wales, where the regulatory authority is the Welsh Ministers.

(6)Where the regulatory authority giving an improvement notice is the regulator, it must as soon as reasonably practicable provide copies of the notice and the statement of reasons to the Secretary of State.

(7)The local authority or registered building control approver to whom the improvement notice is given may appeal to the appropriate court or tribunal against the notice.

58Z5Serious contravention noticesE+W

(1)The regulatory authority may give a serious contravention notice to a local authority or a registered building control approver if it appears to the regulatory authority (following an investigation under section 58Z3 or otherwise) that the condition in subsection (2) or (3) is met.

(2)The condition in this subsection is that—

(a)the local authority or registered building control approver has contravened operational standards rules, and

(b)as a result of the contravention the safety of persons in or about buildings has been, or may have been, put at risk.

(3)This condition in this subsection is that the local authority or registered building control approver—

(a)has been given an improvement notice under section 58Z4, and

(b)has failed to remedy the contravention of operational standards rules in respect of which the notice was given.

(4)A serious contravention notice is a notice requiring the local authority or registered building control approver to remedy the contravention in question by doing, or by refraining from doing, anything specified in the order.

(5)A serious contravention notice may have effect—

(a)until it is revoked, or

(b)for a period specified in the notice.

(6)Where the regulatory authority gives a serious contravention notice, it must also give the local authority or registered building control approver a statement of the reasons for giving the notice.

(7)Where the regulatory authority gives a serious contravention notice to a registered building control approver, in prescribed cases it must as soon as reasonably practicable provide copies of the notice and the statement—

(a)to each local authority in England, where the regulatory authority is the regulator, or

(b)to each local authority in Wales, where the regulatory authority is the Welsh Ministers.

(8)Where the regulatory authority giving a serious contravention notice is the regulator, it must as soon as reasonably practicable provide copies of the notice and the statement of reasons to the Secretary of State.

(9)The local authority or registered building control approver to whom the serious contravention notice is given may appeal to the appropriate court or tribunal against the notice.

(10)A person who, without reasonable excuse, contravenes a serious contravention notice commits an offence and is liable on summary conviction to a fine.

58Z6Continuing failure to meet standards: registered building control approversE+W

(1)This section applies where—

(a)the regulatory authority has given a registered building control approver one or more serious contravention notices under section 58Z5, and

(b)it appears to the regulatory authority that the way in which the approver exercises their building control functions—

(i)falls short of the standards expected, and

(ii)puts, or may put, the safety of persons in or about buildings at risk,

and is likely to continue to do so.

(2)The regulatory authority may cancel the approver’s registration.

(3)But before cancelling a registered building control approver’s registration under subsection (2) the regulatory authority must—

(a)give the approver notice that it is considering its registration under that subsection, and explain its reasons, and

(b)invite the approver to make representations within a period specified in the notice (which must not be less than 14 days).

(4)Where the regulatory authority cancels a registered building control approver’s registration under subsection (2) it must as soon as reasonably practicable—

(a)notify the approver that it has done so,

(b)give the approver a statement of its reasons, and

(c)notify—

(i)each local authority in England, where the regulatory authority is the regulator, or

(ii)each local authority in Wales, where the regulatory authority is the Welsh Ministers.

(5)A registered building control approver may appeal to the appropriate court or tribunal against the cancellation of its registration under subsection (2).

58Z7Continuing failure to meet standards: local authorities in EnglandE+W

(1)This section applies where—

(a)the regulatory authority is the regulator,

(b)the regulatory authority has given a local authority one or more serious contravention notices under section 58Z5, and

(c)it appears to the regulatory authority that the way in which the local authority exercises their building control functions—

(i)falls short of the standards expected, and

(ii)puts, or may put, the safety of persons in or about buildings at risk,

and is likely to continue to do so.

(2)The regulatory authority may recommend to the Secretary of State that the Secretary of State make an order under section 116(4) (transfer of functions to the Secretary of State or another local authority).

(3)But before making a recommendation under subsection (2) the regulatory authority must—

(a)give the local authority notice that it is considering making a recommendation under that subsection, and explain its reasons, and

(b)invite the authority to make representations within a period specified in the notice (which must not be less than 14 days).

(4)Where the regulatory authority makes a recommendation under subsection (2) it must as soon as reasonably practicable—

(a)notify the local authority that it has done so, and

(b)give the local authority a statement of its reasons.

(5)A local authority may appeal to the tribunal against a recommendation under subsection (2).]

Yn ôl i’r brig

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act without Schedules as a PDF

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open y Ddeddf Gyfan

Y Ddeddf Gyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open y Ddeddf Gyfan heb Atodlenni

Y Ddeddf Gyfan heb Atodlenni you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill