Directive 2011/92/EU of the European Parliament and of the Council of 13 December 2011 on the assessment of the effects of certain public and private projects on the environment (codification) (Text with EEA relevance)

 Help about advanced features

Nodweddion Uwch

Rhagor o Adnoddau

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

Mae hon yn eitem o ddeddfwriaeth sy’n deillio o’r UE

Mae unrhyw newidiadau sydd wedi cael eu gwneud yn barod gan y tîm yn ymddangos yn y cynnwys a chyfeirir atynt gydag anodiadau.Ar ôl y diwrnod ymadael bydd tair fersiwn o’r ddeddfwriaeth yma i’w gwirio at ddibenion gwahanol. Y fersiwn legislation.gov.uk yw’r fersiwn sy’n weithredol yn y Deyrnas Unedig. Y Fersiwn UE sydd ar EUR-lex ar hyn o bryd yw’r fersiwn sy’n weithredol yn yr UE h.y. efallai y bydd arnoch angen y fersiwn hon os byddwch yn gweithredu busnes yn yr UE. EUR-Lex Y fersiwn yn yr archif ar y we yw’r fersiwn swyddogol o’r ddeddfwriaeth fel yr oedd ar y diwrnod ymadael cyn cael ei chyhoeddi ar legislation.gov.uk ac unrhyw newidiadau ac effeithiau a weithredwyd yn y Deyrnas Unedig wedyn. Mae’r archif ar y we hefyd yn cynnwys cyfraith achos a ffurfiau mewn ieithoedd eraill o EUR-Lex. The EU Exit Web Archive legislation_originated_from_EU_p3

Changes over time for: Directive 2011/92/EU of the European Parliament and of the Council (without Annexes)

 Help about opening options

Status:

EU Directives are published on this site to aid cross referencing from UK legislation. Since IP completion day (31 December 2020 11.00 p.m.) no amendments have been applied to this version.

Article 1U.K.

1.This Directive shall apply to the assessment of the environmental effects of those public and private projects which are likely to have significant effects on the environment.

2.For the purposes of this Directive, the following definitions shall apply:

(a)‘project’ means:

  • (a)the execution of construction works or of other installations or schemes,

  • other interventions in the natural surroundings and landscape including those involving the extraction of mineral resources;

(b)‘developer’ means the applicant for authorisation for a private project or the public authority which initiates a project;

(c)‘development consent’ means the decision of the competent authority or authorities which entitles the developer to proceed with the project;

(d)‘public’ means one or more natural or legal persons and, in accordance with national legislation or practice, their associations, organisations or groups;

(e)‘public concerned’ means the public affected or likely to be affected by, or having an interest in, the environmental decision-making procedures referred to in Article 2(2). For the purposes of this definition, non-governmental organisations promoting environmental protection and meeting any requirements under national law shall be deemed to have an interest;

(f)‘competent authority or authorities’ means that authority or those authorities which the Member States designate as responsible for performing the duties arising from this Directive[F1;]

[F2(g) environmental impact assessment means a process consisting of:

(i)

the preparation of an environmental impact assessment report by the developer, as referred to in Article 5(1) and (2);

(ii)

the carrying out of consultations as referred to in Article 6 and, where relevant, Article 7;

(iii)

the examination by the competent authority of the information presented in the environmental impact assessment report and any supplementary information provided, where necessary, by the developer in accordance with Article 5(3), and any relevant information received through the consultations under Articles 6 and 7;

(iv)

the reasoned conclusion by the competent authority on the significant effects of the project on the environment, taking into account the results of the examination referred to in point (iii) and, where appropriate, its own supplementary examination; and

(v)

the integration of the competent authority's reasoned conclusion into any of the decisions referred to in Article 8a.]

[F13. Member States may decide, on a case-by-case basis and if so provided under national law, not to apply this Directive to projects, or parts of projects, having defence as their sole purpose, or to projects having the response to civil emergencies as their sole purpose, if they deem that such application would have an adverse effect on those purposes.]

F34.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Article 2U.K.

[F11. Member States shall adopt all measures necessary to ensure that, before development consent is given, projects likely to have significant effects on the environment by virtue, inter alia, of their nature, size or location are made subject to a requirement for development consent and an assessment with regard to their effects on the environment. Those projects are defined in Article 4.

2. The environmental impact assessment may be integrated into the existing procedures for development consent to projects in the Member States, or, failing this, into other procedures or into procedures to be established to comply with the aims of this Directive.

3. In the case of projects for which the obligation to carry out assessments of the effects on the environment arises simultaneously from this Directive and from Council Directive 92/43/EEC (1) and/or Directive 2009/147/EC of the European Parliament and the Council (2) , Member States shall, where appropriate, ensure that coordinated and/or joint procedures fulfilling the requirements of that Union legislation are provided for.

In the case of projects for which the obligation to carry out assessments of the effects on the environment arises simultaneously from this Directive and Union legislation other than the Directives listed in the first subparagraph, Member States may provide for coordinated and/or joint procedures.

Under the coordinated procedure referred to in the first and second subparagraphs, Member States shall endeavour to coordinate the various individual assessments of the environmental impact of a particular project, required by the relevant Union legislation, by designating an authority for this purpose, without prejudice to any provisions to the contrary contained in other relevant Union legislation.

Under the joint procedure referred to in the first and second subparagraphs, Member States shall endeavour to provide for a single assessment of the environmental impact of a particular project required by the relevant Union legislation, without prejudice to any provisions to the contrary contained in other relevant Union legislation.

The Commission shall provide guidance regarding the setting up of any coordinated or joint procedures for projects that are simultaneously subject to assessments under this Directive and Directives 92/43/EEC, 2000/60/EC, 2009/147/EC or 2010/75/EU.]

[F14. Without prejudice to Article 7, Member States may, in exceptional cases, exempt a specific project from the provisions laid down in this Directive, where the application of those provisions would result in adversely affecting the purpose of the project, provided the objectives of this Directive are met.]

In that event, the Member States shall:

(a)consider whether another form of assessment would be appropriate;

(b)make available to the public concerned the information obtained under other forms of assessment referred to in point (a), the information relating to the decision granting exemption and the reasons for granting it;

(c)inform the Commission, prior to granting consent, of the reasons justifying the exemption granted, and provide it with the information made available, where applicable, to their own nationals.

The Commission shall immediately forward the documents received to the other Member States.

The Commission shall report annually to the European Parliament and to the Council on the application of this paragraph.

[F25. Without prejudice to Article 7, in cases where a project is adopted by a specific act of national legislation, Member States may exempt that project from the provisions relating to public consultation laid down in this Directive, provided the objectives of this Directive are met.

Member States shall inform the Commission of any application of the exemption referred to in the first subparagraph every two years from 16 May 2017 .]

[F1Article 3 U.K.

1. The environmental impact assessment shall identify, describe and assess in an appropriate manner, in the light of each individual case, the direct and indirect significant effects of a project on the following factors:

(a) population and human health;

(b) biodiversity, with particular attention to species and habitats protected under Directive 92/43/EEC and Directive 2009/147/EC;

(c) land, soil, water, air and climate;

(d) material assets, cultural heritage and the landscape;

(e) the interaction between the factors referred to in points (a) to (d).

2. The effects referred to in paragraph 1 on the factors set out therein shall include the expected effects deriving from the vulnerability of the project to risks of major accidents and/or disasters that are relevant to the project concerned.]

Article 4U.K.

1.Subject to Article 2(4), projects listed in Annex I shall be made subject to an assessment in accordance with Articles 5 to 10.

2.Subject to Article 2(4), for projects listed in Annex II, Member States shall determine whether the project shall be made subject to an assessment in accordance with Articles 5 to 10. Member States shall make that determination through:

(a)a case-by-case examination;

or

(b)thresholds or criteria set by the Member State.

Member States may decide to apply both procedures referred to in points (a) and (b).

[F13. Where a case-by-case examination is carried out or thresholds or criteria are set for the purpose of paragraph 2, the relevant selection criteria set out in Annex III shall be taken into account. Member States may set thresholds or criteria to determine when projects need not undergo either the determination under paragraphs 4 and 5 or an environmental impact assessment, and/or thresholds or criteria to determine when projects shall in any case be made subject to an environmental impact assessment without undergoing a determination set out under paragraphs 4 and 5.

4. Where Member States decide to require a determination for projects listed in Annex II, the developer shall provide information on the characteristics of the project and its likely significant effects on the environment. The detailed list of information to be provided is specified in Annex IIA. The developer shall take into account, where relevant, the available results of other relevant assessments of the effects on the environment carried out pursuant to Union legislation other than this Directive. The developer may also provide a description of any features of the project and/or measures envisaged to avoid or prevent what might otherwise have been significant adverse effects on the environment.]

[F25. The competent authority shall make its determination, on the basis of the information provided by the developer in accordance with paragraph 4 taking into account, where relevant, the results of preliminary verifications or assessments of the effects on the environment carried out pursuant to Union legislation other than this Directive. The determination shall be made available to the public and:

(a) where it is decided that an environmental impact assessment is required, state the main reasons for requiring such assessment with reference to the relevant criteria listed in Annex III; or

(b) where it is decided that an environmental impact assessment is not required, state the main reasons for not requiring such assessment with reference to the relevant criteria listed in Annex III, and, where proposed by the developer, state any features of the project and/or measures envisaged to avoid or prevent what might otherwise have been significant adverse effects on the environment.

6. Member States shall ensure that the competent authority makes its determination as soon as possible and within a period of time not exceeding 90 days from the date on which the developer has submitted all the information required pursuant to paragraph 4. In exceptional cases, for instance relating to the nature, complexity, location or size of the project, the competent authority may extend that deadline to make its determination; in that event, the competent authority shall inform the developer in writing of the reasons justifying the extension and of the date when its determination is expected.]

Article 5U.K.

[F11. Where an environmental impact assessment is required, the developer shall prepare and submit an environmental impact assessment report. The information to be provided by the developer shall include at least:

(a) a description of the project comprising information on the site, design, size and other relevant features of the project;

(b) a description of the likely significant effects of the project on the environment;

(c) a description of the features of the project and/or measures envisaged in order to avoid, prevent or reduce and, if possible, offset likely significant adverse effects on the environment;

(d) a description of the reasonable alternatives studied by the developer, which are relevant to the project and its specific characteristics, and an indication of the main reasons for the option chosen, taking into account the effects of the project on the environment;

(e) a non-technical summary of the information referred to in points (a) to (d); and

(f) any additional information specified in Annex IV relevant to the specific characteristics of a particular project or type of project and to the environmental features likely to be affected.

Where an opinion is issued pursuant to paragraph 2, the environmental impact assessment report shall be based on that opinion, and include the information that may reasonably be required for reaching a reasoned conclusion on the significant effects of the project on the environment, taking into account current knowledge and methods of assessment. The developer shall, with a view to avoiding duplication of assessments, take into account the available results of other relevant assessments under Union or national legislation, in preparing the environmental impact assessment report.

2. Where requested by the developer, the competent authority, taking into account the information provided by the developer in particular on the specific characteristics of the project, including its location and technical capacity, and its likely impact on the environment, shall issue an opinion on the scope and level of detail of the information to be included by the developer in the environmental impact assessment report in accordance with paragraph 1 of this Article. The competent authority shall consult the authorities referred to in Article 6(1) before it gives its opinion.

Member States may also require the competent authorities to give an opinion as referred to in the first subparagraph, irrespective of whether the developer so requests.

3. In order to ensure the completeness and quality of the environmental impact assessment report:

(a) the developer shall ensure that the environmental impact assessment report is prepared by competent experts;

(b) the competent authority shall ensure that it has, or has access as necessary to, sufficient expertise to examine the environmental impact assessment report; and

(c) where necessary, the competent authority shall seek from the developer supplementary information, in accordance with Annex IV, which is directly relevant to reaching the reasoned conclusion on the significant effects of the project on the environment.]

4.Member States shall, if necessary, ensure that any authorities holding relevant information, with particular reference to Article 3, make this information available to the developer.

Article 6U.K.

[F11. Member States shall take the measures necessary to ensure that the authorities likely to be concerned by the project by reason of their specific environmental responsibilities or local and regional competences are given an opportunity to express their opinion on the information supplied by the developer and on the request for development consent, taking into account, where appropriate, the cases referred to in Article 8a(3). To that end, Member States shall designate the authorities to be consulted, either in general terms or on a case-by-case basis. The information gathered pursuant to Article 5 shall be forwarded to those authorities. Detailed arrangements for consultation shall be laid down by the Member States.]

[F12. In order to ensure the effective participation of the public concerned in the decision-making procedures, the public shall be informed electronically and by public notices or by other appropriate means, of the following matters early in the environmental decision-making procedures referred to in Article 2(2) and, at the latest, as soon as information can reasonably be provided:]

(a)the request for development consent;

(b)the fact that the project is subject to an environmental impact assessment procedure and, where relevant, the fact that Article 7 applies;

(c)details of the competent authorities responsible for taking the decision, those from which relevant information can be obtained, those to which comments or questions can be submitted, and details of the time schedule for transmitting comments or questions;

(d)the nature of possible decisions or, where there is one, the draft decision;

(e)an indication of the availability of the information gathered pursuant to Article 5;

(f)an indication of the times and places at which, and the means by which, the relevant information will be made available;

(g)details of the arrangements for public participation made pursuant to paragraph 5 of this Article.

3.Member States shall ensure that, within reasonable time-frames, the following is made available to the public concerned:

(a)any information gathered pursuant to Article 5;

(b)in accordance with national legislation, the main reports and advice issued to the competent authority or authorities at the time when the public concerned is informed in accordance with paragraph 2 of this Article;

(c)in accordance with the provisions of Directive 2003/4/EC of the European Parliament and of the Council of 28 January 2003 on public access to environmental information(3), information other than that referred to in paragraph 2 of this Article which is relevant for the decision in accordance with Article 8 of this Directive and which only becomes available after the time the public concerned was informed in accordance with paragraph 2 of this Article.

4.The public concerned shall be given early and effective opportunities to participate in the environmental decision-making procedures referred to in Article 2(2) and shall, for that purpose, be entitled to express comments and opinions when all options are open to the competent authority or authorities before the decision on the request for development consent is taken.

[F15. The detailed arrangements for informing the public, for example by bill posting within a certain radius or publication in local newspapers, and for consulting the public concerned, for example by written submissions or by way of a public inquiry, shall be determined by the Member States. Member States shall take the necessary measures to ensure that the relevant information is electronically accessible to the public, through at least a central portal or easily accessible points of access, at the appropriate administrative level.]

[F16. Reasonable time-frames for the different phases shall be provided for, allowing sufficient time for:

(a) informing the authorities referred to in paragraph 1 and the public; and

(b) the authorities referred to in paragraph 1 and the public concerned to prepare and participate effectively in the environmental decision-making, subject to the provisions of this Article.]

[F27. The time-frames for consulting the public concerned on the environmental impact assessment report referred to in Article 5(1) shall not be shorter than 30 days.]

Article 7U.K.

1.Where a Member State is aware that a project is likely to have significant effects on the environment in another Member State or where a Member State likely to be significantly affected so requests, the Member State in whose territory the project is intended to be carried out shall send to the affected Member State as soon as possible and no later than when informing its own public, inter alia:

(a)a description of the project, together with any available information on its possible transboundary impact;

(b)information on the nature of the decision which may be taken.

The Member State in whose territory the project is intended to be carried out shall give the other Member State a reasonable time in which to indicate whether it wishes to participate in the environmental decision-making procedures referred to in Article 2(2), and may include the information referred to in paragraph 2 of this Article.

2.If a Member State which receives information pursuant to paragraph 1 indicates that it intends to participate in the environmental decision-making procedures referred to in Article 2(2), the Member State in whose territory the project is intended to be carried out shall, if it has not already done so, send to the affected Member State the information required to be given pursuant to Article 6(2) and made available pursuant to points (a) and (b) of Article 6(3).

3.The Member States concerned, each insofar as it is concerned, shall also:

(a)arrange for the information referred to in paragraphs 1 and 2 to be made available, within a reasonable time, to the authorities referred to in Article 6(1) and the public concerned in the territory of the Member State likely to be significantly affected; and

(b)ensure that the authorities referred to in Article 6(1) and the public concerned are given an opportunity, before development consent for the project is granted, to forward their opinion within a reasonable time on the information supplied to the competent authority in the Member State in whose territory the project is intended to be carried out.

[F14. The Member States concerned shall enter into consultations regarding, inter alia, the potential transboundary effects of the project and the measures envisaged to reduce or eliminate such effects and shall agree on a reasonable time- frame for the duration of the consultation period.

Such consultations may be conducted through an appropriate joint body.]

[F15. The detailed arrangements for implementing paragraphs 1 to 4 of this Article, including the establishment of time-frames for consultations, shall be determined by the Member States concerned, on the basis of the arrangements and time-frames referred to in Article 6(5) to (7), and shall be such as to enable the public concerned in the territory of the affected Member State to participate effectively in the environmental decision-making procedures referred to in Article 2(2) for the project.]

[F1Article 8 U.K.

The results of consultations and the information gathered pursuant to Articles 5 to 7 shall be duly taken into account in the development consent procedure.]

[F2Article 8a U.K.

1. The decision to grant development consent shall incorporate at least the following information:

(a) the reasoned conclusion referred to in Article 1(2)(g)(iv);

(b) any environmental conditions attached to the decision, a description of any features of the project and/or measures envisaged to avoid, prevent or reduce and, if possible, offset significant adverse effects on the environment as well as, where appropriate, monitoring measures.

2. The decision to refuse development consent shall state the main reasons for the refusal.

3. In the event Member States make use of the procedures referred to in Article 2(2) other than the procedures for development consent, the requirements of paragraphs 1 and 2 of this Article, as appropriate, shall be deemed to be fulfilled when any decision issued in the context of those procedures contains the information referred to in those paragraphs and there are mechanisms in place which enable the fulfilment of the requirements of paragraph 6 of this Article.

4. In accordance with the requirements referred to in paragraph 1(b), Member States shall ensure that the features of the project and/or measures envisaged to avoid, prevent or reduce and, if possible, offset significant adverse effects on the environment are implemented by the developer, and shall determine the procedures regarding the monitoring of significant adverse effects on the environment.

The type of parameters to be monitored and the duration of the monitoring shall be proportionate to the nature, location and size of the project and the significance of its effects on the environment.

Existing monitoring arrangements resulting from Union legislation other than this Directive and from national legislation may be used if appropriate, with a view to avoiding duplication of monitoring.

5. Member States shall ensure that the competent authority takes any of the decisions referred to in paragraphs 1 to 3 within a reasonable period of time.

6. The competent authority shall be satisfied that the reasoned conclusion referred to in Article 1(2)(g)(iv), or any of the decisions referred to in paragraph 3 of this Article, is still up to date when taking a decision to grant development consent. To that effect, Member States may set time-frames for the validity of the reasoned conclusion referred to in Article 1(2)(g)(iv) or any of the decisions referred to in paragraph 3 of this Article.]

Article 9U.K.

[F11. When a decision to grant or refuse development consent has been taken, the competent authority or authorities shall promptly inform the public and the authorities referred to in Article 6(1) thereof, in accordance with the national procedures, and shall ensure that the following information is available to the public and to the authorities referred to in Article 6(1), taking into account, where appropriate, the cases referred to in Article 8a(3):

(a) the content of the decision and any conditions attached thereto as referred to in Article 8a(1) and (2);

(b) the main reasons and considerations on which the decision is based, including information about the public participation process. This also includes the summary of the results of the consultations and the information gathered pursuant to Articles 5 to 7 and how those results have been incorporated or otherwise addressed, in particular the comments received from the affected Member State referred to in Article 7.]

2.The competent authority or authorities shall inform any Member State which has been consulted pursuant to Article 7, forwarding to it the information referred to in paragraph 1 of this Article.

The consulted Member States shall ensure that that information is made available in an appropriate manner to the public concerned in their own territory.

[F2Article 9a U.K.

Member States shall ensure that the competent authority or authorities perform the duties arising from this Directive in an objective manner and do not find themselves in a situation giving rise to a conflict of interest.

Where the competent authority is also the developer, Member States shall at least implement, within their organisation of administrative competences, an appropriate separation between conflicting functions when performing the duties arising from this Directive.]

Article 10U.K.

[F1Without prejudice to Directive 2003/4/EC, the provisions of this Directive shall not affect the obligation on the competent authorities to respect the limitations imposed by national laws, regulations and administrative provisions, and accepted legal practices with regard to commercial and industrial confidentiality, including intellectual property, and the safeguarding of the public interest.]

Where Article 7 applies, the transmission of information to another Member State and the receipt of information by another Member State shall be subject to the limitations in force in the Member State in which the project is proposed.

[F2Article 10a U.K.

Member States shall lay down rules on penalties applicable to infringements of the national provisions adopted pursuant to this Directive. The penalties thus provided for shall be effective, proportionate and dissuasive.]

Article 11U.K.

1.Member States shall ensure that, in accordance with the relevant national legal system, members of the public concerned:

(a)having a sufficient interest, or alternatively;

(b)maintaining the impairment of a right, where administrative procedural law of a Member State requires this as a precondition;

have access to a review procedure before a court of law or another independent and impartial body established by law to challenge the substantive or procedural legality of decisions, acts or omissions subject to the public participation provisions of this Directive.

2.Member States shall determine at what stage the decisions, acts or omissions may be challenged.

3.What constitutes a sufficient interest and impairment of a right shall be determined by the Member States, consistently with the objective of giving the public concerned wide access to justice. To that end, the interest of any non-governmental organisation meeting the requirements referred to in Article 1(2) shall be deemed sufficient for the purpose of point (a) of paragraph 1 of this Article. Such organisations shall also be deemed to have rights capable of being impaired for the purpose of point (b) of paragraph 1 of this Article.

4.The provisions of this Article shall not exclude the possibility of a preliminary review procedure before an administrative authority and shall not affect the requirement of exhaustion of administrative review procedures prior to recourse to judicial review procedures, where such a requirement exists under national law.

Any such procedure shall be fair, equitable, timely and not prohibitively expensive.

5.In order to further the effectiveness of the provisions of this Article, Member States shall ensure that practical information is made available to the public on access to administrative and judicial review procedures.

Article 12U.K.

1.The Member States and the Commission shall exchange information on the experience gained in applying this Directive.

[F12. In particular, every six years from 16 May 2017 Member States shall inform the Commission, where such data are available, of:

(a) the number of projects referred to in Annexes I and II made subject to an environmental impact assessment in accordance with Articles 5 to 10;

(b) the breakdown of environmental impact assessments according to the project categories set out in Annexes I and II;

(c) the number of projects referred to in Annex II made subject to a determination in accordance with Article 4(2);

(d) the average duration of the environmental impact assessment process;

(e) general estimates on the average direct costs of environmental impact assessments, including the impact from the application of this Directive to SMEs.]

3.On the basis of that exchange of information, the Commission shall if necessary submit additional proposals to the European Parliament and to the Council, with a view to ensuring that this Directive is applied in a sufficiently coordinated manner.

Article 13U.K.

Member States shall communicate to the Commission the texts of the provisions of national law which they adopt in the field covered by this Directive.

Article 14U.K.

Directive 85/337/EEC, as amended by the Directives listed in Annex V, Part A, is repealed, without prejudice to the obligations of the Member States relating to the time limits for transposition into national law of the Directives set out in Annex V, Part B.

References to the repealed Directive shall be construed as references to this Directive and shall be read in accordance with the correlation table in Annex VI.

Article 15U.K.

This Directive shall enter into force on the 20th day following its publication in the Official Journal of the European Union.

Article 16U.K.

This Directive is addressed to the Member States.

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i mabwysiadwyd gan yr UE): Mae'r wreiddiol version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel adopted version that was used for the EU Official Journal
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

Mae’r llinell amser yma yn dangos y fersiynau gwahanol a gymerwyd o EUR-Lex yn ogystal ag unrhyw fersiynau dilynol a grëwyd ar ôl y diwrnod ymadael o ganlyniad i newidiadau a wnaed gan ddeddfwriaeth y Deyrnas Unedig.

Cymerir dyddiadau fersiynau’r UE o ddyddiadau’r dogfennau ar EUR-Lex ac efallai na fyddant yn cyfateb â’r adeg pan ddaeth y newidiadau i rym ar gyfer y ddogfen.

Ar gyfer unrhyw fersiynau a grëwyd ar ôl y diwrnod ymadael o ganlyniad i newidiadau a wnaed gan ddeddfwriaeth y Deyrnas Unedig, bydd y dyddiad yn cyd-fynd â’r dyddiad cynharaf y daeth y newid (e.e. ychwanegiad, diddymiad neu gyfnewidiad) a weithredwyd i rym. Am ragor o wybodaeth gweler ein canllaw i ddeddfwriaeth ddiwygiedig ar Ddeall Deddfwriaeth.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel adopted fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill