9. For the purposes of section 20(1) of the 1975 Act, the following certificates must be in the form prescribed in Schedule 4—
(a)a preliminary certificate given under section 7(1) of the 1975 Act;
(b)an interim certificate given under section 7(2) of the 1975 Act;
(c)a final certificate given under section 7(3) of the 1975 Act;
(d)a certificate of efficient execution of works given under section 7(6) or 8(7) of the 1975 Act(1);
(e)a certificate given under section 10(5) of the 1975 Act(2) as to the report of an inspecting engineer;
(f)a certificate given under section 10(6) of the 1975 Act as to the carrying into effect of safety recommendations;
(g)a certificate given under section 12AA(3) of the 1975 Act(3) as to the satisfaction of the requirements of a direction to prepare a flood plan;
(h)an interim certificate given under section 13(1A) of the 1975 Act;
(i)a certificate given under section 13(2) of the 1975 Act as to the completion and efficient execution of an alteration so as to discontinue a large raised reservoir;
(j)a certificate given under section 14(3) of the 1975 Act as to the report of an engineer;
(k)a certificate given under section 15(2) of the 1975 Act(4) as to the carrying into effect of safety recommendations; or
(l)a referee’s certificate given under section 19(4) of the 1975 Act(5).
Section 8 was amended in relation to England and Wales by section 33 of, and paragraphs 3 and 11 of Schedule 4 to, the Flood and Water Management Act 2010 (c.29) and section 75 of the Water Act 2003 (2003 c.37).
Section 10 was amended in relation to England and Wales by section 33 of, and paragraphs 11 and 12 of Schedule 4 to, the Flood and Water Management Act 2010 (c.29).
Section 12AA was inserted in relation to England and Wales by section 33 of, and paragraph 21 of Schedule 4 to, the Flood and Water Management Act 2010 (c.29).
Section 15 was amended in relation to England and Wales by section 33 of, and paragraph 26 of Schedule 4 to, the Flood and Water Management Act 2010 (c.29) and section 75 of the Water Act 2003 (c.37).
Section 19 was amended in relation to England and Wales by section 33 of, and paragraph 14 and 22 of Schedule 4 to, the Flood and Water Management Act 2010 (c.29).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.
Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: