- Latest available (Revised)
- Original (As made)
There are outstanding changes not yet made by the legislation.gov.uk editorial team to The National Grid (Bramford to Twinstead Reinforcement) Order 2024. Any changes that have already been made by the team appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Article 2
1.—(1) In this Schedule unless the context requires otherwise—E+W
“biodiversity metric” means Biodiversity Metric 3.1 as published by Natural England in April 2022;
“discharging authority” means the body responsible for giving any consent, agreement or approval required by a requirement included in this Order, or further to any document referred to in any requirement, or the local authority in the exercise of functions set out in sections 60 or 61 of the Control of Pollution Act 1974(1);
“HGV” means lorries over 3.5 tonnes maximum gross weight;
“intrusive” means an activity which requires or is facilitated by breaking the surface of the ground;
“lead local flood authority” has the same meaning as in section 6(7) of the Flood and Water Management Act 2010;
“part” means a given geographical section, component or location of the authorised development;
“reinstatement planting” includes, unless otherwise agreed with the relevant planning authority, embedded planting, reinstatement hedgerow or other planting and mitigation planting as each are described in the Landscape and Ecological Management Plan approved pursuant to requirement 4;
“reinstatement planting plan” means the plan referenced at Requirements 9 and 10 and which provides detail on reinstatement planting to be prepared for each stage of the authorised development;
“stage” means a defined stage of the authorised development, the extent of which is shown in a scheme submitted to the relevant planning authority pursuant to Requirement 3;
“start-up and close down activities” means—
arrival and departure of workforce and staff at site and movement to and from places of work;
general refuelling of plant;
site inspections and safety checks;
site meetings inspections and walkovers;
site clean-up (site housekeeping that does not require the use of plant);
general site maintenance; and
low key maintenance and safety checking of plant and machinery.
(2) Where under any of the Requirements the approval or agreement of the relevant planning authority or the relevant highway authority is required, that approval or agreement must be given in writing.
(3) Where any Requirement requires the authorised development to be carried out in accordance or general accordance with matters including a plan, document, or details approved by the relevant planning authority or the relevant highway authority, those matters are to be taken to include any amendments that may subsequently be approved in writing by the relevant planning authority or the relevant highway authority.
(4) Where an approval or agreement is required under the terms of any Requirement or a document referred to in a Requirement, or any Requirement specifies “unless otherwise approved” or “unless otherwise agreed” by the relevant highway authority or the relevant planning authority, such approval or agreement may only be given in relation to minor or immaterial changes and where it has been demonstrated to the satisfaction of the relevant highway authority or the relevant planning authority that the subject matter of the approval or agreement sought will not give rise to any materially new or materially different environmental effects from those assessed in the Environmental Statement.
(5) Unless otherwise provided in this Order, where a Requirement relates to a specific site or work and it specifies “commencement of development”, it refers to the commencement of development on that site or in relation to that work only.
Commencement Information
I1Sch. 3 para. 1 in force at 4.10.2024, see art. 1
2.—(1) The authorised development must commence no later than the expiration of five years beginning with the date on which this Order comes into force.E+W
(2) If any proceedings are begun to challenge the validity of this Order, the period specified in paragraph (1) is extended for the period specified in paragraph (3).
(3) Under paragraph (2) the period is taken to be extended by—
(a)a period equivalent to the period beginning with the day the proceedings are filed and ending on the day they are withdrawn or finally determined, or
(b)if shorter, one year.
(4) Proceedings are not finally determined for the purposes of sub-paragraph (3)(a) if any appeal—
(a)could be brought (ignoring any possibility of an appeal out of time with permission), or
(b)has been made and not withdrawn or finally determined.
Commencement Information
I2Sch. 3 para. 2 in force at 4.10.2024, see art. 1
3.—(1) Unless otherwise agreed with the relevant planning authority, written notice setting out the anticipated programme for the carrying out of pre-commencement operations must be given to the relevant planning authority no less than seven days prior to the date on which those pre-commencement operations are first carried out.E+W
(2) The authorised development may not commence until a written scheme setting out all stages of the authorised development has been submitted to the relevant planning authority.
(3) Any revisions to the written scheme referred to in sub-paragraph (2) above must be submitted to the relevant planning authority in advance of the commencement of the stage of the authorised development to which the revisions relate.
(4) Written notice of the commencement and completion of construction of each stage of the authorised development, and the operational use of each stage of the authorised development, must be given to the relevant planning authority within ten business days of the relevant event occurring.
(5) The authorised development must be carried out in accordance with the written scheme submitted further to sub-paragraph (2) or (3) and, to the extent applicable, in general accordance with the written notice submitted further to sub-paragraph (1).
Commencement Information
I3Sch. 3 para. 3 in force at 4.10.2024, see art. 1
4.—(1) No stage of the authorised development may commence until, for that stage, the following plans as relevant to that stage, have been submitted to and approved by the relevant planning authority (in consultation with Natural England in the case of the landscape and ecological management plan) or other discharging authority as may be appropriate to the relevant plan concerned and in the case of the construction traffic management plan, the relevant highway authority. The relevant plans are—E+W
(a)A construction environmental management plan (which must be substantially in accordance with the outline construction environmental management plan);
(b)A materials and waste management plan (which must be substantially in accordance with the outline materials and waste management plan);
(c)A construction traffic management plan (which must be substantially in accordance with the outline construction traffic management plan);
(d)A landscape and ecological management plan (which must be substantially in accordance with the outline landscape and ecological management plan); and
(e)A public right of way management plan (which must be substantially in accordance with the outline public right of way management plan).
(2) All construction works forming part of the authorised development must be carried out in accordance with the plans listed in paragraph (1), unless otherwise agreed with the relevant planning authority or other discharging authority as may be appropriate to the relevant plan concerned, and in the case of the construction traffic management plan, the relevant highway authority.
(3) For the avoidance of doubt, all pre-commencement operations must be carried out in accordance with the outline construction environmental management plan, the outline materials waste management plan, the outline construction traffic management plan, the outline landscape and ecological management plan and the outline public right of way management plan unless otherwise agreed with the relevant planning authority or other discharging authority as may be appropriate to the relevant plan concerned, and in the case of the Construction Traffic Management Plan, the relevant highway authority.
Commencement Information
I4Sch. 3 para. 4 in force at 4.10.2024, see art. 1
5.—(1) No stage of the authorised development may be brought into operational use until, for that stage, a drainage management plan, to address operational surface water management matters, has been submitted to and approved by the relevant planning authority, after consultation with the lead local flood authority and the relevant highway authority.E+W
(2) The operational use of each stage of the authorised development must be carried out in accordance with the approved drainage management plan referred to in sub-paragraph (1) or with any amended drainage management plan that may subsequently be approved by the relevant planning authority, after consultation with the lead local flood authority and the relevant highway authority.
Commencement Information
I5Sch. 3 para. 5 in force at 4.10.2024, see art. 1
6.—(1) The authorised development must be undertaken in accordance with the archaeological framework strategy and the outline written scheme of investigation.E+W
(2) No stage of the authorised development may commence until either a preservation in situ management plan, or a detailed written scheme of investigation of areas of archaeological interest relevant to that stage (if any), as identified within the outline written scheme of investigation or identified through evaluation work as set out in the outline written scheme of investigation has been submitted to and approved by the relevant planning authority.
(3) Any detailed archaeological works must be carried out in accordance with the approved detailed written scheme of investigation for that stage.
(4) The detailed written scheme of investigation must be in accordance with the outline written scheme of investigation and must identify areas where archaeological works are required and the measures to be taken to protect, record or preserve any significant archaeological remains that may be found and must include—
(a)an assessment of significance and research questions;
(b)the programme of methodology of site investigation and reporting;
(c)the programme for post-investigation assessment;
(d)proposals for providing for the analysis of site investigation and recording;
(e)proposals for providing archive deposition of the analysis and records of the site investigation;
(f)nomination of a competent person or persons/organisation to undertake the works set out within the detailed written scheme of investigation; and
(g)an implementation timetable.
Commencement Information
I6Sch. 3 para. 6 in force at 4.10.2024, see art. 1
7.—(1) Subject to sub-paragraphs (2) to (4), work may only take place between 07.00 and 19.00 Monday to Friday and between 08.00 and 17.00 on Saturdays, Sundays and Bank Holidays (the core working hours), unless otherwise approved by the relevant planning authority.E+W
(2) No piling operations may take place between 19.00 and 07.00, or on Sundays, Bank Holidays or other public holidays, and, unless otherwise agreed with the local highway authority, no HGV deliveries may be made to site between 19.00 and 07.00, or on Sundays, Bank Holidays or other public holidays.
(3) The following operations may take place outside the core working hours referred to in sub-paragraph (1)—
(a)trenchless crossing operations including beneath highways, railway lines, woodlands or watercourses;
(b)the installation and removal of conductors, pilot wires and associated protective netting across highways, railway lines or watercourses;
(c)the jointing of underground cables (save for the cutting of underground cables);
(d)the continuation of operations commenced during the core working hours to a point where they can safely be paused;
(e)any highway works requested by the highway authority to be undertaken on a Saturday, Sunday or a Bank Holiday or outside the core working hours;
(f)the testing or commissioning of any electrical plant installed as part of the authorised development;
(g)the completion of works delayed or held up by severe weather conditions which disrupted or interrupted normal construction activities that the undertaker and its contractor agree forms the critical path for the accepted construction programme. In such cases, the undertaker must, as soon as practicable, notify the relevant planning authority of the disruption or interruption and explain why that work could not be completed within the core working hours referred to in sub-paragraph (1);
(h)activity necessary in the instance of an emergency where there is a risk to persons or property;
(i)security monitoring;
(j)non-intrusive surveys; and
(k)intrusive surveys, in the instance of an emergency where there is a risk to persons or property or following a request made by the relevant planning authority.
(4) The core working hours referred to in sub-paragraph (1) exclude start-up and close down activities up to one hour either side of the core working hours. A 50dBA noise limit (LOAEL) will apply at the nearest noise-sensitive receptors for start-up and close down activities up to one hour either side of the core working hours.
(5) No construction activities may take place between 19.00 and 07.00, or on Sundays, Bank Holidays or other public holidays at—
(a)pylon PCB 64;
(b)pylon 4Y004A;
(c)pylon RB44;
(d)pylon RB7;
(e)pylon RB33;
(f)pylon RB25; and
(g)pylon 4YLA002,
as shown on Figure 4.1 in the environmental statement figures (document reference 6.4(B)).
(6) The severe weather conditions referred to in sub-paragraph 3(g) means any weather which prevents work from taking place during the core working hours referred to in sub-paragraph (1) by reason of physical incapacity (whether for reasons of visibility, ground conditions, power availability, site access or otherwise) or being contrary to safe working practices.
Commencement Information
I7Sch. 3 para. 7 in force at 4.10.2024, see art. 1
8.—(1) Unless otherwise agreed with the relevant planning authority, no stage of the authorised development may commence until, for that stage, a plan showing the trees, groups of trees, woodlands and hedgerows to be retained and/or removed during that stage has been submitted to and approved by the relevant planning authority.E+W
(2) The plan submitted under sub-paragraph (1) must include details of the location, species and condition of the trees, groups of trees, woodlands and hedgerows to be removed and retained during that stage of the authorised development.
(3) The plan submitted under sub-paragraph (1) must be in accordance with the outline landscape and ecological management plan (or the final landscape and ecological management plan if approved pursuant to requirement 4) and the trees and hedgerows to be removed or managed plans.
(4) All trees, groups of trees, woodlands and hedgerows shown on the relevant plan for that stage of the authorised development must be retained and/or removed in accordance with the relevant plan for that stage of the authorised development, unless otherwise approved by the relevant planning authority.
Commencement Information
I8Sch. 3 para. 8 in force at 4.10.2024, see art. 1
9.—(1) Unless otherwise agreed with the relevant planning authority, no stage of the authorised development may be brought into operational use until, for that stage, a reinstatement planting plan for trees, groups of trees, woodlands and hedgerows to be reinstated during that stage has been submitted to and approved by the relevant planning authority.E+W
(2) Unless otherwise agreed with the relevant planning authority, the reinstatement planting plan submitted under sub-paragraph (1) must include a landscape plan for each cable sealing end compound where relevant to that stage, which will show landscape mounds, planting and proposed finishes for hard landscape features.
(3) The reinstatement planting plan submitted under sub-paragraphs (1) and (2) must include a schedule of trees, hedgerows or other plants or seedlings to be planted, noting numbers, species, sizes and planting density of any proposed planting or seedlings.
(4) The reinstatement planting plan submitted under sub-paragraphs (1) and (2) must be in general accordance with the outline landscape and ecological management plan (or the final landscape and ecological management plan if approved pursuant to requirement 4).
Commencement Information
I9Sch. 3 para. 9 in force at 4.10.2024, see art. 1
10.—(1) Unless otherwise agreed with the relevant planning authority, all reinstatement planting works referred to in requirement 9 must be implemented at the earliest opportunity and no later than by the first available planting season after that part of the authorised development to which the reinstatement planting works apply is first brought into operational use.E+W
(2) All reinstatement planting works referred to in requirement 9 must be carried out in accordance with the relevant reinstatement planting plan for that stage of the authorised development, unless otherwise approved by the relevant planning authority.
(3) All reinstatement planting works referred to in requirement 9 must be implemented, monitored and maintained in accordance with the ‘Aftercare’ section of the landscape and ecological management plan approved pursuant to requirement 4.
(4) Any trees or hedgerows planted as part of an approved reinstatement planting plan that, within a period of five years after planting (or such other period as is specified in the landscape and ecological management plan approved pursuant to requirement 4), are removed, die or become in the opinion of the relevant planning authority seriously damaged or diseased, must be replaced in the first available planting season with a specimen of the same species and size as that originally planted, unless otherwise approved by the relevant planning authority.
Commencement Information
I10Sch. 3 para. 10 in force at 4.10.2024, see art. 1
11.—(1) No work to construct, alter or temporarily alter any highway, including any new or existing means of access to a highway to be used by vehicular traffic, may commence until written details of design, layout and reinstatement of those highway works have been submitted to and approved by the relevant highway authority.E+W
(2) The highway works must be constructed and reinstated in accordance with the details approved under sub-paragraph (1).
(3) For the avoidance of doubt, all pre-commencement operations involving the construction or alteration of temporary accesses must be carried out in accordance with sub-paragraphs (1) and (2) unless otherwise agreed with the relevant highway authority
(4) Unless otherwise agreed with the relevant highway authority, the undertaker must—
(a)carry out Stage 1 and Stage 2 road safety audits of the highway works authorised by this Order in accordance with Standard GG 119 (Revision 2) of the Department for Transport’s Design Manual for Roads and Bridges or any superseding Standard;
(b)agree with the relevant highway authority on a case by case basis the need for a Stage 3 and, where applicable, a Stage 4 road safety audit of any elements of the highway works authorised by this Order and, where so agreed, carry out such audit(s) in accordance with Standard GG 119 (Revision 2) of the Department for Transport’s Design Manual for Roads and Bridges or any superseding Standard; and
(c)to the reasonable satisfaction of the highway authority, implement any recommendations to mitigate or remove road safety problems and defects identified in any such road safety audits arising out of the authorised development.
Commencement Information
I11Sch. 3 para. 11 in force at 4.10.2024, see art. 1
12.—(1) In the event that, at some future date, the authorised development, or part of it, is to be decommissioned, a written scheme of decommissioning must be submitted to the relevant planning authority for its approval in consultation with the relevant highway authority, at least six months prior to any decommissioning works.E+W
(2) The approved scheme must be implemented as approved as part of the decommissioning of the authorised development or relevant part of it.
(3) This requirement does not apply to the part of the authorised development and associated development described in Schedule 1 (authorised development) which relates to the dismantling and removal of existing infrastructure or apparatus.
(4) The written scheme of decommissioning submitted under sub-paragraph (1) must include an environmental assessment undertaken in accordance with the laws and regulations applicable at the time it is submitted to the relevant planning authority.
Commencement Information
I12Sch. 3 para. 12 in force at 4.10.2024, see art. 1
13. Unless otherwise agreed with the relevant planning authority, written evidence (in the form of the outputs of the biodiversity metric) demonstrating how at least ten per cent in biodiversity net gain is to be delivered as part of the authorised development must be submitted to the relevant planning authority no later than the date on which that part of the authorised development comprising the transmission electric line forming part of the authorised development is first brought into operational use.E+W
Commencement Information
I13Sch. 3 para. 13 in force at 4.10.2024, see art. 1
14.—(1) Unless otherwise agreed with the relevant planning authority, no stage of the authorised development may commence until, for that stage, a soil management plan prepared in accordance with Chapter 11 of the outline construction environmental management plan (or the final construction environmental management plan if approved pursuant to requirement 4) describing how construction works should be undertaken to minimise effects on the nature and quality of soil has been submitted to and approved by the relevant planning authority.E+W
(2) The construction works for each stage of the authorised development must be carried out in general accordance with the approved soil management plan referred to in sub-paragraph (1), unless otherwise agreed with the relevant planning authority.
Commencement Information
I14Sch. 3 para. 14 in force at 4.10.2024, see art. 1
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: