Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
10.—(1) Notwithstanding any provision in the contract between the relevant intermediary and the end user at the time the scheme benefit was provided to the relevant intermediary, the relevant intermediary must effect the pass-through so that the pass-through amount is provided to the end user as soon as reasonably practicable.
(2) Where the relevant intermediary makes energy, heating and/or hot water available through equipment which automatically charges a tariff per unit of energy, heating and/or hot water used, paid by end users at the time that the energy, heating and/or hot water is made available, the relevant intermediary must as soon as reasonably practicable make such adjustments to its tariff as is necessary to effect the pass-through required under regulation 7(2).
(3) Without prejudice to paragraph (1), a pass-through can be effected, in pounds sterling or pounds sterling per kWh (as appropriate) by—
(a)application of a credit in the next invoice, statement of account or other similar document provided by the relevant intermediary to the end user,
(b)a payment in cash or by any other means, including a bank transfer,
(c)tariff adjustment on tariff equipment,
(d)adjusting the amount of money taken pursuant to a direct debit or the amount of a standing order,
(e)set off against an amount or part of an amount which was owed by the end user to the relevant intermediary at the time at which the scheme benefit was provided to the relevant intermediary in accordance with regulation 7(5),
or a combination of the methods set out in this paragraph, as appropriate.
(4) A relevant intermediary has discharged its duty under regulations 7(2), 9(1) or 9(2), and paragraph (1) in respect of an end user if and to the extent it has taken reasonable steps to notify and effect a pass-through of a just and reasonable pass-through amount to that end user but is unable to do so.
(5) An end user has no right to a pass-through amount if the relevant intermediary has discharged its duty under regulations 7(2), 9(1) or 9(2), and paragraph (1) pursuant to paragraph (4) and a period of six months has elapsed after the scheme benefit concerned was provided to the relevant intermediary.
(6) If the contract between the relevant intermediary and the end user expires or is terminated before the pass-through required by these Regulations is effected (such that the full value of the pass-through amount has not been provided to the end user), the relevant intermediary must effect a pass through to the end user to reflect the end user’s entitlement (or remaining entitlement) under these Regulations as soon as reasonably practicable following such expiry or termination.
Commencement Information
I1Reg. 10 in force at 12.1.2023, see reg. 1(1)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: