The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2021

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening Options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Amendments to Part 3 (Requirements) of Schedule 1 (Authorised Project)

5.  Part 3 (Requirements) of Schedule 1 (Authorised Project) is amended as follows—

(a)in paragraph 5(8B)(b) for “3,000 kilojoules” substitute “4,000 kilojoules”.

(b)in Paragraph 6(1) for “Wind” substitute “Within Work No. 1A, wind”.

(c)after paragraph 6 insert—

6A.(1) Within Work No. 1(B), wind turbine generator foundation structures must be of 1 or more of the following foundation options: monopole, multi-leg or gravity base.

(2) No wind turbine generator foundation structure employing a footing of driven piles may—

(a)have more than 6 driven piles;

(b)in the case of single-pile structures, have a pile diameter exceeding 12 metres or employ a hammer energy during installation exceeding 4,000 kilojoules;

(c)in the case of structures with 2 or more piles, have a pile diameter exceeding 3.5 metres or employ a hammer energy during installation exceeding 2,300 kilojoules.

(3) No wind turbine generator foundation may have—

(a)a main supporting structure exceeding 61 metres in width;

(b)a seabed footprint (excluding subsea scour protection) exceeding 2,376 square metres;

(c)a seabed footprint (including subsea scour protection) exceeding 5,675 square metres.

(4) The foundations for wind turbine generators must be in accordance with the wave reflection co-efficient values set out in Table 3.6 in Chapter 5, Appendix B (foundation characterisation study) of the environmental statement.;

(d)in paragraph 9(3)(b) for “1 fibre-optic cable’ substitute “2 fibre-optic cables”.

(e)in paragraph 13(6)(b) after “(see Condition 16(a)” insert “Pre-construction plans and documentation: Array location and layout plan”.

(f)in paragraph 14 after “Condition 22 (Aids to Navigation) of Marine Licence 3 or” delete “4” and insert “Condition 23 (Aids to Navigation) of Marine Licence 4 ”.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources