Search Legislation

The Wheelabrator Kemsley K3 Generating Station Order 2021

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

PART 1REQUIREMENTS

Commencement of the authorised development

2.  The authorised development must commence within five years of the date on which this Order comes into force.

Notice of commissioning

3.—(1) Notice of commencement of commissioning of Work No 1 must be given to the relevant planning authority within 7 days of the date on which commissioning is commenced.

(2) Notice of completion of commissioning of Work No 1 must be given to the relevant planning authority within 7 days of the date on which commissioning is completed.

Decommissioning

4.—(1) Within six months after it notifies the relevant planning authority that it intends to decommission the K3 Generating Station, the undertaker must submit to the relevant planning authority for its approval a written decommissioning environmental management plan for that generating station.

(2) Decommissioning works must not be carried out until the relevant planning authority has approved the scheme.

(3) The decommissioning environmental management plan submitted and approved must include details of—

(a)the buildings to be demolished;

(b)the means of removal of the materials resulting from the decommissioning works;

(c)the phasing of the demolition and removal works;

(d)all measures necessary for the protection from the potential environmental effects pursuant to decommissioning;

(e)any restoration works to restore the Order land to a condition agreed with the relevant planning authority;

(f)the phasing of any restoration works;

(g)a timetable for the implementation of the scheme.

(4) The undertaker must implement the scheme as approved and is responsible for the costs of the decommissioning works.

Fuel storage

5.—(1) All fuels, oils and other liquids with the potential to contaminate the Order land shall be stored in a secure bonded area in order to prevent any accidental or unauthorised discharge to the ground.

(2) The area for storage shall not drain to any surface water system.

(3) Where it is proposed to store more than 200 litres of any type of oil must be stored in accordance with the provisions of the Control of Pollution (Oil Storage) (England) Regulations 2001(1).

(4) Where a drum or barrel has a capacity less than 200 litres a drip tray capable of retaining 25% of the maximum capacity of the drum or barrel may be used in lieu of storing the drum or barrel in the secure bonded area.

Rail and water transportation strategy

6.  The K3 Generating Station must be operated in accordance with the approved K3 rail and water transportation strategy.

Amendments to approved plans, etc.

7.—(1) With respect to any approved plans, the undertaker may submit to the relevant planning authority for approval any amendments to the approved plans and following any such approval by the relevant planning authority the approved plans are to be taken to include the amendments approved pursuant to this paragraph.

(2) Approval under sub-paragraph (1) for any amendments to the parameters must not be given except where it has been demonstrated to the satisfaction of the relevant planning authority that the subject-matter of the approval sought does not give rise to any materially new or materially different environmental effects in comparison with the authorised development as approved (as identified in the environmental statement).

Works in the vicinity of gas apparatus

8.—(1) No work involving excavations shall take place within 3 metres of gas apparatus belonging to Southern Gas Networks PLC unless the undertaker has first obtained written consent from Southern Gas Networks PLC for those works to proceed.

(2) The undertaker shall provide such information as Southern Gas Networks PLC may reasonably require in order for it to respond to a request for consent under sub-paragraph (1).

Approved details

9.  The authorised development must be carried out in accordance with the K3 Generation Station approved plans and documents as listed in Part 2 of this Schedule.

Operational traffic and travel plans

10.—(1) The number of Heavy Goods Vehicle Movements to and from the K3 Generating Station shall not exceed 348 movements per day until the following have been submitted to and, after consultation with the relevant highway authority, approved by the relevant planning authority:

(a)a written operational traffic routing and management plan; and,

(b)a written travel plan for operational staff.

(2) The plan submitted and approved under sub-paragraph (1)(a) must be in accordance with the draft K3 operational traffic routing and management plan certified by the Secretary of State under article 16.

(3) The plan submitted and approved under sub-paragraph (1)(b) must be in accordance with the draft K3 travel plan certified by the Secretary of State under article 16.

(4) The plans referred to in sub-paragraphs (1)(a) and (1)(b) must be implemented as approved.

(5) Subject to paragraph (1), the total maximum number of Heavy Goods Vehicle Movements to and from the K3 Generating Station shall not exceed a combined total of 416 movements per day subject to any prior written variation as approved by the relevant planning authority

(6) Sub-paragraphs (1) to (5) do not apply to waste deliveries originating from and returning to the railway depot at Ridham Docks accessing and egressing the K3 Generating Station by the use of Ridham Dock Road.

Trees

11.—(1) All trees and shrubs planted under the approved Landscape Masterplan shall be maintained for a period of 5 years.

(2) Any trees or shrubs that either die, are lost, damaged or become diseased during this 5 year period shall be replaced with a tree or shrub of the same species within the next available planting season.

Surface water drainage

12.  All surface water drainage from the authorised development discharging to a local water course shall be attenuated for a 1:100 year return storm with a limited discharge of 7 litres per second per hectare or the equivalent run off from a greenfield site for a 1:2 storm.

Combined heat and power

13.—(1) Within 12 months of ceasing to supply heat and/or power to the Kemsley Paper Mill, the undertaker must submit to the relevant planning authority for its approval a strategy (“the CHP strategy”).

(2) The CHP strategy submitted and approved must—

(a)consider the opportunities that reasonably exist at the time of submission for the export of heat and/or power from the K3 Generating Station to other users; and

(b)include a list of actions (if any) that the undertaker is reasonably to take (without material additional cost to the undertaker) to increase the potential for the export of heat from the K3 Generating Station to other users.

(3) The undertaker must take such actions as are included, within the timescales specified, in the approved CHP strategy.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources