4.—(1) The licence holder must—
(a)notify the MMO local office of the commencement of the first instance of any licensed activity at least 5 working days prior to the commencement of that licensed activity;
(b)notify the MMO local office of the completion of the licensed activities within 10 working days of such completion; and
(c)notify the Source Data Receipt team, UK Hydrographic Office, Taunton, Somerset, TA1 2DN (email: sdr@ukho.gov.uk) of the completion of the licensed activities within 2 weeks of the date of completion of the licensed activities;
(d)send a copy of the notification required under sub-paragraph (c) to the MMO Marine Licensing Team within 1 week of issue; and
(e)ensure that a notice to mariners is issued at least 10 working days prior to the commencement of the licensed activities, or any part of them, advising of the start date and the expected vessel routes from the local construction ports to the relevant location.
(2) Except in case of emergency, the licence holder must notify the MMO local office of the date of commencement and anticipated duration of any temporary closure of any part of the river Yare under the powers conferred by article 23(2) or (4) (temporary suspension of navigation in connection with the authorised development) of the Order at least 10 working days prior to any such temporary closure.
(3) In sub-paragraph (2) “emergency” has the meaning given to it by article 23(11) of the Order.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: