1. This Order may be cited as the North London Heat and Power Generating Station (Amendment) Order 2018 and comes into force on 20th July 2018.
2.—(1) The North London Heat and Power Generating Station Order 2017 is amended as follows.
(2) In paragraph 1(1) of Schedule 1 (Authorised Development) before “megawatts”, for “70” substitute “78”.
Signed by authority of the Secretary of State for Business, Energy and Industrial Strategy
Gareth Leigh
Head of Energy Infrastructure Planning
Department for Business, Energy and Industrial Strategy
19th July 2018
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: