The North London Heat and Power Generating Station (Amendment) Order 2018

Citation and commencement

1.  This Order may be cited as the North London Heat and Power Generating Station (Amendment) Order 2018 and comes into force on 20th July 2018.

Amendment to the North London Heat and Power Generating Station Order 2017

2.—(1) The North London Heat and Power Generating Station Order 2017 is amended as follows.

(2) In paragraph 1(1) of Schedule 1 (Authorised Development) before “megawatts”, for “70” substitute “78”.

Signed by authority of the Secretary of State for Business, Energy and Industrial Strategy

Gareth Leigh

Head of Energy Infrastructure Planning

Department for Business, Energy and Industrial Strategy

19th July 2018