22.—(1) The process for the award of licences shall consist of the procedure set out in Part 6 (“principal stage”), the procedure set out in Part 7 (“assignment stage”) and the procedure set out in Part 8 (“grant stage”).
(2) During the principal stage, OFCOM shall determine the total number of 2.3 GHz lots and the total number of 3.4 GHz lots which each bidder wins, but not the particular numbered 2.3 GHz lots and particular numbered 3.4 GHz lots.
(3) Following completion of the principal stage, OFCOM shall determine the particular numbered 2.3 GHz lots and particular numbered 3.4 GHz lots that are to be assigned to the winning bidders in accordance with the procedure set out in the assignment stage.
(4) Following completion of the assignment stage, OFCOM shall grant licences authorising the use of the frequencies determined in accordance with the grant stage.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: