- Latest available (Revised)
- Original (As made)
This is the original version (as it was originally made).
1. These Regulations may be cited as the Construction (Design and Management) Regulations 2015 and come into force on 6th April 2015 immediately after the Mines Regulations 2014(1).
2.—(1) In these Regulations—
“the 1974 Act” means the Health and Safety at Work etc. Act 1974;
“the 2007 Regulations” means the Construction (Design and Management) Regulations 2007(2);
“the Management Regulations” means the Management of Health and Safety at Work Regulations 1999(3);
“business” means a trade, business or other undertaking (whether for profit or not);
“client” means any person for whom a project is carried out;
“construction phase” means the period of time beginning when construction work in a project starts and ending when construction work in that project is completed;
“construction phase plan” means a plan drawn up under regulations 12 or 15;
“construction site” includes any place where construction work is being carried out or to which the workers have access, but does not include a workplace within the site which is set aside for purposes other than construction work;
“construction work” means the carrying out of any building, civil engineering or engineering construction work and includes—
the construction, alteration, conversion, fitting out, commissioning, renovation, repair, upkeep, redecoration or other maintenance (including cleaning which involves the use of water or an abrasive at high pressure, or the use of corrosive or toxic substances), de-commissioning, demolition or dismantling of a structure;
the preparation for an intended structure, including site clearance, exploration, investigation (but not site survey) and excavation (but not pre-construction archaeological investigations), and the clearance or preparation of the site or structure for use or occupation at its conclusion;
the assembly on site of prefabricated elements to form a structure or the disassembly on site of the prefabricated elements which, immediately before such disassembly, formed a structure;
the removal of a structure, or of any product or waste resulting from demolition or dismantling of a structure, or from disassembly of prefabricated elements which immediately before such disassembly formed such a structure;
the installation, commissioning, maintenance, repair or removal of mechanical, electrical, gas, compressed air, hydraulic, telecommunications, computer or similar services which are normally fixed within or to a structure,
but does not include the exploration for, or extraction of, mineral resources, or preparatory activities carried out at a place where such exploration or extraction is carried out;
“contractor” means any person (including a non-domestic client) who, in the course or furtherance of a business, carries out, manages or controls construction work;
“design” includes drawings, design details, specifications and bills of quantities (including specification of articles or substances) relating to a structure, and calculations prepared for the purpose of a design;
“designer” means any person (including a client, contractor or other person referred to in these Regulations) who in the course or furtherance of a business—
prepares or modifies a design; or
arranges for, or instructs, any person under their control to do so,
relating to a structure, or to a product or mechanical or electrical system intended for a particular structure, and a person is deemed to prepare a design where a design is prepared by a person under their control;
“domestic client” means a client for whom a project is being carried out which is not in the course or furtherance of a business of that client;
“excavation” includes any earthwork, trench, well, shaft, tunnel or underground working;
“the general principles of prevention” means the general principles of prevention specified in Schedule 1 to the Management Regulations;
“health and safety file” means a file prepared under regulation 12(5);
“inspector for the Executive” means an inspector within the meaning given in section 53(1) of the 1974 Act(4);
“loading bay” means any facility for loading or unloading;
“place of work” means any place which is used by any person at work for the purposes of construction work or for the purposes of any activity arising out of or in connection with construction work;
“pre-construction information” means information in the client’s possession or which is reasonably obtainable by or on behalf of the client, which is relevant to the construction work and is of an appropriate level of detail and proportionate to the risks involved, including—
information about—
the project;
planning and management of the project;
health and safety hazards, including design and construction hazards and how they will be addressed; and
information in any existing health and safety file;
“pre-construction phase” means any period of time during which design or preparatory work is carried out for a project and may continue during the construction phase;
“principal contractor” means the contractor appointed under regulation 5(1)(b) to perform the specified duties in regulations 12 to 14;
“principal designer” means the designer appointed under regulation 5(1)(a) to perform the specified duties in regulations 11 and 12;
“project” means a project which includes or is intended to include construction work and includes all planning, design, management or other work involved in a project until the end of the construction phase;
“site rules” means rules which are drawn up for a particular construction site and are necessary for health or safety purposes;
“structure” means—
any building, timber, masonry, metal or reinforced concrete structure, railway line or siding, tramway line, dock, harbour, inland navigation, tunnel, shaft, bridge, viaduct, waterworks, reservoir, pipe or pipeline, cable, aqueduct, sewer, sewage works, gasholder, road, airfield, sea defence works, river works, drainage works, earthworks, lagoon, dam, wall, caisson, mast, tower, pylon, underground tank, earth retaining structure or structure designed to preserve or alter any natural feature and fixed plant;
any structure similar to anything specified in paragraph (a);
any formwork, falsework, scaffold or other structure designed or used to provide support or means of access during construction work,
and any reference to a structure includes part of a structure;
“traffic route” means a route for pedestrian traffic or for vehicles and includes any doorway, gateway, loading bay or ramp;
“vehicle” includes any mobile work equipment;
“work equipment” means any machinery, appliance, apparatus, tool or installation for use at work (whether exclusively or not);
“working day” means any day on which construction work takes place;
“workplace” means a workplace within the meaning of regulation 2(1) of the Workplace (Health, Safety and Welfare) Regulations 1992(5) other than a construction site.
(2) Any reference in these Regulations to a plan, rule, document, report or copy includes a copy or electronic version which is—
(a)capable of being retrieved or reproduced when required; and
(b)secure from loss or unauthorised interference.
3. These Regulations apply—
(a)in Great Britain; and
(b)to premises and activities outside Great Britain to which sections 1 to 59 and 80 to 82 of the 1974 Act apply by virtue of articles 9 and 11(1)(a) of the Health and Safety at Work etc. Act 1974 (Application outside Great Britain) Order 2013(6).
S.I. 2007/320, as amended by S.I. 2012/632, 2013/1471, 2013/1666 and 2014/469.
S.I. 1999/3242, as amended by S.I. 2003/2457, 2007/320, 2010/93 and 2013/1667. S.I. 2005/1541 amends the instrument in relation to England and Wales and S.S.I. 2006/457 in relation to Scotland.
There are amendments to section 53(1) of the 1974 Act but none is relevant.
S.I. 1992/3004; the definition of “workplace” in regulation 2(1) was amended by S.I. 2002/2174.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: