13.—(1) No authorised development shall commence until a Construction Environmental Management Plan (“CEMP”) has, after consultation with Natural Resources Wales, been submitted to and approved by the relevant planning authorities. The CEMP must reflect the proposals set out in the draft CEMP set out at appendix 4.2 of volume 3 of the environmental statement including:
(a)traffic and access;
(b)air quality and dust;
(c)ecology and nature conservation;
(d)water protection and management;
(e)noise management;
(f)waste and materials management; and
(g)a complaints procedure.
(2) All construction works must be undertaken in accordance with the approved CEMP, or with such changes to that document as agreed by the relevant planning authorities.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: