The South Hook Combined Heat and Power Plant Order 2014

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

  1. Introductory Text

  2. 1.Citation and commencement

  3. 2.Interpretation

  4. 3.Development consent etc. granted by the Order

  5. 4.Procedure in relation to certain approvals etc. under requirements

  6. 5.Maintenance of authorised development

  7. 6.Operation of generating station

  8. 7.Consent to transfer benefit of Order

  9. 8.Defence to proceedings in respect of statutory nuisance

  10. 9.Access to works

  11. 10.Discharge of water

  12. 11.Authority to survey and investigate and remediate the land

  13. 12.Application of landlord and tenant law

  14. 13.Operational land for purposes of the 1990 Act

  15. 14.Carbon Capture Readiness

  16. 15.Certification of plans etc

  17. 16.Arbitration

  18. Signature

    1. Expand +/Collapse -

      SCHEDULE 1

      AUTHORISED DEVELOPMENT

    2. Expand +/Collapse -

      SCHEDULE 2

      REQUIREMENTS

      1. 1.Interpretation

      2. 2.Time limits

      3. 3.Commencement of authorised development

      4. 4.Commencement and completion of commissioning

      5. 5.Detailed design approval

      6. 6.Provision, implementation and maintenance of landscaping

      7. 7.Fencing and other means of enclosure

      8. 8.Drainage and aerial emissions

      9. 9.Contaminated land and groundwater

      10. 10.Archaeology

      11. 11.Ecological management plan

      12. 12.Code of Construction Practice

      13. 13.Construction Environmental Management Plan

      14. 14.Construction Traffic Management Plan

      15. 15.Local Liaison Committee

      16. 16.External lighting

      17. 17.Construction hours

      18. 18.Accumulations and deposits

      19. 19.Travel plan

      20. 20.European protected species

      21. 21.Restoration of land used temporarily for construction

      22. 22.Safety

      23. 23.Carbon capture and storage

      24. 24.Decommissioning

      25. 25.Requirement for written approval

      26. 26.Amendments to approved details

  19. Explanatory Note

Back to top

Options/Help