23. No phase of the authorised development is to commence until a surface water drainage scheme for that phase based on sustainable drainage principles and an assessment of the hydrological and hydrogeological context of the development in accordance with the Surface Water Drainage Strategy submitted with the application at appendix E1 of the environmental statement (Document 6.2) has been submitted to and approved in writing by the relevant planning authority or in accordance with such other approval process that may be prescribed under the Flood and Water Management Act 2010. The scheme must include:
(a)provision for limiting the surface water run-off generated by all rainfall events up to the 1:100 year plus 20% (for climate change) critical rain storm so that it will not exceed the run-off from the undeveloped site and not increase the risk of flooding off-site;
(b)provision of surface water run-off attenuation storage to accommodate the difference between the allowable discharge rates and all rainfall events up to the 1:100 year plus 20% (for climate change) critical rain storm;
(c)detailed design (plans, cross sections and calculations) in support of any surface water drainage scheme, including details of any attenuation system, and the outfall arrangements; and
(d)details of how the scheme is to be maintained and managed after completion.
The scheme must subsequently be implemented in accordance with the approved details or in accordance with any variations to the details agreed in writing by the relevant planning authority prior to the completion of the authorised development.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: