- Latest available (Revised)
- Original (As made)
This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
5.—(1) The undertaker shall, before commencing construction of any specified work, including any temporary works, supply to MSCC proper and sufficient plans of that work and such further particulars available to it as MSCC may within 14 days of the submission of the plans reasonably require for the reasonable approval of the engineer and shall not commence the construction of any specified work except in accordance with such plans as have been approved in writing by the engineer or settled by arbitration.
(2) The approval of the engineer under sub-paragraph (1) shall not be unreasonably withheld or delayed, and if within 42 days after such plans (including any other particulars reasonably required under sub-paragraph (1)) have been supplied to MSCC the engineer has not intimated disapproval of those plans and the grounds of disapproval the engineer shall be deemed to have approved the plans as submitted.
(3) When signifying approval of the plans the engineer may specify—
(a)any protective work to be carried out before the commencement of a specified work (whether temporary or permanent) that may be reasonably required to prevent detriment; and
(b)such other requirements as may be reasonably necessary to prevent detriment but not involving alteration to the basic design of the specified works,
and such protective work shall be constructed by the undertaker or (if the undertaker so elects) MSCC without unnecessary delay and the undertaker shall not commence the construction of any specified work until the engineer has notified the undertaker that the protective work has been completed to the engineer’s reasonable satisfaction.
(4) The approval of the engineer under sub-paragraph (3) shall not be unreasonably withheld or delayed, and if by the end of the period of 14 days beginning with the date on which the engineer is notified of the completion of such protective work the engineer has not intimated disapproval and the grounds of disapproval the engineer shall be deemed to have approved the protective work.
(5) MSCC shall at all times afford reasonable facilities to the undertaker and its agents for access to any protective works carried out by MSCC under this paragraph during their construction and shall supply the undertaker with such information as it may reasonably require with regard to such protective works or the method of constructing them.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: