1.—(1) These Regulations may be cited as the Wireless Telegraphy (Licence Charges) (Amendment) Regulations 2009 and shall come into force on 13th February 2009.
(2) In these Regulations “the principal Regulations” means the Wireless Telegraphy (Licence Charges) Regulations 2005(1).
(3) These Regulations shall not extend to the Bailiwick of Guernsey.
2. The principal Regulations shall be amended in accordance with the following provisions of these Regulations.
3. In regulation 3 (interpretation) in paragraph (7)—
(a)omit “a Satellite (Aircraft Earth Station) Licence,”; and
(b)omit “and a Satellite (Earth Station on board Vessel) Licence”.
4.—(1) In Schedule 2 (licence charges and payment intervals) under the heading “Satellite Services”—
(a)in relation to the licence class “Satellite (Aircraft Earth Station)” omit all of the entries in Columns 1 to 4;
(b)in relation to the licence class “Satellite (Earth Station on Board Train)” omit all of the entries in Columns 1 to 4; and
(c)in relation to the licence class “Satellite (Earth Station Network)” for the entries in Columns 1 to 4 substitute the following entries—
“Satellite (Earth Station Network) | £200 | 12 months | |
---|---|---|---|
For each terminal requiring technical coordination by Ofcom £200.” |
(2) In this regulation—
(a)the column headed “Class of licence” in Schedule 2 to the principal Regulations shall be designated as “Column 1”;
(b)the column headed “Fixed sums” in Schedule 2 to the principal Regulations shall be designated as “Column 2”;
(c)the column headed “Variable sums” in Schedule 2 to the principal Regulations shall be designated as “Column 3”; and
(d)the column headed “Prescribed payment interval” in Schedule 2 to the principal Regulations shall be designated as “Column 4”.
5.—(1) Schedule 8 (fees payable for satellite (permanent earth station), (transportable earth station) and (transportable very small aperture terminal) licences) shall be amended in accordance with paragraph (2).
(2) In relation to Part 2 (band factor for calculating the appropriate sum for a satellite (permanent earth station) licence)—
(a)in the first row of Column 3, for “1.54” substitute “2.33”;
(b)in the second row of Column 3 for “1.23” substitute “1.72”; and
(c)in the third row of Column 3 for “0.87” substitute “1.00”.
Ed Richards
Chief Executive Officer
For and by the authority of the Office of Communications
20th January 2009
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: