Regulation 3

SCHEDULE 1CASES IN WHICH NO FEE IS PAYABLE

1.  No fee shall be payable in respect of a request where, on the date of such request, there is in effect a written agreement between the undertaker and the authority under which the undertaker agrees to make a financial contribution to the authority’s costs incurred in handling requests.

2.  In paragraphs 3, 4, 5 and 6 below:

“deemed refusal” means deemed refusal of a request pursuant to paragraph 30(3) of the Schedule, and “deemed to be refused” shall be construed accordingly;

“operation” means any operation, work, matter or scheme (including any arrangements with respect to a matter, any bringing into use of works or any additional details) for which approval is required; and

“similar request” means one further request which is made to the same authority and which relates solely to:

(a)

the whole or part of the same site as that to which an earlier request related (and to no other land); and

(b)

an operation which is, in the opinion of the authority, of the same character or description as that which was the subject of the earlier request.

3.  Where a request for which the prescribed fee has been paid is withdrawn, and within a period of 12 months beginning with the date of the receipt by the authority of the request, a similar request is made, no fee shall be payable in respect of that similar request.

4.  Where:

(a)a request for which the prescribed fee has been paid is refused by the authority or is deemed to be so refused;

(b)no appeal is made in respect of the refusal or deemed refusal; and

(c)within a period of 12 months beginning with the date of such refusal or deemed refusal, a similar request is made –

no fee shall be payable in respect of that similar request.

5.  Where:

(a)a request for which the prescribed fee has been paid is refused, and an appeal is made in respect of it;

(b)the appeal is dismissed; and

(c)within a period of 12 months beginning with the date of the dismissal of the appeal, a similar request is made –

no fee shall be payable in respect of that similar request.

6.  Where:

(a)a request for which the prescribed fee has been paid is deemed to be refused, and an appeal is made in respect of it;

(b)within a period of 12 months beginning with the date of the expiry of the appropriate period mentioned in paragraph 30(4) of the Schedule, a similar request is made; and

(c)the appeal has not, on or before the date of making of that similar request, been determined in favour of the appellant –

no fee shall be payable in respect of that similar request.

Regulation 4

SCHEDULE 2TABLE OF FEES PAYABLE

Category of development for

which approval is sought:

Fee Payable

1. PLANS AND SPECIFICATIONS FOR THE FOLLOWING WORKS

A.

(i)

The erection, construction, alteration or extension of a building (including any transformer or telecommunications mast) excluding anything in C below

(ii)

The erection, construction, alteration or extension of any fences, walls or other barriers (including bunds) for visual or noise screening or dust suppression, or any other fences or walls

(iii)

The erection, construction or installation of lighting equipment

(a)

Where no gross floor space is to be created by the development, £170;

(b)

where the area of gross floor space to be created by the development does not exceed 40 square metres, £170;

(c)

where the area of gross floor space to be created by the development exceeds 40 square metres but does not exceed 75 square metres, £335;

(d)

where the area of gross floor space to be created by the development exceeds 75 square metres but does not exceed 3750 square metres £335 for each 75 square metres or part thereof of that area; and

(e)

where the area of gross floor space to be created by the development exceeds 3750 square metres, £16,565 and an additional £100 for each 75 square metres or part thereof subject to a maximum of £250,000.

B. Where no gross floor space is to be created by the development£170;
C. Construction, alteration or extension of any terracing, cuttings, embankments or other earth works.£170 for each 0.1 hectares or part thereof of the site, subject to a maximum of £1,700.
D. The erection, construction, alteration or extension of a pedestrian access to the railway line.£170
E. The disposal of waste or spoil or the excavations of bulk materials from borrow pits.£170 for each 0.1 hectare or part thereof of the site area, subject to a maximum of £25,500.
F. Additional Details Request£85
2. CONSTRUCTION ARRANGEMENTS
Road transport£170
Handling of re-usable spoil or top soil£170
Storage sites£170
Construction camps£170
Screening£170
Artificial lighting£170
Suppression of dust£170
Mud on highway£170
3. BRINGING INTO USE
Bringing into use works referred to in paragraph 9(3) or 17(3) of the Schedule.£170
4. MITIGATION OR SITE RESTORATION SCHEMES
Mitigation or site restoration schemes.£170

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources