PART 1PRELIMINARY

Citation and commencement

1.—(1) This Order may be cited as the Teesport (Land Acquisition) Order 2008 and shall come into force on 21st May 2008.

(2) The Teesport Acts and Orders 1966 to 2008(1) and this Order may be cited together as the Teesport Acts and Orders 1966 to 2008.

Interpretation

2.—(1) In this Order—

“the 1961 Act” means the Land Compensation Act 1961(2);

“the 1965 Act” means the Compulsory Purchase Act 1965(3);

“address” includes any number or address used for the purposes of electronic transmission;

“the book of reference” means the book of reference certified by the Secretary of State as the book of reference for the purposes of this Order;

“the Company” means PD Teesport Limited, a company incorporated under the Companies Act 1985(4), whose registered number is 2636007;

“electronic transmission” means a communication transmitted—

(a)

by means of an electronic communications network; or

(b)

by other means but while in electronic form;

“harbour” has the same meaning as in section 3 (Interpretation) of the Tees and Hartlepools Port Authority Act 1966(5);

“the land plans” means the plans certified by the Secretary of State as the land plans for the purposes of this Order;

“Northern Gateway Container Terminal” means the development of that part of the harbour for which planning permission was granted by Redcar and Cleveland Borough Council on 4th October 2007 and which includes the area in the River Tees to be reclaimed under the provisions of the Teesport Harbour Revision Order 2008(6);

“the tribunal” means the Lands Tribunal; and

“the undertaking” means the harbour undertaking of the Company as authorised from time to time.

(2) References in this Order to rights over land include references to rights to do, or to place and maintain, anything in, on or under land or in the air-space over its surface.

(3) All measurements stated in any description of lands in the book of reference shall be construed as if the words “or thereabouts” were inserted after each measurement.

PART 2ACQUISITION AND POSSESSION OF LAND

Power to acquire land

3.—(1) Subject to paragraph (2), the Company may acquire compulsorily—

(a)so much of the land shown coloured pink and edged black on the land plans and described in the book of reference; or

(b)such estates, interests, easements, or other rights in or over the land, as may be required for, or in connection with, the Northern Gateway Container Terminal,

and may use any land so acquired for, or in connection with, the Northern Gateway Container Terminal or for any other purposes ancillary to the undertaking.

(2) The Company shall not under the powers of this Order acquire compulsorily any interest held by BOC Limited in the land numbered 10 on the land plans.

(3) This article is subject to article 6 (temporary use of land for construction of works).

Application of Part 1 of the Compulsory Purchase Act 1965

4.—(1) Part 1 of the 1965 Act, in so far as not modified by or inconsistent with the provisions of this Order, shall apply to the acquisition of land under this Order—

(a)as it applies to a compulsory purchase to which the Acquisition of Land Act 1981(7) applies; and

(b)as if this Order were a compulsory purchase order under that Act.

(2) Part 1 of the 1965 Act, as so applied, shall have effect as if section 4 (which provides a time limit for compulsory purchase of land) and paragraph 3(3) of Schedule 3 (which makes provision as to the giving of bonds) were omitted.

Power to acquire new rights

5.—(1) The Company may acquire compulsorily such easements or other rights over any land referred to in paragraph (1) of article 3 (power to acquire land) as may be required for any purpose for which that land may be acquired under that provision, by creating them as well as by acquiring easements or other rights already in existence.

(2) Subject to section 8 of the 1965 Act (as substituted by paragraph 5 of Schedule 1), where the Company acquires a right over land under paragraph (1) it shall not be required to acquire a greater interest in that land.

(3) Schedule 1 (modification of compensation and compulsory purchase enactments for creation of new rights) shall have effect for the purpose of modifying the enactments relating to compensation and the provisions of the 1965 Act in their application in relation to the compulsory acquisition under this article of a right over land by the creation of a new right.

Temporary use of land for construction of works

6.—(1) The Company may, in connection with the construction of the Northern Gateway Container Terminal—

(a)enter upon and take temporary possession of the land numbered 1a shown coloured pink and edged black on the land plans and described in the book of reference for the purpose of constructing Work No. 1 authorised by the Teesport Harbour Revision Order 2008;

(b)remove any equipment and apparatus (including a conveyor) from that land; and

(c)construct temporary works (including the provision of means of access) on that land.

(2) Not less than 14 days before entering upon and taking temporary possession of land under this article the Company shall serve notice of the intended entry on the owners and occupiers of the land.

(3) The Company may not, without the agreement of the owners of the land, remain in possession of any land under this article after the end of the period of one year beginning with the date of completion of the work specified in relation to that land in paragraph (1)(a).

(4) Before giving up possession of land of which temporary possession has been taken under this article, the Company shall remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.

(5) The Company shall pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the powers conferred by this article.

(6) Any dispute as to a person’s entitlement to compensation under paragraph (5), or as to the amount of the compensation, shall be determined under Part 1 of the 1961 Act.

(7) Without prejudice to article 13 (no double recovery), nothing in this article shall affect any liability to pay compensation under section 10(2) of the 1965 Act or under any other enactment in respect of loss or damage arising from the execution of any works, other than loss or damage for which compensation is payable under paragraph (5).

(8) The powers of compulsory acquisition of land conferred by this Order shall not apply in relation to the land referred to in paragraph (1) except that the Company shall not be precluded from acquiring new rights over any part of that land under article 5 (power to acquire new rights).

(9) Where the Company takes possession of land under this article, it shall not be required to acquire the land or any interest in it.

(10) Section 13 of the 1965 Act shall apply to the temporary use of land pursuant to this article to the same extent as it applies to the acquisition of land under this Order by virtue of article 4(1) (application of Part 1 of the Compulsory Purchase Act 1965).

Disregard of certain interests and improvements

7.—(1) In assessing the compensation payable to any person on the acquisition from him of any land under this Order, the tribunal shall not take into account—

(a)any interest in land, or

(b)any enhancement of the value of any interest in land by reason of any building erected, works executed or improvement or alteration made on relevant land,

if the tribunal is satisfied that the creation of the interest, the erection of the building, the execution of the works or the making of the improvement or alteration was not reasonably necessary and was undertaken with a view to obtaining compensation or increased compensation.

(2) In paragraph (1), “relevant land” means the land acquired from the person concerned or any other land with which he is, or was at the time when the building was erected, the works executed or the improvement or alteration made, directly or indirectly concerned.

Extinction or suspension of private rights of way

8.—(1) All private rights of way over land subject to compulsory acquisition under this Order shall be extinguished—

(a)as from the date of acquisition of the land by the Company, whether compulsorily or by agreement; or

(b)on the date of entry on the land by the Company under section 11(1) of the 1965 Act,

whichever is the sooner.

(2) All private rights of way over land owned by the Company which, being within the limits of land which may be acquired shown on the land plans, are required for the purposes of this Order shall be extinguished on the appropriation of the land for any of those purposes by the Company.

(3) All private rights of way over land of which the Company takes temporary possession under this Order shall be suspended and unenforceable for as long as the Company remains in lawful possession of the land.

(4) Any person who suffers loss by the extinguishment or suspension of any private right of way under this article shall be entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

(5) This article does not apply in relation to any right of way to which section 271 or 272 of the Town and Country Planning Act 1990(8) (extinguishment of rights of statutory undertakers etc.) applies.

Time limit for exercise of powers of acquisition

9.—(1) After the end of the period of 5 years beginning with the day on which this Order comes into force, no notice to treat shall be served under Part 1 of the 1965 Act as applied to the acquisition of land by article 4 (application of Part 1 of the Compulsory Purchase Act 1965).

(2) The powers conferred by article 6 (temporary use of land for construction of works) shall cease at the end of the period referred to in paragraph (1), save that nothing in this paragraph shall prevent the Company remaining in possession of land after the end of that period, if the land was entered and possession of it was taken before the end of that period.

PART 3MISCELLANEOUS AND GENERAL

Statutory undertakers etc.

10.  The provisions of Schedule 2 (provisions relating to statutory undertakers etc.) shall have effect.

Certification of plans etc.

11.  The Company shall, as soon as practicable after the making of this Order, submit copies of the book of reference and the land plans to the Secretary of State for certification that they are, respectively, true copies of the book of reference and land plans referred to in this Order; and a document so certified shall be admissible in any proceedings as evidence of the contents of the document of which it is a copy.

Service of notices

12.—(1) A notice or other document required or authorised to be served for the purposes of this Order may be served—

(a)by post; or

(b)with the consent of the recipient and subject to paragraphs (6) to (8) by electronic transmission.

(2) Where the person on whom a notice or other document to be served for the purposes of this Order is a body corporate, the notice or document is duly served if it is served on the secretary or clerk of that body.

(3) For the purposes of section 7 of the Interpretation Act 1978(9) as it applies for the purposes of this article, the proper address of any person in relation to the service on him of a notice or document under paragraph (1) is, if he has given an address for service, that address, and otherwise—

(a)in the case of the secretary or clerk of a body corporate, the registered or principal office of that body, and

(b)in any other case, his last known address at the time of service.

(4) Where for the purposes of this Order a notice or other document is required or authorised to be served on a person as having any interest in, or as the occupier of, land and his name or address cannot be ascertained after reasonable enquiry, the notice may be served by—

(a)addressing it to him by name or by the description of “owner”, or as the case may be “occupier”, of the land (describing it), and

(b)either leaving it in the hands of a person who is or appears to be resident or employed on the land or leaving it conspicuously affixed to some building or object on or near the land.

(5) Where a notice or other document required to be served or sent for the purposes of this Order is served or sent by electronic transmission the requirement shall be taken to be fulfilled where the recipient of the notice or other document to be transmitted has given his consent to the use of electronic transmission either in writing or by electronic transmission.

(6) Where the recipient of a notice or other document served or sent by electronic transmission notifies the sender within 7 days of receipt that he requires a paper copy of all or any part of that notice or other document the sender shall provide such a copy as soon as reasonably practicable.

(7) A person may revoke his consent to the use of electronic transmission in accordance with paragraph (8).

(8) Where a person is no longer willing to accept the use of electronic transmission for any of the purposes of this Order—

(a)he shall give notice in writing or by electronic transmission revoking any consent given by him for that purpose; and

(b)such revocation shall be final and shall take effect on a date specified by the person in the notice but that date shall not be less than 7 days after the date on which the notice is given.

(9) This article shall not be taken to exclude the employment of any method of service not expressly provided for by it.

No double recovery

13.  Compensation shall not be payable in respect of the same matter both under this Order and under any other enactment, any contract or any rule of law.

Arbitration

14.  Any difference under any provision of this Order, unless otherwise provided for, shall be referred to and settled by a single arbitrator to be agreed between the parties or, failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) by the President of the Institution of Civil Engineers.

Signed by authority of the Secretary of State

Ellis Harvey

Head of Transport and Works Act Orders Unit

Department for Transport

30th April 2008

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources