8.—(1) In the execution of the works, or any part thereof, the Rivers Authority may deviate from the lines or situations thereof shown on the deposited plans to any extent within the limits of deviation shown on those plans, and may deviate vertically from the levels shown on the deposited sections to any extent upwards or downwards:
Provided that notwithstanding anything in this Article the barrier shall be so constructed that–
the width of the navigable opening is not less than 30 metres; and
the cill of the navigable opening shall not be higher than 2.2 metres below Ordnance Datum (Newlyn).
(2) Nothing in paragraph (3) or paragraph (4) of the last foregoing Article shall authorise the Rivers Authority to execute any part of the works in contravention of the restrictions imposed by the proviso to the foregoing paragraph of this Article.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: