25.—(1) In respect of every auxiliary fan at a mine the manager shall fix the minimum quantity of air to be delivered or exhausted per minute at the end of the air duct.
(2) The manager shall make and secure the efficient carrying out of a arrangements whereby at least once in every week a competent person appointed for that purpose by him measures the quantity of air being so delivered or exhausted and determines whether any air is being re-circulated by that fan.
(3) Particulars of the quantity fixed under paragraph (1) and of every measurement and determination made under paragraph (2) shall be recorded forthwith by the manager or the competent person, as the case may be, in a book provided for that purpose by the owner of the mine.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: