Table 1 (Marine Construction Licence) is categorised into 9 bands which reflect the size and scale of the project, in monetary terms. The applicant will be required to pay the licence fee (Column 2) on submission of an application.
Tables 2 (Maintenance Dredging Licence), 3 (Capital Dredging Licence), 4 (Maintenance Dredge Disposal Licence) and 5 (Capital Dredge Disposal Licence) are all categorised into bands which reflect the metric tonnages of material to be dredged or disposed of. In each case, the applicant will be required to pay the Licence Fee (Column 2) on submission of an application.
Tables 6 (Deposit of Tracer Dyes, Biocides and Other Such Materials Licence) and 7 (Marine Minerals Extraction Licence) each have a single band. The fee to be paid by the applicant on submission of an application is as indicated.
Table 8 (Marine Renewable Energy Licence) is categorised into 4 bands which reflect the size and scale of the project, in terms of its output in Megawatts. The applicant will be required to pay the Licence Fee (Column 2) on submission of an application.
Column 1 Banded values in monetary terms | Column 2 Licence Fee |
---|---|
Band A Up to £19,999 | £550 |
Band B £20,000 - £49,999 | £759 |
Band C £50,000 - £199,999 | £1,446 |
Band D £200,000 - £499,999 | £2,075 |
Band E £500,000 - £999,999 | £2,410 |
Band F £1,000,000 - £2,999,999 | £4,506 |
Band G £3,000,000 - £4,999,999 | £5,554 |
Band H £5,000,000 - £19,999,999 | £6,602 |
Band I £20,000,000 and above | £10,795 |
Column 1 Banded values in terms of mass of material dredged. (t = tonne) | Column 2 Licence Fee |
---|---|
Band 1 0 – 9,999t | £250 |
Band 2 10,000t – 24,999t | £300 |
Band 3 25,000t – 49,999t | £350 |
Column 1 Banded values in terms of mass of material dredged. (t = tonne) | Column 2 Licence Fee |
---|---|
Band 1 0 – 9,999t | £902 |
Band 2 10,000t – 24,999t | £1,253 |
Band 3 25,000t – 49,999t | £1,704 |
Band 4 50,000t – 99,999t | £2,405 |
Band 5 100,000t – 499,999t | £3,358 |
Band 6 500,000t – 999,999t | £4,761 |
Band 7 1,000,000t and above | £8,019 |
Column 1 Banded values in terms of mass of material disposed. (t = tonne) | Column 2 Licence Fee |
---|---|
Band 1 0 – 9,999t | £2,017 |
Band 2 10,000t – 24,999t | £2,751 |
Band 3 25,000t – 49,999t | £3,856 |
Band 4 50,000t – 99,999t | £5,428 |
Band 5 100,000t – 499,999t | £7,650 |
Band 6 500,000t – 999,999t | £10,795 |
Band 7 1,000,000t and above | £18,131 |
Column 1 Banded values in terms of mass of material disposed. (t = tonne) | Column 2 Licence Fee |
---|---|
Band 1 0 – 9,999t | £2,709 |
Band 2 10,000t – 24,999t | £3,715 |
Band 3 25,000t – 49,999t | £5,208 |
Band 4 50,000t – 99,999t | £7,367 |
Band 5 100,000t – 499,999t | £10,365 |
Band 6 500,000t – 999,999t | £14,672 |
Band 7 1,000,000t and above | £24,723 |
Licence Fee |
---|
£419 |
Licence Fee |
---|
£29,345 |
Column 1 Banded values in terms of the project’s power output. (MW = Megawatts) | Column 2 Licence Fee |
---|---|
Band R1 0 – 0.99MW | £4,009 |
Band R2 1.0MW – 9.99MW | £12,530 |
Band R3 10MW – 99.9MW | £20,550 |
Band R4 100MW and above | £30,574 |
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Rule and provides information about its policy objective and policy implications. They aim to make the Statutory Rule accessible to readers who are not legally qualified and accompany any Northern Ireland Statutory Rule or Draft Northern Ireland Statutory Rule laid before the UK Parliament during the suspension of the Northern Ireland Assembly.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: