Section 43 – Notice to Department and commission of construction engineer
This section requires reservoir managers of controlled reservoirs which are to be subject to relevant works to commission a construction engineer to supervise the relevant works and the safety of the reservoir. Not later than 28 days before the works commence the reservoir manager must give the Department notice of the proposed works and notice of the construction engineer’s commission. A construction engineer must be an appropriate panel engineer, and is required to supervise the relevant works and the safety of the reservoir until a copy of the final certificate issued in respect of the works is given to the reservoir manager and copied to the Department in respect of the works. The persons listed in subsection (5) are disqualified from being commissioned as a construction engineer in relation to a particular reservoir.