Search Legislation

Commission Implementing Regulation (EU) 2019/317Show full title

Commission Implementing Regulation (EU) 2019/317 of 11 February 2019 laying down a performance and charging scheme in the single European sky and repealing Implementing Regulations (EU) No 390/2013 and (EU) No 391/2013 (Text with EEA relevance)

 Help about what version

What Version

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

This item of legislation originated from the EU

Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).

Status:

This is the original version as it was originally adopted in the EU.
This legislation may since have been updated - see the latest available (revised) version

CHAPTER III PERFORMANCE TARGET SETTING

Article 7Duration of the reference periods

1.The third reference period shall cover the calendar years 2020 to 2024 inclusive.

2.Subsequent reference periods shall each cover five calendar years.

3.The duration of the reference periods specified in paragraphs 1 and 2 shall be without prejudice to Article 10(6).

Article 8Key performance indicators and indicators for monitoring

1.The key performance indicators and the indicators for monitoring the performance of air navigation services at Union level for each key performance area shall be those established in Section 1 of Annex I.

2.The key performance indicators and the indicators for monitoring the performance of air navigation services at national level or at the level of functional airspace blocks shall be those established in Section 2 of Annex I.

3.The key performance indicators and the indicators for monitoring the performance of the network functions shall be those established in Section 3 of Annex I.

4.Member States may establish key performance indicators and indicators for monitoring in addition to those referred to in paragraph 2 as regards, in particular, civil-military or meteorological aspects.

Article 9Union-wide performance targets

1.At the latest 19 months before the start of a reference period, the national supervisory authorities shall provide to the Commission initial cost data and information about traffic forecasts referred to in point (f) of Article 10(2) related to the upcoming reference period, as inputs for the setting of Union-wide performance targets.

2.At the latest 15 months before the start of a reference period, the Commission shall publish indicative target ranges for the Union-wide performance targets, consisting of the annual minimum and maximum values within which the Commission intends to set the Union-wide performance targets.

The Commission shall consult the stakeholders referred to in Article 10(3) of Regulation (EC) No 549/2004, other relevant persons and organisations and, regarding safety aspects, the European Union Aviation Safety Agency on those indicative target ranges.

3.At the latest seven months before the start of a reference period, the Commission shall adopt in accordance with point (a) of Article 11(3) of Regulation (EC) No 549/2004 the Union-wide performance targets for the key performance indicators referred to in Article 8(1).

For this purpose, the Commission shall:

(a)take account of the relevant inputs from the Performance Review Body, the Network Manager and the national supervisory authorities;

(b)use en route traffic forecasts, expressed in terms of IFR movements and in service units and based on the latest available Eurocontrol's Statistics and Forecast Service (‘STATFOR’) base forecast;

(c)substantiate each Union-wide performance target with a description of the underlying assumptions and rationale for that target, including the use made of inputs referred to in point (a) of this paragraph, the outcome of the consultation referred to in paragraph 2 and other relevant factual data.

4.Together with the adoption of the Union-wide performance targets, the Commission shall establish:

(a)a Union-wide ‘baseline value for determined costs’ and a Union-wide ‘baseline value for the determined unit cost’, for the purpose of setting targets in the key performance area of cost-efficiency for the key performance indicator referred to in point 4.1 of Section 1 of Annex I. Those baseline values shall be calculated in respect to the year preceding the start of the reference period.

The baseline value for determined costs shall be estimated by using the actual costs available for the preceding reference period and adjusted to take account of latest available cost estimates, traffic variations and their relation to costs.

The baseline value for the determined unit cost shall be derived by dividing the baseline value for the determined costs with the traffic forecast expressed in service units for the year preceding the start of the reference period;

(b)alert thresholds beyond which Member States may request a revision of the performance targets contained in performance plans, in accordance with point (a)(i) of Article 18(1). Those alert thresholds shall be based on the following parameters:

(i)

the deviation of the actual traffic from the traffic forecast over a given calendar year, expressed as a percentage of IFR movements;

(ii)

the deviation of the actual traffic from the traffic forecast over a given calendar year, expressed as a percentage of service units;

(iii)

the variation of the reference values as a result of the seasonal updates of the Network Operations Plan pursuant to point (a) of Article 9(4) and Article 9(8) of Implementing Regulation (EU) 2019/123 in comparison to the reference values from the latest version of the Network Operations Plan available at the time of drawing up the performance plan. This variation shall be expressed as a percentage of variation or as a fraction of minutes of en route ATFM delay, depending on the magnitude of the references values;

(c)the comparator groups of air navigation service providers with a similar operational and economic environment, for the purposes of assessing performance targets in the key performance area of cost-efficiency.

Article 10Performance plans

1.National supervisory authorities shall draw up performance plans, either at national level or at the level of functional airspace blocks.

2.The performance plans shall be drawn up in accordance with the template set out in Annex II and shall include:

(a)binding national performance targets or binding FAB performance targets, set on the basis of the key performance indicators referred to in Article 8(2), including a ‘baseline value for determined costs’ and a ‘baseline value for the determined unit cost’ for each charging zone, for the purpose of setting targets in the key performance area of cost-efficiency. Those baseline values shall be calculated in respect to the year preceding the start of the reference period.

The baseline value for determined costs shall be estimated by using the actual costs available for the preceding reference period and shall be adjusted to take account of latest available cost estimates, traffic variations and their relation to costs.

The baseline value for the determined unit costs shall be derived by dividing the baseline value for the determined costs with the latest available traffic forecast expressed in service units for the year preceding the start of the reference period;

(b)determined costs for en route and terminal air navigation services set in accordance with points (a) and (b) of Article 15(2) of Regulation (EC) No 550/2004 and with this Regulation;

(c)the incentive schemes established in accordance with Article 11, specifying the parameters of the incentive schemes, the modulation mechanism of pivot values referred to in Article 11(3) where applicable, as well as measures aimed at achieving the objectives of those incentive schemes;

(d)a description of the main measures aimed at achieving performance targets;

(e)a confirmation that it is consistent with the scope of this Regulation pursuant to Article 1 of this Regulation and Article 7 of Regulation (EC) No 549/2004;

(f)en route traffic forecasts, expressed in terms of IFR movements and in service units and based on Eurocontrol's STATFOR base forecast;

(g)terminal traffic forecasts, expressed in terms of IFR movements and in service units, based on Eurocontrol's STATFOR base forecast;

(h)a description of initiatives to support cross-border coordination and the provision of cross-border services which are beneficial to the operational performance or cost-efficiency, or both;

(i)information about:

(i)

major investments;

(ii)

change management plans for the entry into service of major airspace changes or for ATM system improvements, aimed at minimising any negative impact on the network performance.

However, as regards point (f) and (g), national supervisory authorities may decide to use other en route and terminal traffic forecasts than those based on Eurocontrol's STATFOR base forecast. In that case, they shall consult the airspace users' representatives and air navigation service providers concerned and set out the reasons for using the other forecasts in the performance plan. Any differences with the Eurocontrol's STATFOR base forecast shall be related to specific local factors not sufficiently addressed by Eurocontrol's STATFOR base forecast. The same forecasts shall be used for all key performance areas.

3.The performance plans may contain additional performance targets set on the basis of the key performance indicators referred to in Article 8(4). Those targets shall support the achievement of the performance targets referred to in Article 9(3) and in point (a) of paragraph 2 of this Article.

4.In accordance with Article 10(1) and point (b) of Article 11(3) of Regulation (EC) No 549/2004, national supervisory authorities shall consult air navigation service providers, airspace users' representatives and, where relevant, airport operators and airport coordinators on the draft performance plans, including on the performance targets and incentive schemes contained therein.

5.The Network Manager shall draw up the Network Performance Plan. The Network Performance Plan shall be drawn up in accordance with the template set out in Annex III and shall set out:

(a)the value added of the Network Manager in support to the activities of Member States, functional airspace blocks, air navigation service providers and civil and military airspace users towards achieving capacity and environment targets, and set out the contribution of the network functions towards achieving the Union-wide performance targets;

(b)the performance targets and objectives for the Network Manager and for each network function and the measures aimed at achieving those targets.

6.Where as provided in the fourth subparagraph of point (c) of Article 11(3) of Regulation (EC) No 549/2004 the Commission has revised the Union-wide performance targets, Member States shall revise their performance plans and include revised performance targets in accordance with this Regulation.

Article 11Incentive schemes

1.The incentive schemes contained in the performance plans as adopted by the Member States shall:

(a)set out incentives of financial nature for the achievement of the performance targets in the key performance areas of cost-efficiency and capacity in an effective and proportional manner;

(b)apply during the entire period covered by the performance plan;

(c)be non-discriminatory, transparent and effective;

(d)apply to en route and terminal air navigation services.

2.The incentive schemes on performance targets in the key performance area of cost-efficiency shall be governed by Articles 27 and 28.

3.The incentive schemes on performance targets in the key performance area of capacity shall in addition to the principles set out in paragraph 1, meet the following principles:

(a)they shall be proportionate to the level of ATFM delay and consist of financial advantages and financial disadvantages having material impact on revenue at risk;

(b)they shall be set so that the maximum financial disadvantages are at least equal to the maximum financial advantages;

The national supervisory authority shall define the maximum fixed percentages referred to in the second subparagraphs of points 2.1(a) and 2.2(a) of Annex XIII and in the second subparagraphs of points 2.1(b) and 2.2(b) of Annex XIII for the calculation of the financial advantages and disadvantages, subject to consultation of airspace users' representatives and of air navigation service providers concerned.

In respect to the maximum fixed percentages referred to in the second subparagraphs of points 2.1(a) and 2.2(a) of Annex XIII for the calculation of the financial advantages, those percentages shall not exceed 2 %;

(c)for the purpose of calculating the financial advantages or disadvantages, pivot values shall be used;

The national supervisory authority shall decide, before the start of the reference period, whether those pivot values are to be based:

(i)

on the performance targets at national level, broken down at the level of each individual air navigation service provider; or

(ii)

on modulated performance targets at national level, broken down at the level of each individual air navigation service provider, set annually by the national supervisory authority for the following year in accordance with point 1 of Annex XIII and subject to consultation of airspace users' representatives and of air navigation service providers concerned. The modulation mechanism shall be defined in the performance plan and shall apply for each year of the reference period and shall not be changed during the reference period.

The national supervisory authority shall inform the Commission about the pivot values annually;

(d)there shall be a symmetric range around the pivot value set by the national supervisory authority, subject to consultation of airspace users' representatives and of air navigation service providers concerned, to ensure that minor variations in ATFM delay do not lead to any financial advantages or disadvantages;

(e)where the actual average ATFM delay per flight in year n is lower than the pivot value set for year n and beyond the range referred to in point (d), this shall result in a financial advantage through an increase of the unit rate in year n+2 in accordance with point 2 of Annex XIII;

(f)where the actual average ATFM delay per flight in year n is higher than the pivot value set for year n and beyond the range referred to in point (d), this shall result in a financial disadvantage through a reduction of the unit rate in year n+2 in accordance with point 2 of Annex XIII;

(g)for the en route targets in the key performance area of capacity and where the performance plan is established at functional airspace block level, the following provisions shall apply, in additional to the principles referred to in points (a) to (f):

(i)

the national supervisory authorities concerned shall break down the FAB performance target referred to in point 3.1(a) of Section 2 of Annex I at the level of each individual air navigation service provider concerned, for the purpose of setting incentives at national level. The resulting values shall form the basis for pivot values referred to in point (c);

(ii)

the national supervisory authorities concerned shall apply the same incentive scheme, in a consistent manner to all air navigation service providers concerned;

(iii)

pivot values for the functional airspace block shall also be used in addition to pivot values at the level of each individual air navigation service provider referred to in point (i), and shall be based either:

  • on the performance targets at functional airspace block level, or

  • on modulated performance targets at functional airspace block level in accordance with point 1 of Annex XIII and subject to consultation of airspace users' representatives and of air navigation service providers concerned;

(iv)

by way of derogation from point (c), all national supervisory authorities concerned shall jointly decide on whether the pivot values at the level of each individual air navigation service provider and functional airspace block level are to be modulated or not. This decision shall apply in a uniform manner to all pivot values at the level of each individual air navigation service provider and functional airspace block level, for the entire duration of the reference period;

(v)

where performance targets at national and functional airspace block level are to be modulated, the same modulation mechanism shall apply to performance targets at national level and functional airspace block level;

(vi)

where the total en route ATFM delay per flight in year n at the functional airspace block level is higher than the pivot value set for year n referred to in point (iii) and beyond the range referred to in point (d) of paragraph 3, point (e) of paragraph 3 shall not apply and point (f) of paragraph 3 shall apply only to those air navigation service providers for which the actual ATFM delay per flight in year n is higher than the pivot value set for year n and beyond the range referred to in point (d);

(vii)

where the total en route ATFM delay per flight in year n at the functional airspace block level is lower than the pivot value set for year n referred to in point (iii) and beyond the range referred to in point (d) of paragraph 3, point (f) of paragraph 3 shall not apply and point (e) of paragraph 3 shall apply only to those air navigation service providers for which the actual ATFM delay per flight in year n is lower than the pivot value set for year n and beyond the range referred to in point (d).

4.The incentive schemes contained in the performance plans as adopted by the Member States may also set out incentives of financial nature for the achievement of the performance targets in the key performance area of environment or for the achievement of the additional performance targets referred to in Article 10(3) in line with points (b) and (c) of paragraph 1, provided that they are effective and proportional. Those incentive schemes should be applied in addition to and independently from the incentive schemes referred to in paragraphs 2 and 3. The aggregated financial advantage or financial disadvantage from those incentive schemes shall not exceed 2 % and 4 % of the determined costs of year n respectively.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources