Commission Implementing Regulation (EU) 2019/317 of 11 February 2019 laying down a performance and charging scheme in the single European sky and repealing Implementing Regulations (EU) No 390/2013 and (EU) No 391/2013 (Text with EEA relevance)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
This is the original version as it was originally adopted in the EU.
This legislation may since have been updated - see the latest available (revised) version
1.During the reference period Member States may revise one or more performance targets contained in the performance plans and adopt performance plans which are amended accordingly, only where both of the following conditions are met:
(a)the Member State or Member States concerned consider that the intended revision is necessary and proportionate in light of the occurrence of one or more of the following situations:
at least one of the alert thresholds referred to in point (b) of Article 9(4) is reached and the national supervisory authority or authorities concerned have assessed the situation and have shown that the resulting effects of reaching the alert threshold or thresholds cannot be sufficiently mitigated unless the performance targets are revised;
the initial data, assumptions and rationales, including on investments, on the basis of which the performance targets concerned were set are to a significant and lasting extent no longer accurate due to circumstances that were unforeseeable at the time of the adoption of the performance plan, and the national supervisory authority or authorities concerned have assessed the situation and have shown that the resulting effects cannot be sufficiently mitigated unless the performance targets are revised;
(b)the Commission has, based on a reasoned request by the Member State or Member States concerned, decided that:
it agrees that the intended revision is necessary and proportionate in light of the occurrence of one or more of the following situations referred to in point (a);
the intended revised performance targets are consistent with the Union-wide performance targets, having assessed those targets on the basis of the criteria laid down in point 1 of Annex IV.
The Commission shall adopt the decision referred to in point (b) within seven months from the date of the submission of the complete request submitted by the Member State or Member States concerned.
2.Any revisions of performance targets adopted in application of this Article shall not apply retroactively.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: