Commission Implementing Regulation (EU) 2017/6 of 5 January 2017 on the European Rail Traffic Management System European deployment plan
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
This is the original version as it was originally adopted in the EU.
This legislation may since have been updated - see the latest available (revised) version
1.This Regulation lays down the timetable for the deployment of the European Rail Traffic Management System ('ERTMS') on core network corridors as set out in Annex I.
2.This Regulation does not apply to ERTMS on-board implementation laid down in point 7.3.3 of Annex III to Decision 2012/88/EU.
1.Railway infrastructure managers shall equip the core network corridors with ERTMS and put ERTMS into operation in those corridors at the latest by the dates specified in Annex I to this Regulation, including in railway stations and junctions. The railway link to the elements listed in Annex II of Regulation (EU) No 1315/2013 and to the infrastructure components as referred to in Article 11 of Regulation (EU) No 1315/2013 that are located on the core network corridor shall be equipped and put into operation at the date specified for the respective core network corridor section.
Deployment shall be in compliance with Articles 1(4), 7(2c) and 39(3) of Regulation (EU) No 1315/2013.
2.A core network corridor shall be considered equipped with ERTMS when ERTMS is authorised for the placing in service in accordance with Article 15 of Directive 2008/57/EC of the European Parliament and of the Council(1) or Article 18 of Directive (EU) 2016/797 of the European Parliament and of the Council(2), allowing passenger and freight traffic in both directions in particular in case of works or disturbances, and, to the extent necessary for operations of ERTMS-only equipped vehicles, sidings.
3.Railway infrastructure managers, acting in cooperation, shall make an effort to equip and put into operation ERTMS on cross-border sections simultaneously, in a technically consistent manner. The railway infrastructure managers shall, after having consulted the railway undertakings affected, sign an agreement on technical and operational aspects of the deployment for each cross-border section. The railway infrastructure managers shall conclude such an agreement not later than one year before the earlier of the deployment dates for the given cross-border section. This agreement shall provide transitional provisions for taking into account the needs of the railway undertakings' cross-border operations. In case of a disagreement, the Member States concerned shall initiate an active dialogue in order to find common convergent solutions. They may request support from the Commission. The Member States shall notify such agreements to the Commission not later than one month after the conclusion.
4.The completion dates set out in agreements for projects co-funded by the Union which are earlier than the dates set out in Annex I shall prevail over those dates.
5.Member States may decide to keep the existing Class B systems, as defined in point 2.2 of the Annex to Regulation (EU) 2016/919. However, by the dates set out in Annex I, the vehicles referred to in point 1.1 of the Annex to Regulation (EU) 2016/919 which are equipped with ERTMS in a version compatible with the track-side equipment, shall be given access to those lines and to the infrastructure components as referred to in Article 11 of Regulation (EU) No 1315/2013 without requiring them to be equipped with a Class B system.
1.Once ERTMS is put into operation on a core network corridor section, the Member State concerned shall notify the Commission of that fact within one month, through the systems established under Article 49(1) of Regulation (EU) No 1315/2013 and Article 5(1) of Commission Implementing Decision 2014/880/EU(3).
2.Member States shall notify the Commission of any delays in putting ERTMS in operation on a given core network corridor section to be equipped. The railway infrastructure managers shall inform the Member States about those delays accordingly.
3.When notifying the delays referred in paragraph 2, the Member State concerned shall send to the Commission a file containing a technical description of the project and specifying a new date for putting ERTMS into operation. The file shall specify the causes for the delay and shall indicate the corrective measures taken by the railway infrastructure manager.
4.If the delay results from an exceptional circumstance, the Commission may accept to postpone the relevant date by a maximum of three years. If a postponement is granted, the Member State shall make the necessary amendments to its national implementation plan as referred to in point 7.4.4 of the Annex to Regulation (EU) 2016/919 within one month of granting that postponement.
Exceptional circumstance referred to in the first subparagraph means a circumstance resulting from the planning phase and which is related to specific geological findings, environmental or species protection, archaeological finds, permitting procedures, implementation of an environmental impact assessment pursuant to Directive 2014/52/EU of the European Parliament and of the Council(4); or a circumstance resulting from the construction and authorisation phases that are out of the control of the project promoter and do not fall into the category of the usual risks that should be addressed at project management level in this type of projects.
5.If ERTMS specifications set out in Regulation (EU) 2016/919 are changed by legislative act in an incompatible way the Member States shall provide the Commission with an analysis of the impact of the application of the modified legal reference on their network and on the ERTMS planning without unreasonable delay, but at latest at the time of the formal opinion of the Committee referred to in Article 51 of Directive (EU) 2016/797. If a direct impact of the changes can be demonstrated in terms of cost or timeline for specific implementations, Annex I shall be adapted accordingly.
Not later than 31 December 2023, the Commission shall, after consultation with the Member States, and with the assistance of the European ERTMS Coordinator referred to in Article 45 of Regulation (EU) No 1315/2013, carry out a review of the dates after 1 January 2024 that are laid down in Annex I to this Regulation.
References to Annex III to Decision 2012/88/EU shall be construed as references to this Regulation and shall be read in accordance with the correlation table in Annex II.
This Regulation shall enter into force on 26 January 2017.
This Regulation shall be binding in its entirety and directly applicable in all Member States.
Done at Brussels, 5 January 2017.
For the Commission
The President
Jean-Claude Juncker
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: