Regulation 3 (2)

FIRST SCHEDULEMANNER IN WHICH, FOR THE PURPOSE OF THE DEFINITION OF “LEAD PAINT”, MATERIAL IS TO BE TREATED WITH A VIEW TO ASCERTAINING THE PERCENTAGE OF COMPOUND OF LEAD PRESENT

The material is to be treated with suitable solvents to remove the oil, varnish and other media, and the residue to be dried at one hundred degrees Centigrade and thoroughly mixed. A weighed quantity of this extracted, dried and mixed material is to be continuously shaken for one hour, at the common temperature, with one thousand times its weight of an aqueous solution of hydrochloric acid containing 0·25 per cent. by weight of hydrogen chloride. This solution is thereafter to be allowed to stand for one hour and then filtered. The lead salt contained in the clear filtrate is then to be precipitated as lead sulphide and weighed as lead sulphate.

Regulations 34 (1), 36 (1) and 40

SECOND SCHEDULEMANNER OF TEST AND EXAMINATION BEFORE TAKING ANY CHAIN, WIRE ROPE, LIFTING APPLIANCE OR LIFTING GEAR INTO USE

(a)

Every winch, and every derrick with the whole of the gear accessory thereto, shall be tested with a proof load which shall not be less than the following—

Safe working load Proof load
Under 20 tons 25 per cent.in excess of the safe working load
20–50 tons 5 tons
over 50 tons 10 per cent.

In the case of a derrick with its accessory gear the proof load shall be applied as follows:—

(i)

where reasonably practicable by hoisting movable weights; or

(ii)

in other cases by maintaining the load by means of an accurate spring or hydraulic balance or similar device for a period of not less than five minutes. Where movable test weights are used the derrick shall be swung, with the load suspended, as far as possible in both directions. Where a spring or hydraulic balance or similar device is employed it shall be sufficient if the proof load is applied with the derrick swung as far as practicable first in one direction and then in the other. In each case the derrick shall be tested at the smallest angle to the horizontal at which it will operate and this angle shall be stated in the certificate of the test.

(b)

Every crane, crab, sheer-legs, teagle, transporter or runway, with its accessory gear, shall be tested with a proof load which shall not be less than the following—

Safe working load Proof load
Under 20 tons 25 per cent.in excess of the safe working load
20–50 tons 5 tons
over 50 tons 10 per cent.

In the case of a crane having a variable radius it shall be tested with a proof load applied at the maximum and minimum working radii. At each such radius the crane shall be swung as far as possible in both directions with the corresponding proof load suspended. In the case of hydraulic cranes where, owing to the limitation of pressure it is impossible to hoist a load 25 per cent. in excess of the safe working load, it shall be sufficient to hoist the greatest possible load.

(c)

Every article of lifting gear (whether it is accessory to any lifting appliance or not) and every pulley block other than a pulley block specially constructed for use with a crane to which it is permanently attached, and every chain shall be tested with a proof load at least equal to that shown against it in the following table:—

Article of gear Safe working load Proof load
Chain sling Twice the safe working load
Rope sling
Plate clamp
Ring
Link
Hook (other than a ramshorn hook)
Shackle
Swivel
Eye-bolt
Ramshorn hook Under 50 tons Twice the safe working load
50 tons to 100 tonsSafe working loads plus 50 tons
Over 100 tons One and a half times the safe working load
Pulley blocks
Single sheave block Four times the safe working load
Multiple sheave block with safe working load up to and including 20 tons Twice the safe working load
Multiple sheave block with safe working load over 20 tons up to and including 40 tons 20 tons in excess of the safe working load
Multiple sheave block with safe working load over 40 tons One and a half times the safe working load
Chains (other than calibrated load chains) Twice the safe working load
Calibrated load chains One and a half times the safe working load
(d)

After being tested as aforesaid, every lifting appliance with the whole of the gear accessory thereto, every article of lifting gear and every chain shall be examined, and the sheaves and the pins of the pulley blocks shall be removed for the purpose of the examination, to see that no part is injured or permanently deformed by the test.

(e)

In the case of wire ropes, a sample shall be tested to destruction.

Regulation 79 (3)

THIRD SCHEDULEEQUIPMENT OF AMBULANCE ROOMS

(1) A glazed sink with hot and cold water available during working hours.

(2) A table with smooth top.

(3) Means for sterilising instruments.

(4) A supply of suitable dressings, bandages and splints.

(5) A couch.

(6) A stretcher.

(7) Blankets and hot-water bottles.

(8) A foot bath.

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill