Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
(1)SEPA must, when requested by a planning authority, give the authority advice as to flood risk in the authority's district.
(2)SEPA must, when requested by a National Park authority which, though not a planning authority, is (by virtue of the order designating the National Park for which the authority is established) to be treated as the planning authority for the Park for any purpose, give the authority advice in relation to flood risk in the Park.
(3)Advice under subsection (1) or (2) is to be based on such information as respects such flood risk as SEPA possesses, taking into account—
(a)the flood risk assessment, any flood hazard map and flood risk map, the flood risk management plan and any local flood risk management plan for the time being applicable to the authority's district, and
(b)information provided to it by any planning authority or National Park authority which is not a planning authority.
(4)In this section—
(a)“planning authority” and a planning authority's “district” (except where paragraph (b) provides otherwise) have the meanings given in section 1(1) of the Town and Country Planning (Scotland) Act 1997 (c. 8),
(b)where—
(i)all or part of a planning authority's district is designated as a National Park, and
(ii)the designation order makes provision for the National Park authority to be the planning authority for the Park for the purposes of the planning Acts,
“planning authority” in relation to the National Park means the National Park authority and a planning authority's “district” means the National Park for which the National Park authority is established, and
(c)“the planning Acts” has the meaning given in section 277(1) of that Act.
Commencement Information
I1S. 72 in force at 26.11.2009 by S.S.I. 2009/393, art. 2, Sch.
(1)SEPA may—
(a)(in addition to the flood risk assessment it is required to prepare under section 9 and review under section 10) carry out such other assessment of flood risk as it considers appropriate, and
(b)(in addition to the flood hazard maps and flood risk maps it is required to prepare under section 21 and review under section 24) prepare such other maps in relation to flood risk as it considers appropriate.
(2)In the exercise of its power under subsection (1), SEPA must take into account the flood risk assessment, any flood hazard map and flood risk map and the flood risk management plan for the time being applicable to the area being assessed.
(3)SEPA may, where it considers it appropriate, integrate any map prepared by it under subsection (1)(b) with any such flood hazard map or flood risk map.
Commencement Information
I2S. 73 in force at 26.11.2009 by S.S.I. 2009/393, art. 2, Sch.
(1)SEPA must, where it considers that a flood is occurring or likely to occur in the near future, make available warnings in relation to the flood.
(2)Any warning under subsection (1)—
(a)of a flood which SEPA considers is occurring must be made available as soon as practicable after SEPA considers that is the case,
(b)of a flood which SEPA considers is likely to occur in the near future must be made available as soon as SEPA considers appropriate,
(c)is to be based on information available to SEPA, and
(d)must be made publicly available by SEPA by such means as it considers appropriate.
Commencement Information
I3S. 74 in force at 26.11.2009 by S.S.I. 2009/393, art. 2, Sch.
(1)SEPA may, and must where the Scottish Ministers direct, assess whether in its opinion—
(a)provision and operation by it of a flood warning system, or alteration of any flood warning system provided and operated by it, would assist in providing earlier or more accurate flood warning as respects an area, and
(b)the earlier or more accurate flood warning so provided would be likely to reduce the potential adverse consequences of flooding of the area for human health, the environment, cultural heritage and economic activity there.
(2)Any assessment under subsection (1) is to be based on such information as SEPA possesses.
(3)In carrying out any such assessment SEPA must consult in accordance with section 77(1).
(4)In this section and section 76, “flood warning system” means a system by which, for the purpose of detecting, forecasting or providing warning of any flood which is occurring or likely to occur in the near future, information as respects any of the following matters is obtained and transmitted—
(a)rainfall,
(b)the level or flow of any surface water (within the meaning of section 3(3) of the 2003 Act),
(c)such other matters as appear to SEPA to be appropriate for that purpose.
Commencement Information
I4S. 75 in force at 26.11.2009 by S.S.I. 2009/393, art. 2, Sch.
(1)SEPA may—
(a)provide and operate any flood warning system,
(b)alter any flood warning system provided and operated by it,
(c)for those purposes provide, install or alter apparatus and carry out any engineering or building operations, and
(d)maintain any such apparatus.
(2)Before—
(a)providing a flood warning system in pursuance of paragraph (a) of subsection (1),
(b)for that purpose doing any of the things referred to in paragraph (c) of that subsection, or
(c)for either of the purposes in paragraph (a) or (b) carrying out any engineering or building operations,
SEPA must consult in accordance with section 77(2).
(3)Where SEPA considers—
(a)the alteration of any flood warning system in pursuance of paragraph (b) of subsection (1), or
(b)for that purpose doing any of the things referred to in paragraph (c) of that subsection (“any related thing”),
would be material, it must consult in accordance with section 77(2) before carrying out the alteration of the system or for that purpose any related thing.
Commencement Information
I5S. 76 in force at 26.11.2009 by S.S.I. 2009/393, art. 2, Sch.
(1)The consultation required by section 75 is consultation with—
(a)every local authority whose area includes any part of the area which is the subject of the assessment, and
(b)every category 1 responder (other than a local authority) which has functions exercisable in or in relation to the area which is the subject of the assessment.
(2)The consultation required by section 76 is consultation with—
(a)every local authority in whose area the power is to be exercised, and
(b)any category 1 responder (other than a local authority) which has functions exercisable in or in relation to the area in which the power is to be exercised.
Commencement Information
I6S. 77 in force at 26.11.2009 by S.S.I. 2009/393, art. 2, Sch.
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
F1S. 78 repealed (30.6.2014) by Regulatory Reform (Scotland) Act 2014 (asp 3), s. 61(2), Sch. 3 para. 44; S.S.I. 2014/160, art. 2(1)(2), Sch.
Commencement Information
I7S. 78 in force at 26.11.2009 by S.S.I. 2009/393, art. 2, Sch.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the Scottish Government to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Acts of the Scottish Parliament except those which result from Budget Bills.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: