4.—(1) Not less than 28 days before starting the execution of any works in, on or under any land purchased, held, appropriated or used under this Order that are near to, or will or may affect, any apparatus (or any means of access to it) the removal of which has not been required by the undertaker in accordance with section 185 of the Act, the undertaker must submit to Anglian Water a plan of the works to be executed.
(2) Those works must be executed only (i) if approved by Anglian Water pursuant to sub-paragraph (3) below, (ii) in accordance with the plan submitted under sub-paragraph (1) and (iii) in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (3) by Anglian Water for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and Anglian Water is entitled to watch and inspect the execution of those works.
(3) Any requirements made by Anglian Water under sub-paragraph (2) must be made within a period of 21 days beginning with the date on which a plan under sub-paragraph (1) is submitted to it. The approval that may be given under that sub-paragraph must not be unreasonably withheld (although may be subject to the said requirements) and must be assumed to have been given unless Anglian Water gives written notice to the undertaker that it is being withheld entirely or given subject to the said requirements within the same time period.
(4) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any works, a new plan instead of the plan previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan.
(5) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case must give to Anglian Water notice as soon as is reasonably practicable and a plan of those works as soon as reasonably practicable subsequently and must comply with sub-paragraph (3) in so far as is reasonably practicable in the circumstances, using its best endeavours to keep the impact of those emergency works on Anglian Water’s apparatus, on the operation of its water and sewerage network and on end-users of the services Anglian Water provides to a minimum.
(6) For the purposes of sub-paragraph (1) and without prejudice to the generality of the principles set out in that sub-paragraph—
(a)the establishment of an access way or haul road and underground works are both deemed to be “works” for the purposes of this paragraph; and
(b)works are deemed to be in land near Anglian Water’s apparatus if those works fall within 20 metres measured from the medial line of the closer of the two water mains forming such apparatus to the works in question.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: