Search Legislation

The East Northamptonshire Resource Management Facility Order 2023

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Articles 2 and 10

SCHEDULE 1Authorised Development

A nationally significant infrastructure project as defined in section 14(1)(p) and 30 of the 2008 Act comprising—

Work No. 1 – A hazardous waste landfill facility for the disposal at a direct input rate of up to 150,000 tonnes per annum of predominantly hazardous waste together with small quantities of low level waste on the areas identified on the works plan comprising-

Work No. 1A – the construction and filling of a landfill including -

(a)extraction and stockpiling of soil, clay and other suitable materials for engineering and restoration purposes and the exportation of some clay and other suitable materials;

(b)all other associated engineering works to construct the landfill phases including a leachate collection system;,

(c)a landfill gas pump and gas flare; and

(d)surface water management and pumping systems including ponds as needed.

Work No. 1B – the construction and filling of a landfill including -

(a)extraction and stockpiling of soil, clay and other suitable materials for engineering and restoration purposes and the exportation of some clay and other suitable materials;

(b)all other associated engineering works to construct the landfill phases including a leachate collection system; and

(c)surface water management and pumping systems including ponds as needed.

Work No. 2 – A hazardous waste facility, namely the alteration of an existing waste treatment and recovery facility with an increase from the capacity of 200,000tpa in the original order to a capacity of 250,000tpa of predominantly hazardous wastes including -

(a)a modular plant located on a concrete pad with associated enclosures or buildings, surface water drainage and collection;

(b)stocking areas, stocking bays with concrete walls and storage lagoons;

(c)process, reagent, acid waste, water or other liquid storage tanks;

(d)storage silos;

(e)feed hoppers;

(f)screens;

(g)conveyors;

(h)washing units;

(i)separators;

(j)mixing vessels;

(k)sedimentation units;

(l)bioremediation area;

(m)a mobile crusher on a campaign basis;

(n)open concrete lined settlement tanks;

(o)a process control office and staff welfare facilities; and

(p)bunded fuel storage tanks and an electricity generator in an insulated container.

Work No. 3 – the site reception area which will include -

(a)site access and surfaced access road;

(b)storage shed;

(c)laboratory;

(d)canteen, welfare facilities and offices;

(e)car parking area;

(f)weighbridge;

(g)wheel washing facilities;

(h)cess pit, and

(i)bunded fuel storage tanks.

Work No.4 – the conversion of a culverted drain to an open watercourse with associated ecological works.

Work No. 5 – the diversion of an overhead electricity cable.

And for the purposes of or in connection with the construction of Work No.1, Work No. 2 and Work No. 3 further development within the Order limits consisting of—

(a)monitoring bore holes;

(b)leachate storage tanks;

(c)bunded fuel storage tanks;

(d)security cameras;

(e)lighting;

(f)internal site roads; and

(g)hardstanding and bunding.

And for the purposes of or in connection with the construction of any of those works mentioned above further development within the Order limits consisting of—

(a)boundary fencing;

(b)surface water collection ponds;

(c)surface and foul water drainage;

(d)the restoration of the site including the creation of footpaths and tracks for public access and retention of the car parking area; and aftercare.

And for the purpose of or in connection with the construction of any of the works mentioned in this Schedule within the Order limits, any further development which does not give rise to any materially new or materially different environmental effects to those identified in the environmental statement.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources