9.—(1) In the Building (Approved Inspectors etc.) Regulations 2010, Schedule 1 (forms) is amended as follows.
(2) In Form 1 (initial notice)(1), in paragraph 5, after sub-paragraph (c) insert—
“(d)in the case of the erection of a dwelling, or a building that is to contain one or more dwellings—
(i)a statement giving details of any public electronic communications network in relation to which a connection is to be provided,
(ii)if an exemption in regulation 44ZB of the Building Regulations 2010 is proposed to be relied on, a statement giving details in support of the exemption,
(iii)if regulation 44ZC of the Building Regulations 2010 is proposed to be relied on, a statement giving details of the matters mentioned in regulation 44ZC(6)(a) and (b) of those Regulations and, if paragraph RA1(1)(c)(i) or (ii) of Schedule 1 to those Regulations is also proposed to be relied on, evidence of the steps taken to establish whether, and if so where, a distribution point for a gigabit-capable public electronic communications network (as defined by regulation 44C of those Regulations) is likely to be installed, in a location relevant for the purposes of paragraph RA1(1)(c) of that Schedule, within the period of two years beginning with the day on which the notice is given.”.
(3) In Form 2 (amendment notice)(2), in paragraph 4, after sub-paragraph (e) insert—
“(f)in the case of the erection of a dwelling, or a building that is to contain one or more dwellings—
(i)a statement giving details of any public electronic communications network in relation to which a connection is to be provided,
(ii)if an exemption in regulation 44ZB of the Building Regulations 2010 is proposed to be relied on, a statement giving details in support of the exemption, and
(iii)if regulation 44ZC of the Building Regulations 2010 is proposed to be relied on, a statement giving details of the matters mentioned in regulation 44ZC(6)(a) and (b) of those Regulations and, if paragraph RA1(1)(c)(i) or (ii) of Schedule 1 to those Regulations is also proposed to be relied on, evidence of the steps taken to establish whether, and if so where, a distribution point for a gigabit-capable public electronic communications network (as defined by regulation 44C of those Regulations) is likely to be installed, in a location relevant for the purposes of paragraph RA1(1)(c) of that Schedule, within the relevant 2-year period (as defined by paragraph RA1(3) of that Schedule).”.
(4) In Form 4 (combined initial notice and plans certificate)(3), in paragraph 5, after sub-paragraph (c) insert—
“(d)in the case of the erection of a dwelling, or a building that is to contain one or more dwellings—
(i)a statement giving details of any public electronic communications network in relation to which a connection is to be provided,
(ii)if an exemption in regulation 44ZB of the Building Regulations 2010 is proposed to be relied on, a statement giving details in support of the exemption, and
(iii)if regulation 44ZC of the Building Regulations 2010 is proposed to be relied on, a statement giving details of the matters mentioned in regulation 44ZC(6)(a) and (b) of those Regulations and, if paragraph RA1(1)(c)(i) or (ii) of Schedule 1 to those Regulations is also proposed to be relied on, evidence of the steps taken to establish whether, and if so where, a distribution point for a gigabit-capable public electronic communications network (as defined by regulation 44C of those Regulations) is likely to be installed, in a location relevant for the purposes of paragraph RA1(1)(c), within the period of two years beginning with the day on which the notice is given.”.
(5) In Form 9 (public body’s notice)(4), in paragraph 4, after sub-paragraph (c) insert—
“(d)in the case of the erection of a dwelling, or a building that is to contain one or more dwellings—
(i)a statement giving details of any public electronic communications network in relation to which a connection is to be provided,
(ii)if an exemption in regulation 44ZB of the Building Regulations 2010 is proposed to be relied on, a statement giving details in support of the exemption, and
(iii)if regulation 44ZC of the Building Regulations 2010 is proposed to be relied on, a statement giving details of the matters mentioned in regulation 44ZC(6)(a) and (b) of those Regulations and, if paragraph RA1(1)(c)(i) or (ii) of Schedule 1 to those Regulations is also proposed to be relied on, evidence of the steps taken to establish whether, and if so where, a distribution point for a gigabit-capable public electronic communications network (as defined by regulation 44C of those Regulations) is likely to be installed, in a location relevant for the purposes of paragraph RA1(1)(c) of that Schedule, within the period of two years beginning with the day on which the notice is given.”.
(6) In Form 11 (combined public body’s notice and plans certificate)(5), in paragraph 4, after sub-paragraph (c) insert—
“(d)in the case of the erection of a dwelling, or a building that is to contain one or more dwellings—
(i)a statement giving details of any public electronic communications network in relation to which a connection is to be provided,
(ii)if an exemption in regulation 44ZB of the Building Regulations 2010 is proposed to be relied on, a statement giving details in support of the exemption, and
(iii)if regulation 44ZC of the Building Regulations 2010 is proposed to be relied on, a statement giving details of the matters mentioned in regulation 44ZC(6)(a) and (b) of those Regulations and, if paragraph RA1(1)(c)(i) or (ii) of Schedule 1 to those Regulations is also proposed to be relied on, evidence of the steps taken to establish whether, and if so where, it is reasonable to expect that a distribution point for a gigabit-capable public electronic communications network (as defined by regulation 44C of those Regulations) is likely to be installed, in a location relevant for the purposes of paragraph RA1(1)(c) of that Schedule, within the period of two years beginning with the day on which the notice is given.”.
Form 1 was substituted, in relation to buildings in England, by Schedule 2 to S.I. 2015/767 and amended by S.I. 2022/718.
Form 2 was substituted, in relation to buildings in England, by Schedule 2 to S.I. 2015/767, and amended by S.I. 2022/718.
Form 4 was substituted, in relation to buildings in England, by Schedule 2 to S.I. 2015/767, and amended by S.I. 2022/718.
Form 9 was substituted, in relation to buildings in England, by Schedule 2 to S.I. 2015/767.
Form 11 was substituted, in relation to buildings in England, by Schedule 2 to S.I. 2015/767.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: