8.—(1) No phase of the authorised development may commence until written details of all proposed permanent and temporary fences, walls or other means of enclosure of the connection works for that phase have been submitted to and approved by the relevant planning authority as part of the detailed design approval required by requirement 2(1).
(2) For the purposes of requirement 8(1), “commence” includes any site preparation works.
(3) Any construction site must remain securely fenced in accordance with the approved details at all times during construction of the authorised development.
(4) Any temporary fencing must be removed on completion of the phase of construction of the authorised development for which it was used.
(5) Any approved permanent fencing must be completed before completion of the authorised development.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: