Search Legislation

The Drax Power (Generating Stations) Order 2019

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: SCHEDULE 8

 Help about opening options

Alternative versions:

Changes to legislation:

There are currently no known outstanding effects for the The Drax Power (Generating Stations) Order 2019, SCHEDULE 8. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Article 22

SCHEDULE 8E+WLAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED

InterpretationE+W

1.  In this Schedule—

Work Nos. 1C, 1D, 2C and 2D infrastructure” means any works or development comprised within Work Nos. 1C, 1D, 2C and 2D, ancillary apparatus and any other necessary works or development permitted within the area delineated as Work Nos. 1C, 1D, 2C and 2D on the works plans;

Work No. 5 infrastructure” means any works or development comprised within Work No. 5, ancillary apparatus and any other necessary works or development permitted within the area delineated as Work No. 5 on the works plans;

Work No. 6 infrastructure” means any works or development comprised within Work No. 6, ancillary apparatus and any other necessary works or development permitted within the area delineated as Work No. 6 on the works plans;

Work No. 6A access road” means any works or development comprised within Work No. 6A(viii), including any other necessary works or development permitted within the area delineated as Work No. 6A on the works plans;

Work No. 6A infrastructure” means any works or development comprised within Work No. 6A(ii), including any other necessary works or development permitted within the area delineated as Work No. 6A on the works plans;

Work No. 6A planting” means the hard and soft landscaping comprised within Work No. 6A(viii), including any other necessary works or development permitted in respect of such landscaping within the area delineated as Work No. 6A on the works plans;

Work No. 6B infrastructure” means any works or development comprised within Work No. 6B(ii), including any other necessary works or development permitted within the area delineated as Work No. 6B on the works plans;

Work No. 6B planting” means the hard and soft landscaping comprised within Work No. 6B(vii), including any other necessary works or development permitted in respect of such landscaping within the area delineated as Work No. 6B on the works plans;

Work No. 7 infrastructure” means any works or development comprised within Work No. 7, ancillary apparatus and any other necessary works or development permitted within the area delineated as Work No. 7 on the works plans;

Work No. 7A planting” means the hard and soft landscaping comprised within Work No. 7A(vi), including any other necessary works or development permitted in respect of such landscaping within the area delineated as Work No. 7A on the works plans;

Work No. 8 infrastructure” means any works or development comprised within Work No. 8, ancillary apparatus and any other necessary works or development permitted within the area delineated as Work No. 8 on the works plans;

Work No. 8 planting” means the hard and soft landscaping comprised within Work Nos. 8A(vi) and 8B(vi), including any other necessary works or development permitted in respect of such landscaping within the area delineated as Work Nos. 8A and 8B on the works plans;

Work No. 9A(iii) infrastructure” means any works or development comprised within Work No. 9A(iii), ancillary apparatus and any other necessary works or development permitted within the area delineated as Work No. 9A(iii) on the works plans;

Work No. 10C planting” means the hard and soft landscaping comprised within Work No. 10C, including any other necessary works or development permitted in respect of such landscaping within the area delineated as Work No. 10C on the works plans;

Work No. 11 planting” means the retained and enhanced landscaping comprised within Work No. 11, including any other necessary works or development permitted in respect of such landscaping within the area delineated as Work No. 11 on the works plans;

Work No. 13 infrastructure” means any works or development comprised within Work No. 13, ancillary apparatus and including any other necessary works or development permitted within the area delineated as Work No. 13 on the works plans.

Table 10

(1) Number of plot shown on the land plans(2) Rights etc. which may be acquired
5

For and in connection with the Work No. 8 infrastructure, the right to create or improve accesses and a right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work No. 8 infrastructure, together with the right to install, retain, use and maintain the Work No. 8 infrastructure, and a right of support for it, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 8 infrastructure, or interfere with or obstruct access from and to the Work No. 8 infrastructure, including the right to prevent or remove the whole of any building, or fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.

For and in connection with the Work No. 8 planting, the right to create or improve accesses and a right for the undertaker and all persons authorised on its behalf to enter, pass and repass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with improvement, reinstatement, installation, implementation, retention, removal, relocation and maintenance of the Work No. 8 planting, together with the right to retain, maintain, inspect and replant the Work No. 8 planting, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 8 planting, or interfere with or obstruct access from and to the Work No. 8 planting.

For and in connection with the Work No. 13 infrastructure the right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the removal of the Work No. 13 infrastructure.

8a

For and in connection with the Work No. 10C planting, the right to create or improve accesses and a right for the undertaker and all persons authorised on its behalf to enter, pass and repass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with improvement, reinstatement, installation, implementation, retention, removal, relocation and maintenance of the Work No. 10C planting, together with the right to retain, maintain, inspect and replant the Work No. 10C planting, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 10C planting, or interfere with or obstruct access from and to the Work No. 10C planting.

For and in connection with the Work No. 11 planting, the right to create or improve accesses and a right for the undertaker and all persons authorised on its behalf to enter, pass and repass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with improvement, reinstatement, installation, implementation, retention, removal, relocation and maintenance of the Work No. 11 planting, together with the right to retain, maintain, inspect and replant the Work No. 11 planting, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 11 planting, or interfere with or obstruct access from and to the Work No. 11 planting.

9aFor and in connection with the Work Nos. 1C, 1D, 2C and 2D infrastructure the right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work Nos. 1C, 1D, 2C and 2D infrastructure, together with the right to install, retain, use and maintain the Work Nos. 1C, 1D, 2C and 2D infrastructure, and a right of support for it, and the right to the free flow of water, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work Nos. 1C, 1D, 2C and 2D infrastructure, or interfere with or obstruct access from and to the Work Nos. 1C, 1D, 2C and 2D infrastructure, including the right to prevent or remove the whole of any fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.
12

For and in connection with the Work Nos. 1C, 1D, 2C and 2D infrastructure and the Work No. 5 infrastructure the right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work Nos. 1C, 1D, 2C and 2D infrastructure and the Work No. 5 infrastructure, together with the right to install, retain, use and maintain the Work Nos. 1C, 1D, 2C and 2D infrastructure and the Work No. 5 infrastructure, and a right of support for it, and the right to the free flow of water, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work Nos. 1C, 1D, 2C and 2D infrastructure and the Work No. 5 infrastructure, or interfere with or obstruct access from and to the Work Nos. 1C, 1D, 2C and 2D infrastructure and the Work No. 5 infrastructure, including the right to prevent or remove the whole of any fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.

For and in connection with the Work No. 7 infrastructure within a corridor of up to 15m in width, the right to create or improve accesses and a right for the undertaker and all persons authorised on its behalf to enter, pass and repass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work No. 7 infrastructure, together with the right to install, retain, use and maintain the Work No. 7 infrastructure, and a right of support for it, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 7 infrastructure, or interfere with or obstruct access from and to the Work No. 7 infrastructure, including the right to prevent or remove the whole of any building, or fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.

For and in connection with the Work No. 7A planting, the right to create or improve accesses and a right for the undertaker and all persons authorised on its behalf to enter, pass and repass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with improvement, reinstatement, installation, implementation, retention, removal, relocation and maintenance of the Work No. 7A planting, together with the right to protect, retain, maintain, inspect and replant the Work No. 7A planting and existing planting, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 7A planting or existing planting, or interfere with or obstruct access from and to the Work No. 7A planting or existing planting.

14For and in connection with the Work No. 9A(iii) infrastructure within an air-space corridor of up to 10m in width, the right for the undertaker and all persons authorised on its behalf to enter, pass and repass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the installation, use, maintenance and removal of the Work No. 9A(iii) infrastructure, together with the right to install, retain, use, maintain and remove the Work No. 9A(iii) infrastructure, and a right of support for it, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 9A(iii) infrastructure, or interfere with or obstruct access from and to the Work No. 9A(iii) infrastructure.
18, 24, 25, 56

For and in connection with the Work No. 7 infrastructure within a corridor of up to 15m in width, the right to create or improve accesses and a right for the undertaker and all persons authorised on its behalf to enter, pass and repass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work No. 7 infrastructure, together with the right to install, retain, use and maintain the Work No. 7 infrastructure, and a right of support for it, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 7 infrastructure, or interfere with or obstruct access from and to the Work No. 7 infrastructure, including the right to prevent or remove the whole of any building, or fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.

For and in connection with the Work No. 7A planting, the right to create or improve accesses and a right for the undertaker and all persons authorised on its behalf to enter, pass and repass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with improvement, reinstatement, installation, implementation, retention, removal, relocation and maintenance of the Work No. 7A planting, together with the right to protect, retain, maintain, inspect and replant the Work No. 7A planting and existing planting, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 7A planting or existing planting, or interfere with or obstruct access from and to the Work No. 7A planting or existing planting.

27, 27a, 29, 29a, 33, 37, 40, 42, 43, 47, 49, 50, 59For and in connection with the Work No. 7 infrastructure within a corridor of up to 15m in width, the right to create or improve accesses and a right for the undertaker and all persons authorised on its behalf to enter, pass and repass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work No. 7 infrastructure, together with the right to install, retain, use and maintain the Work No. 7 infrastructure, and a right of support for it, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 7 infrastructure, or interfere with or obstruct access from and to the Work No. 7 infrastructure, including the right to prevent or remove the whole of any building, or fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.
58, 61, 67For and in connection with the Work No. 7A planting, the right to create or improve accesses and a right for the undertaker and all persons authorised on its behalf to enter, pass and repass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with improvement, reinstatement, installation, implementation, retention, removal, relocation and maintenance of the Work No. 7A planting, together with the right to protect, retain, maintain, inspect and replant the Work No. 7A planting and existing planting, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 7A planting or existing planting, or interfere with or obstruct access from and to the Work No. 7A planting or existing planting.
65

For and in connection with the Work No. 6A infrastructure, the right to create or improve accesses and a right for the undertaker and all persons authorised on its behalf to enter, pass and repass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work No. 6A infrastructure, together with the right to install, retain, use and maintain the Work No. 6A infrastructure and a right of support for it, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 6A infrastructure, or interfere with or obstruct access from and to the Work No. 6A infrastructure, including the right to prevent or remove the whole of any building, or fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.

For and in connection with the Work No. 6A planting, the right to create or improve accesses and a right for the undertaker and all persons authorised on its behalf to enter, pass and repass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with improvement, reinstatement, installation, implementation, retention, removal, relocation and maintenance of the Work No. 6A planting, together with the right to retain, maintain, inspect and replant the Work No. 6A planting, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 6A planting, or interfere with or obstruct access from and to the Work No. 6A planting.

For and in connection with the Work No. 6A access road, the right to create or improve accesses and a right for the undertaker and all persons authorised on its behalf to enter, pass and repass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work No. 6A access road, together with the right to install, retain, use and maintain the Work No. 6A access road and a right of support for it, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 6A access road, or interfere with or obstruct access from and to the Work No. 6A access road, including the right to prevent or remove the whole of any building, or fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.

66

For and in connection with the Work No. 6B infrastructure, the right to create or improve accesses and a right for the undertaker and all persons authorised on its behalf to enter, pass and repass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work No. 6B infrastructure, together with the right to install, retain, use and maintain the Work No. 6B infrastructure, and a right of support for it, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 6B infrastructure, or interfere with or obstruct access from and to the Work No. 6B infrastructure, including the right to prevent or remove the whole of any building, or fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.

For and in connection with the Work No. 6B planting, the right to create or improve accesses and a right for the undertaker and all persons authorised on its behalf to enter, pass and repass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with improvement, reinstatement, installation, implementation, retention, removal, relocation and maintenance of the Work No. 6B planting, together with the right to retain, maintain, inspect and replant the Work No. 6B planting, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 6B planting, or interfere with or obstruct access from and to the Work No. 6B planting.

Commencement Information

I1Sch. 8 para. 1 in force at 25.10.2019, see art. 1

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources