26.—(1) No part of the authorised development may commence, save for the permitted preliminary works, until a construction site waste management plan for that part has been submitted to and, after consultation with North Yorkshire County Council in its capacity as the relevant waste planning authority, approved by the relevant planning authority.
(2) The plan submitted and approved must be in accordance with the principles set out in chapter 17 and appendix 5A of the environmental statement.
(3) The plan must be implemented as approved unless otherwise agreed with the relevant planning authority.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: