Search Legislation

The North London Heat and Power Generating Station Order 2017

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

2.  Associated development within the meaning of section 115(2) of the 2008 Act in connection with the nationally significant infrastructure project Works No.1a as follows—

(1) Works No. 1b — works required to provide buildings, structures, plant and equipment needed for the operation of the electricity and heat generating station located within the limits of deviation identified on drawing C_0002 Rev 01 of the works plans and as follows—

(a)a wastewater treatment facility;

(b)a water pre-treatment plant;

(c)external stores and workshops;

(d)a fuelling area and fuel storage, vehicle wash, transport offices and staff facilities, toilets, natural gas intake and management compound, and fire control water tanks; and

(e)electrical substations.

(2) Works No. 2 — the construction of a resource recovery facility comprising the following buildings, structures and plant located within the limits of deviation identified on drawing C_0004 Rev 01 of the works plans and as follows—

(a)a recycling and fuel preparation facility;

(b)a reuse and recycling centre;

(c)offices, and staff and visitor welfare facilities;

(d)odour abatement and dust suppression plant and equipment; and

(e)fire control water tanks and pump house and equipment.

(3) Works No. 3 — the construction of a building to provide visitor, community and education facilities, office accommodation and a boat canopy located within the limits of deviation identified on drawing C_0006 Rev 01 of the works plans.

(4) Works No. 4 — utilities and infrastructure works, landscaping, access, security and lighting, and weighbridges located within the limits of deviation identified on drawing C_0008 Rev 01 of the works plans and as follows—

(a)with regard to potable water, waste water, surface water, foul water, raw water, electricity, gas, cctv, telecoms and data—

(i)the diversion, repositioning, decommissioning, removal, replacement, modification or upgrading of existing pipes, cables, systems and associated apparatus;

(ii)the laying or installation of new pipes, cables, systems and associated apparatus; and

(iii)the creation of connections to existing or new pipes, cables, systems and associated apparatus;

(b)the erection of a raw water pumping station;

(c)stabilisation works to the eastern bank of Salmon’s Brook;

(d)the construction of surface water pumps, pipework and attenuation tanks;

(e)landscaping works;

(f)the installation of areas of green roof and brown roof;

(g)the widening of the existing entrance into the Edmonton EcoPark from Advent Way, including modification or replacement of the bridge over Enfield Ditch;

(h)the construction within the Edmonton EcoPark of vehicle and cycle parking, vehicle, cycle and pedestrian routes and weighbridges;

(i)the construction of an access into the Edmonton EcoPark from Lee Park Way, including bridging over Enfield Ditch;

(j)improvements to Lee Park Way including vehicle barriers and the creation of segregated pedestrian and cycle paths or the repositioning of existing pedestrian and cycle paths;

(k)improvements to Deephams Farm Road (including improvements to the existing access into Deephams Farm Road from Ardra Road) and the use of Deephams Farm Road as an access to and from the Edmonton EcoPark;

(l)the resurfacing of Ardra Road (if required);

(m)security, fencing and lighting works and equipment;

(n)the erection of security facilities and equipment and gatehouses within the operational site at access points from Advent Way, Ardra Road and Lee Park Way;

(o)the upgrade and maintenance of the existing bridge over the River Lee Navigation;

(p)the installation of photovoltaic panels at roof level of the electricity and heat generating station and the resource recovery facility;

(q)the modification of kerb lines and pavements within plots 28 and 29;

(r)the creation of a new footpath within plot 21;

(s)the improvement of the existing junction between Meridian Way and Ardra Road; and

(t)the improvement of the existing junction between Advent Way and Lee Park Way.

(5) Works No. 5 — the creation of a temporary laydown area and its temporary use located within the limits of deviation identified on drawing C_0009 Rev 01 of the works plans and as follows—

(a)areas of hardstanding;

(b)the erection of fencing, hoarding or any other means of enclosure;

(c)the erection of security facilities and equipment and gatehouses;

(d)vehicle parking;

(e)office and staff welfare accommodation;

(f)storage, fabrication, laydown area;

(g)foul water storage and pumps and surface water attenuation storage and pumps;

(h)utility works including electricity, water, cctv, telecoms and data;

(i)the creation of vehicular, cycle and pedestrian access from Lee Park Way to the temporary laydown area;

(j)the improvement of the existing junction between Walthamstow Avenue and Lower Hall Lane; and

(k)restoration of the temporary laydown area.

(6) Works No. 6 — site preparation and demolition works within the area located within the limits of deviation identified on drawing C_0010 Rev 01 of the works plans comprising—

(a)the demolition of existing buildings, structures and plant excluding demolition of the energy from waste facility;

(b)the construction of a temporary ash storage building;

(c)the realignment of the exit ramp from the energy from waste facility; and

(d)works to prepare the land shown on drawing C_0010 Rev 01 of the works plans for the construction of Works No. 1a, 1b, 2, 3, 4 and 5.

(7) Works No. 7 — decommissioning, demolition and removal of the energy from waste facility located within the limits of deviation identified on drawing C_0011 Rev 01 of the works plans and demolition and removal of the existing stack, demolition of the existing water pumping station on Ardra Road; and making good.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources