Temporary closure of streets and public rights of way

11.—(1) The undertaker, during and for the purposes of carrying out the authorised development, may temporarily close, alter or divert any street or public right of way and may for any reasonable time—

(a)divert the traffic from the street or public right of way; and

(b)subject to paragraph (3), prevent all persons from passing along the street or public right of way.

(2) Without prejudice to paragraph (1), the undertaker may use any street or public right of way closed under the powers conferred by this article within the Order limits as a temporary working site.

(3) The undertaker must provide reasonable access for pedestrians going to or from premises abutting a street or public right of way affected by the temporary closure, alteration or diversion of a street or public right of way under this article if there would otherwise be no such access.

(4) Without prejudice to the generality of paragraph (1), the undertaker may temporarily close, alter or divert the streets and public rights of way specified in column (2) of Schedule 7 (streets/rights of way to be temporarily closed, altered or diverted) to the extent specified, by reference to the letters and numbers shown on the access and rights of way plans, in column (4) of that Schedule.

(5) The undertaker must not temporarily close, alter or divert—

(a)any street or public right of way specified as mentioned in paragraph (4) without first consulting the street authority; and

(b)any other street or public right of way without the consent of the street authority which may attach reasonable conditions to any consent, but such consent is not to be unreasonably withheld.

(6) If a street authority fails to notify the undertaker of its decision within 42 days of receiving an application for consent under paragraph (5)(b) that street authority is to be deemed to have granted consent.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources