13.—(1) Numbered work 1 must not commence until written details of the surface and foul water drainage system and sustainable drainage systems, including the subsequent maintenance and management of the system for the operation of the authorised development has been submitted to and approved by the relevant planning authority. The surface and foul water drainage system must be substantially in accordance with the illustrative foul and surface water drainage strategy plan.
(2) The surface and foul water drainage system for the authorised development must be constructed in accordance with the approved details.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: