Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):
79.—(1) Where the objective rules and criteria for the exclusion and selection of—
(a)economic operators requesting qualification in a qualification system; or
(b)candidates and tenderers in open, restricted or negotiated procedures, in competitive dialogues or in innovation partnerships,
include requirements relating to the economic and financial capacity of the economic operator, or its technical and professional abilities, the economic operator may, where necessary, rely on the capacities of other entities, regardless of the legal nature of the links which it has with them, subject to the following provisions of this regulation.
(2) With regard to criteria relating to the educational and professional qualifications of the service provider or contractor or those of the undertaking's managerial staff or to relevant professional experience, economic operators may however only rely on the capacities of other entities where the latter will perform the works or services for which these capacities are required.
(3) Where an economic operator wants to rely on the capacities of other entities, it shall prove to the utility that the necessary resources will be available to it, for example by producing a commitment by those entities to that effect.
(4) For the purposes of paragraph (3), an economic operator requesting qualification in a qualification system shall prove that the necessary resources will be available to it throughout the period of validity of the qualification system.
(5) Where, in accordance with regulation 80, utilities have referred to exclusion or selection criteria provided for under the Public Contracts Regulations, utilities shall verify, in accordance with regulation 80(4), whether the other entities on whose capacity the economic operator intends to rely fulfil the relevant selection criteria or whether there are grounds for exclusion, to which the utilities have referred, under regulation 57 of the Public Contracts Regulations and,
(a)the utility shall require that the economic operator replaces an entity in respect of which there are compulsory grounds for exclusion to which the utility has referred; and
(b)the utility may require that the economic operator replaces an entity in respect of which there are non-compulsory grounds for exclusion to which the utility has referred.
(6) Where an economic operator relies on the capacities of other entities with regard to criteria relating to economic and financial standing, the utility may require that the economic operator and those entities be jointly liable for the execution of the contract.
(7) A group of economic operators within the meaning of regulation 37(3) may rely on the capacities of participants in the group or of other entities, and paragraphs (1) to (6) apply in relation to such a group in the same way that they apply in relation to an economic operator.
(8) In the case of works contracts, service contracts and siting or installation operations in the context of a supply contract, utilities may require that certain critical tasks be performed directly by the tenderer itself or, where the tender is submitted by a group of economic operators within the meaning of regulation 37(3), by a participant in that group.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: