Regulation 2(1)
(1) Regulation | (2) Prescribed Period | (3) Prescribed Sum | (4) Payment Date |
---|---|---|---|
4(2) | 10 working days | £65 | the working day on which the budget estimate should have been dispatched |
4(3) | 20 working days | £65 | the working day on which the budget estimate should have been dispatched |
5(2) | 5 working days | £15 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
5(3) | 15 working days | £15 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
6(2) | 25 working days | £65 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
6(3) | 35 working days | £135 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
6(4) | 65 working days | £200 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
7(3) | not applicable | £335 | the working day on which the quotation is found, in accordance with the quotation accuracy scheme, to have been inaccurate or incomplete |
7(4) | not applicable | £670 | the working day on which the quotation is found, in accordance with the quotation accuracy scheme, to have been inaccurate or incomplete |
8(2) | 7 working days | £15 for each working day after the end of the prescribed period up to and including the day on which contact occurs | the working day on which contact occurs |
8(3) | the agreed date | £35 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
9(2) | 7 working days | £65 for each working day after the end of the prescribed period up to and including the day on which contact occurs | the working day on which contact occurs |
9(3) | 10 working days | £135 for each working day after the end of the prescribed period up to and including the day on which contact occurs | the working day on which contact occurs |
9(4) | 15 working days | £200 for each working day after the end of the prescribed period up to and including the day on which contact occurs | the working day on which contact occurs |
9(5) | the agreed date | £25 for each working day after the agreed date up to and including the day on which the works at the premises are commenced | the working day on which the works at the premises are commenced |
9(6) | the agreed date | £135 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
9(7) | the agreed date | £200 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
9(8) | the agreed date | £270 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
9(9) | the agreed date | £135 for each working day after the agreed date up to and including the day on which energisation occurs | the working day on which energisation occurs |
9(10) | the agreed date | £200 for each working day after the agreed date up to and including the day on which energisation occurs | the working day on which energisation occurs |
9(11) | the agreed date | £270 for each working day after the agreed date up to and including the day on which energisation occurs | the working day on which energisation occurs |
10(2) | 2 hours | £65 | the working day after the day on which the emergency attendance should have taken place |
10(3) | 2 calendar days | £15 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed | the working day on which the fault rectification works are completed |
10(4) | 10 working days | £15 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed | the working day on which the fault rectification works are completed |
10(5) | 20 working days | £15 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed | the working day on which the fault rectification works are completed |
10(6) | 25 working days | £15 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed | the working day on which the fault rectification works are completed |
11(2) | 25 working days | £15 for each working day after the end of the prescribed period up to and including the day the quotation is dispatched | the working day on which the quotation is dispatched |
12(2) | the agreed date | £15 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
12(3) | 35 working days | £15 for each working day after the end of the prescribed period up to and including the day on which the works are completed | the working day on which the works are completed |
14(1) | 10 working days | £65 | not applicable |
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: