21.—(1) No later than 6 months after commencement of the authorised development a written scheme detailing operational noise management and attenuation measures, and their ongoing maintenance, must be submitted to the relevant planning authority for its approval.
(2) The authorised development must not be brought into use until, following consultation with the relevant district authorities, the scheme submitted under sub-paragraph (1) has been approved in writing by the relevant planning authority.
(3) The noise attenuation measures detailed in the scheme approved under sub-paragraph (2) must be installed during the course of the construction of the authorised development and the authorised development must be operated afterwards in accordance with the scheme approved under sub-paragraph (2).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: