3.—(1) No part of the authorised development is to commence until a CEMP has been prepared in consultation with the relevant planning authority, and submitted to and approved in writing by the Secretary of State.
(2) The construction of the authorised development must be carried out in accordance with the approved CEMP.
(3) The CEMP must reflect the mitigation measures included in chapters 6 to 15 of the environmental statement.
(4) The CEMP must incorporate the following plans and programmes—
(a)Site Environmental Control Plans as detailed below—
(i)air pollution prevention;
(ii)water pollution prevention;
(iii)light pollution prevention;
(iv)noise, vibration and other nuisances;
(v)natural environment;
(vi)archaeological management; and
(vii)use of local road network;
(b)Soil Management Plan, including—
(i)soil resource plan, including protection of in situ soils, handling and storage codes of practice;
(ii)on site re-use criteria and measures; and
(iii)borrow pit plan;
(c)Site Waste Management Plan, including—
(i)management of excavated material and other waste arising;
(ii)waste minimisation;
(iii)hazardous waste management; and
(iv)material re-use, or disposal;
(d)Materials Management Plan, including—
(i)material classification;
(ii)on site re-use criteria and measures; and
(iii)disposal measures; and
(e)Change Control Process.
(5) Each Site Environmental Control Plan detailed in sub-paragraph (4)(a) must incorporate the following—
(a)responsibilities;
(b)consent requirements;
(c)client requirements;
(d)general control measures;
(e)specific control measures;
(f)monitoring and measurement; and
(g)in the event of an emergency.
(6) The CEMP must require—
(a)adherence to the relevant Environment Agency Pollution Prevention Guidelines PPG1, PPG5, PPG6, PPG21 and PPG22; and
(b)adherence to working hours of 7:30 am to 6:00 pm on Mondays to Fridays and 7:30 am to 1:00 pm on Saturdays, except for—
(i)work associated with the installation of the new rail bridge;
(ii)work associated with the bridge decks for the Town Street and Brocklesby bridges;
(iii)works in the carriageway that due to network constraints cannot be completed during normal working hours; and
(iv)extended working hours in the summer months for the earthworks to take advantage of the weather and daylight.
(7) The CEMP must include measures to ensure that the part of Work No. 28 that is on or to the east of Rosper Road can only be undertaken during the months of April to October inclusive.
(8) The plans and programmes listed in sub-paragraph (4) must include measures to address the event that the authorised development coincides with any other major projects in the area which may impact those matters, following consultation with the relevant planning authority.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: