Individual reports

84.—(1) For every contract or framework agreement covered by this Part, and every time a dynamic purchasing system is established, contracting authorities shall draw up a written report which shall include at least the following:—

(a)the name and address of the contracting authority, the subject-matter and value of the contract, framework agreement or dynamic purchasing system;

(b)where applicable, the results of the qualitative selection and reduction of numbers pursuant to regulations 65 and 66, namely:—

(i)the names of the selected candidates or tenderers and the reasons for their selection;

(ii)the names of the rejected candidates or tenderers and the reasons for their rejection;

(c)the reasons for the rejection of tenders found to be abnormally low;

(d)the name of the successful tenderer and the reasons why its tender was selected and, where known—

(i)the share (if any) of the contract or framework agreement which the successful tenderer intends to subcontract to third parties, and

(ii)the names of the main contractor’s subcontractors (if any);

(e)for competitive procedures with negotiation and competitive dialogues, the circumstances as laid down in regulation 26 which justify the use of those procedures;

(f)for negotiated procedures without prior publication, the circumstances referred to in regulation 32 which justify the use of this procedure;

(g)where applicable, the reasons why the contracting authority has decided not to award a contract or framework agreement or to establish a dynamic purchasing system;

(h)where applicable, the reasons why means of communication other than electronic means have been used for the submission of tenders;

(i)where applicable, conflicts of interests detected and subsequent measures taken.

(2) But such a report is not required in respect of contracts based on framework agreements where these are concluded in accordance with regulation 33(7) or (8)(a).

(3) To the extent that the contract award notice drawn up in accordance with regulation 50 or 75(3) contains the information required in this paragraph, contracting authorities may refer to that notice.

(4) Where the Commission so requests, a contracting authority shall communicate the report, or its main elements, to the Commission.

(5) Where the Cabinet Office so requests, a contracting authority shall communicate the report, or its main elements, to the Cabinet Office or to such other body as the Cabinet Office may direct in connection with any functions which that body exercises for the purposes of Article 83 of the Public Contracts Directive.

Reporting other information required by the Cabinet Office

(6) Contracting authorities shall send to the Cabinet Office a report containing such other information as the Cabinet Office may from time to time request in respect of procurements—

(a)within the scope of this Part, or

(b)which would have been within the scope of this Part if their value had exceeded the relevant threshold mentioned in regulation 5,

for the purpose of enabling the Cabinet Office to provide the Commission with information.

Documentation of progress and decisions

(7) Contracting authorities shall document the progress of all procurement procedures, whether or not they are conducted by electronic means.

(8) To that end, contracting authorities shall ensure that they keep sufficient documentation to justify decisions taken in all stages of the procurement procedure, such as documentation on —

(a)communications with economic operators and internal deliberations,

(b)preparation of the procurement documents,

(c)dialogue or negotiation if any,

(d)selection and award of the contract.

(9) The documentation shall be kept for a period of at least 3 years from the date of award of the contract.

Back to top

Options/Help

Print Options

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources