12.—(1) No part of the authorised development is to commence until a scheme of the lighting to be erected along the link road has been submitted to and approved in writing by the relevant planning authority.
(2) The scheme submitted under sub-paragraph (1) must include details of—
(a)the areas of the link road to be lit;
(b)the position of the lighting columns and their heights and designs, including their luminaires and any shielding that is to be incorporated into the lighting columns;
(c)the extent of the light spread from each column; and
(d)mitigation measures relating to lighting reflecting the proposals in the environmental statement.
(3) The authorised development must be carried out in accordance with the scheme approved under sub-paragraph (1).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: