The Rampion Offshore Wind Farm Order 2014

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: PART 1

 Help about opening options

Alternative versions:

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Rampion Offshore Wind Farm Order 2014. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to Schedule 1 Part 1:

Changes and effects yet to be applied to the whole Instrument associated Parts and Chapters:

Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):

PART 1E+W+SAuthorised development

1.  A nationally significant infrastructure project as defined in sections 14 and 15 of the 2008 Act on the bed of the English Channel approximately 13 km from the Sussex coast, comprising—E+W+S

  • Work No. 1 –

    (a)

    An offshore wind turbine generating station with a gross electrical output capacity of up to 700 MW comprising up to 175 wind turbine generators each fixed to the seabed by one of six foundation types (namely, monopile foundation, tripod foundation, jacket foundation, IBGS foundation, gravity base foundation or suction caisson foundation), fitted with rotating blades and situated within the area hatched red on the works plan and further comprising (b) below;

    (b)

    a network of cables laid underground within the area hatched red on the works plan between the WTGs and Work No. 2, for the transmission of electricity and electronic communications between these different structures and including one or more cable crossings;

    and associated development within the meaning of section 115(2) of the 2008 Act comprising—

  • Work No. 2 – Up to two offshore substations fixed to the seabed by one of three foundation types (namely monopile foundation, gravity base foundation or jacket foundation) and situated within the area hatched red on the works plan;

  • Work No. 3A – A connection or connections between the offshore substations comprising Work No. 2 and between Work No. 2 and Work No. 3B consisting of up to four cables laid underground along routes within the Order limits seaward of MHWS including one or more cable crossings;

In the county of West Sussex, Worthing Borough

  • Work No. 3B – Onshore connection works consisting of up to four circuits and associated telecommunication cables laid underground from mean low water springs east of Worthing under the A259 Brighton Road to Work No. 7;

  • Work No. 4 – A new temporary vehicular access track running in a southwest – northeast direction on the southern side of the A259 Brighton Road from Work No. 3B to join the A259 Brighton Road at the southern side of the junction between the A259 Brighton Road and Western Road, Worthing together with modifications to the junction of the new vehicular temporary access track and the adopted highway at the A259 Brighton Road;

  • Work No. 5 – vehicular access from the A259 Brighton Road to Work No. 6;

  • Work No. 6 – A new temporary construction compound and a temporary access track to Work No. 7;

  • Work No. 7 – Onshore connection works consisting of up to four circuits and associated telecommunication cables with up to four transition pits located within the Brooklands Pleasure Park, with associated cables, connecting Work No. 3B to Work No. 8 together with new temporary horizontal directional drilling compounds;

  • Work No. 8 – Onshore connection works consisting of up to four circuits and associated telecommunication cables laid underground in a generally north-westerly direction through the Brooklands Pleasure Park from Work No. 7 to Work No. 9;

  • Work No. 9 – Onshore connection works consisting of up to four circuits and associated telecommunication cables laid underground in a generally north-westerly direction from Work No. 8 to Work No. 11 together with new temporary horizontal directional drilling compounds;

  • Work No. 10 – A new temporary vehicular access track running in an east-west direction from Work No. 9 to join St. Pauls Avenue together with modifications to the junction of the new temporary vehicular access track and the highway at St. Pauls Avenue;

In the county of West Sussex, District of Adur

  • Work No. 11 – Onshore connection works consisting of up to four circuits and associated telecommunication cables laid underground in a generally north-westerly direction from Work No. 9 to Work No. 12 and passing under the Brighton to Worthing South Coast railway line together with new temporary horizontal directional drilling compounds;

  • Work No. 12 – Onshore connection works consisting of up to four circuits and associated telecommunication cables laid underground in a generally north-westerly direction from Work No. 11 to Work No. 13;

In the county of West Sussex, Worthing Borough

  • Work No. 13 – Onshore connection works consisting of up to four circuits and associated telecommunication cables laid underground in a generally north-westerly direction from Work No. 12 to Work No. 14 and crossing under Upper Brighton Road together with new temporary horizontal directional drilling compounds;

  • Work No. 14 – Onshore connection works consisting of up to four circuits and associated telecommunication cables laid underground in a generally northerly direction from Work No. 13 to Work No. 15 and crossing under the A27 trunk road together with new temporary horizontal directional drilling compounds;

  • Work No. 15 – Onshore connection works consisting of up to four circuits and associated telecommunication cables laid underground in a generally north-westerly direction together with a new temporary horizontal directional drilling exit compound and then in a generally north-easterly direction from Work No. 14 to Work No. 16 and crossing under Lambley’s Lane;

In the county of West Sussex, District of Adur

  • Work No. 16 – Onshore connection works consisting of up to four circuits and associated telecommunication cables laid underground in a generally north-easterly direction from Work No. 15 to Work No. 17 and crossing under Titch Hill;

  • Work No. 17 – Onshore connection works consisting of up to four circuits and associated telecommunication cables laid underground in a generally easterly direction from Work No. 16 to Work No. 18 and crossing under Coombes Road;

  • Work No. 18 – Onshore connection works consisting of up to four circuits and associated telecommunication cables laid underground in a generally north-easterly direction from Work No. 17 to Work No. 19 and passing under the River Adur, the Downs Link and the A283 Steyning Road together with new temporary horizontal directional drilling compounds;

  • Work No. 19 – Onshore connection works consisting of up to four circuits and associated telecommunication cables laid underground in a generally north-easterly direction from Work No. 18 to Work No. 20 together with a new temporary horizontal directional drilling exit compound;

In the county of West Sussex, District of Horsham

  • Work No. 20 – Onshore connection works consisting of up to four circuits and associated telecommunication cables laid underground in a generally north-easterly direction from Work No. 19 to Work No. 21 and crossing under Mill Hill, an unnamed road at Beeding Hill and the South Downs Way;

  • Work No. 21 – Onshore connection works consisting of up to four circuits and associated telecommunication cables laid underground in a generally westerly then easterly direction from Work No. 20 to Work No. 22 and crossing under a Bronze Age cross-dyke at Tottington Mount and Edburton Road together with a new temporary construction compound south of Tottington Manor;

  • Work No. 22 – Onshore connection works consisting of up to four circuits and associated telecommunication cables laid underground in a generally northerly direction from Work No. 21 to Work No. 23 and crossing under an unnamed road, Horn Lane and the A281 Brighton Road;

  • Work No. 23 – Onshore connection works consisting of up to four circuits and associated telecommunication cables laid underground in a generally north-easterly direction from Work No. 22 to Work No. 24 and crossing under the B2116 Henfield Road;

In the county of West Sussex, District of Mid Sussex

  • Work No. 24 – Onshore connection works consisting of up to four circuits and associated telecommunication cables laid underground in a generally northerly direction from Work No. 23 to Work No. 25 crossing under Bob Lane;

  • Work No. 25 – A new onshore substation to the north-east of the existing National Grid Bolney substation;

  • Work No. 26 – Temporary widening of an existing vehicular access track from Bob Lane to Work No. 25 together with upgrades to the existing access track and modifications to the junction of the existing access track and the highway at Bob Lane;

  • Work No. 27 – Landscaping works including planting;

  • Work No. 28 – A new permanent public footpath;

  • Work No. 29 – A new temporary construction compound together with new construction access from Work No. 32 to Work No. 25 and permanent access to Work No. 30 and landscaping works including planting;

  • Work No. 30 – Landscaping works including planting;

  • Work No. 31 – A grid connection consisting of up to four circuits and associated telecommunication cables laid underground from the new onshore substation within Work No. 25 and continuing towards a connection point at the existing National Grid Bolney substation;

  • Work No. 32 – A new construction access running in a southeast – northwest direction from Work No. 29 to join Wineham Lane together with modifications to the junction of the new construction access and the highway at Wineham Lane;

    and in connection with such Work Nos. 1 to 3A and to the extent that they do not otherwise form part of any such work, further associated development comprising such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised project and which fall within the scope of the work assessed by the environmental statement and the deemed marine licences;

    and in connection with such Work Nos. 3B to 32 and to the extent that they do not otherwise form part of any such work, further associated development shown on the plans referred to in the requirements, or approved pursuant to the requirements, including—

    (a)

    ramps, means of access and footpaths;

    (b)

    bunds, embankments, swales, landscaping and boundary treatments;

    (c)

    habitat creation;

    (d)

    jointing bays, manholes, marker posts and other works associated with cable laying;

    (e)

    water supply works, foul drainage provision, surface water management systems and culverting;

    (f)

    construction lay down areas and compounds and their restoration;

    (g)

    such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised project;

    and which fall within the scope of the works assessed by the environmental statement.

Commencement Information

I1Sch. 1 Pt. 1 para. 1 in force at 6.8.2014, see art. 1

2.  The grid coordinates for that part of the authorised development which is seaward of MHWS are specified below—E+W+S

Coordinates for the Order limits seaward of MHWS

PointLatitude (DMS)Longitude (DMS)
150° 41′ 11.35 N000° 21′ 55.86 W
250° 42′ 24.83 N000° 13′ 45.70 W
350° 40′ 39.19 N000° 04′ 26.23 W
450° 39′ 31.72 N000° 01′ 28.06 W
550° 38′ 34.92 N000° 09′ 02.89 W
650° 37′ 08.17 N000° 15′ 42.14 W
750° 38′ 13.35 N000° 16′ 17.09 W
850° 37′ 03.36 N000° 20′ 36.10 W
950° 41′ 23.11 N000° 20′ 37.74 W
1050° 45′ 18.57 N000° 19′ 44.38 W
1150° 48′ 30.64 N000° 20′ 55.63 W
1250° 48′ 46.78 N000° 20′ 10.23 W
1350° 48′ 57.17 N000° 20′ 16.32 W
1450° 49′ 03.58 N000° 19′ 54.02 W
1550° 48′ 55.62 N000° 19′ 44.17 W
1650° 49′ 05.77 N000° 18′ 57.10 W
1750° 45′ 11.46 N000° 14′ 39.33 W
1850° 41′ 42.91 N000° 10′ 03.13 W

Commencement Information

I2Sch. 1 Pt. 1 para. 2 in force at 6.8.2014, see art. 1

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources